WISCONSIN PRELIMINARY NOTICE
Notice to Preserve Construction Lien Rights
Pursuant to Wisconsin Statutes Chapter 779
IMPORTANT NOTICE
WISCONSIN NOTICE REQUIREMENTS:
-
Prime Contractors: Must include lien notice in written contract OR deliver within 10 days of first furnishing (Wis. Stat. § 779.02(2)(a))
-
Subcontractors/Suppliers: Must provide notice within 60 days of first furnishing (Wis. Stat. § 779.02(2)(b))
IMPORTANT EXEMPTIONS: Notice is NOT required for:
- Projects with more than 4 residential units
- Commercial (non-residential) projects
- Owner-occupied properties where prime is also owner
PROJECT TYPE DETERMINATION
Is this notice required?
☐ Residential (1-4 units) - Owner NOT the prime contractor = Notice REQUIRED
☐ Residential (5+ units) = Notice NOT required
☐ Commercial/Non-residential = Notice NOT required
☐ Owner is Prime Contractor = Notice NOT required
SELECT CLAIMANT TYPE
☐ Prime Contractor - 10-day deadline (or include in contract)
☐ Subcontractor/Supplier - 60-day deadline
NOTICE DATE AND TIMING
Date of This Notice: _________________________________
Date Claimant First Furnished Labor/Materials: _________________________________
Claimant Type:
☐ Prime Contractor - 10-day deadline: _________________________________
☐ Subcontractor/Supplier - 60-day deadline: _________________________________
SECTION 1: RECIPIENT INFORMATION
To Property Owner:
Name: _________________________________
Address:
_________________________________
_________________________________
City: _________________ State: WI ZIP: _________
SECTION 2: PROPERTY INFORMATION
Property Address:
_________________________________
_________________________________
City: _________________ County: _________________ ZIP: _________
Legal Description:
_________________________________
_________________________________
Type of Property:
☐ Residential (1-4 family dwelling)
☐ Residential (5+ units) - Notice not required
☐ Commercial - Notice not required
SECTION 3: PRIME CONTRACTOR INFORMATION (if applicable)
Prime Contractor Name: _________________________________
Address:
_________________________________
_________________________________
City: _________________ State: WI ZIP: _________
SECTION 4: CLAIMANT INFORMATION
Claimant Name: _________________________________
Company Name: _________________________________
Address:
_________________________________
_________________________________
City: _________________ State: _____ ZIP: _________
Phone: _________________________ Email: _________________________
Wisconsin Credential No. (if applicable): _________________________________
Claimant Type:
☐ Prime/General Contractor
☐ Subcontractor
☐ Material Supplier
☐ Equipment Rental Company
☐ Laborer
☐ Other: _________________________________
SECTION 5: STATUTORY NOTICE LANGUAGE (REQUIRED)
NOTICE OF LIEN RIGHTS
(Pursuant to Wis. Stat. § 779.02)
AS A MATTER OF RIGHT, THE CONTRACTOR MAY FILE A LIEN FOR ANY AMOUNTS OWED AND UNPAID AFTER THE CONTRACTOR COMPLETES THE WORK OR IS TERMINATED.
As required by Wisconsin law, the following notice is provided:
NOTICE OF LIEN RIGHTS
ATTENTION OWNER: The contractor, subcontractors, or suppliers may file a lien against your property if they are not paid for their labor, services, or materials. You may protect yourself against any such lien by requiring the contractor to furnish to you, before you make payment to the contractor, a signed waiver of lien from each subcontractor or supplier who has filed with you a request for notice of work authorized and a description of the work and materials to be provided under the contract. If you pay the contractor, demand that the contractor give you a lien waiver from each subcontractor and supplier who worked on your project before you make final payment.
CLAIMANT INFORMATION:
Name: _________________________________
Address: _________________________________
_________________________________
Phone: _________________________________
PROPERTY ADDRESS:
_________________________________
_________________________________
DESCRIPTION OF WORK/MATERIALS:
_________________________________
_________________________________
_________________________________
SECTION 6: WHO MUST GIVE THIS NOTICE
Under Wis. Stat. § 779.02, the following must give preliminary notice:
☐ Prime contractors - Include in contract or deliver within 10 days
☐ Subcontractors - Within 60 days of first furnishing
☐ Suppliers - Within 60 days of first furnishing
☐ Vendors - Within 60 days of first furnishing
The following are EXEMPT from notice requirements (Wis. Stat. § 779.02(1)):
☐ Laborers or mechanics employed by prime contractor or subcontractor
☐ Lien claimants who contracted directly with the owner
☐ Projects that are wholly residential with more than 4 units
☐ Projects that are all or part non-residential (commercial)
☐ Owner is the prime contractor
SECTION 7: CLAIMANT'S SIGNATURE
I, the undersigned, declare under penalty of perjury under the laws of the State of Wisconsin that the foregoing information is true and correct.
Signature: _________________________________ Date: _________________
Printed Name: _________________________________
Title: _________________________________
SECTION 8: PROOF OF SERVICE
Service Requirements (Wis. Stat. § 779.02(2))
Notice must be served by:
☐ Personal service
☐ Registered or certified mail
☐ Service in same manner as summons
☐ Any means with written confirmation of delivery
IMPORTANT: Actual receipt of the notice is essential.
Service Documentation
To Owner:
Method of Service: _________________________________
Date Served: _________________________________
Tracking/Receipt Number: _________________________________
Confirmation of Receipt: ☐ Yes ☐ Pending
Certificate of Service
I certify that I served this Notice on the Owner by the method indicated above.
Two (2) signed copies were delivered as required.
Signature: _________________________________ Date: _________________
Printed Name: _________________________________
WISCONSIN PRELIMINARY NOTICE - LEGAL REQUIREMENTS SUMMARY
WHEN NOTICE IS REQUIRED
Notice is required ONLY for:
- Residential projects (1-4 family dwellings)
- Where claimant does NOT have direct contract with owner
- Where owner is NOT the prime contractor
PRIME CONTRACTOR NOTICE (Wis. Stat. § 779.02(2)(a))
Deadline:
- Include in initial written contract, OR
- Deliver within 10 days of first furnishing labor, services, materials, plans, or specifications
Format:
- Must include statutory language from Wis. Stat. § 779.02(2)(a)
SUBCONTRACTOR/SUPPLIER NOTICE (Wis. Stat. § 779.02(2)(b))
Deadline:
- Within 60 days of first furnishing labor, services, materials, plans, or specifications
Format:
- Two signed copies
- Must include required statutory language
SERVICE METHODS
- Personal service
- Registered or certified mail
- Service in manner for summons
- Any delivery with written confirmation
CRITICAL: Actual receipt is essential - notice must be received by owner
SAVINGS CLAUSE (Wis. Stat. § 779.02(3))
If notice is served late but otherwise proper:
- Claimant has lien rights for labor performed AFTER the late notice is actually received
- Burden of proving labor was furnished after notice date is on the claimant
NOTICE OF INTENTION TO FILE LIEN (Wis. Stat. § 779.02(5))
ADDITIONAL REQUIREMENT: Before filing a lien claim, claimant must serve:
- Notice of Intention to File Claim for Lien
- At least 30 days before filing the lien claim
- On owner (and prime contractor if filed by subcontractor/supplier)
ADDITIONAL IMPORTANT DEADLINES
| Action | Deadline | Citation |
|---|---|---|
| Prime Contractor Notice | 10 days from first furnishing (or in contract) | Wis. Stat. § 779.02(2)(a) |
| Subcontractor/Supplier Notice | 60 days from first furnishing | Wis. Stat. § 779.02(2)(b) |
| Notice of Intention to File Lien | 30 days before filing lien | Wis. Stat. § 779.02(5) |
| File Lien Claim | 6 months from last furnishing | Wis. Stat. § 779.06 |
| Enforce Lien (lawsuit) | 2 years from last furnishing | Wis. Stat. § 779.06 |
EXEMPTIONS (Wis. Stat. § 779.02(1))
No notice required:
- Laborers/mechanics employed by prime or sub
- Direct contract with owner
- Residential projects (5+ units)
- Non-residential (commercial) projects
- Owner is prime contractor
IMPORTANT DISCLAIMERS
This form is provided for informational purposes only and does not constitute legal advice. Wisconsin construction lien law requires strict compliance with notice requirements and is deadline-driven.
CONSULT AN ATTORNEY: Before relying on this form, consult with a Wisconsin-licensed attorney familiar with construction lien law.
VERIFY PROJECT TYPE: Ensure you correctly determine if notice is required for your specific project.
MAINTAIN RECORDS: Keep copies of notice, proof of service, and written confirmation of delivery.
Wisconsin Preliminary Notice Template - Version 2026.01
Based on Wisconsin Statutes Chapter 779
Do more with Ezel
This free template is just the beginning. See how Ezel helps legal teams draft, research, and collaborate faster.
AI that drafts while you watch
Tell the AI what you need and watch your document transform in real-time. No more copy-pasting between tools or manually formatting changes.
- Natural language commands: "Add a force majeure clause"
- Context-aware suggestions based on document type
- Real-time streaming shows edits as they happen
- Milestone tracking and version comparison
Research and draft in one conversation
Ask questions, attach documents, and get answers grounded in case law. Link chats to matters so the AI remembers your context.
- Pull statutes, case law, and secondary sources
- Attach and analyze contracts mid-conversation
- Link chats to matters for automatic context
- Your data never trains AI models
Search like you think
Describe your legal question in plain English. Filter by jurisdiction, date, and court level. Read full opinions without leaving Ezel.
- All 50 states plus federal courts
- Natural language queries - no boolean syntax
- Citation analysis and network exploration
- Copy quotes with automatic citation generation
Ready to transform your legal workflow?
Join legal teams using Ezel to draft documents, research case law, and organize matters — all in one workspace.