NEW HAMPSHIRE NOTICE OF CLAIM OF LIEN
(Preliminary Notice for Subcontractors - RSA 447:5-7)
Pursuant to New Hampshire Revised Statutes Annotated Chapter 447
IMPORTANT NOTICE
THIS IS NOT A LIEN. Under New Hampshire law, subcontractors (those who contract with someone other than the property owner) must provide written notice to the owner BEFORE performing labor or furnishing materials in order to claim the same lien rights as a general contractor.
NOTE: General contractors in direct contract with the owner are NOT required to send preliminary notice.
IMPORTANT: Notice may be given AFTER work is performed, but the lien is then limited to the amount due or that may become due to the contractor/agent/subcontractor at that time.
CLAIMANT TYPE
☐ CONTRACTOR (direct contract with owner) - No preliminary notice required
☐ SUBCONTRACTOR (contract with contractor, agent, or subcontractor of owner) - Notice required BEFORE performing labor/furnishing materials (preferred) OR after (with limitations)
NOTICE TIMING
Date of This Notice: _________________________________
Notice Timing:
☐ This notice is being given BEFORE performing labor or furnishing materials (RECOMMENDED)
☐ This notice is being given AFTER labor performed or materials furnished (lien limited to amount then due)
Date Labor/Materials First Furnished (if applicable): _________________________________
SECTION 1: PROPERTY OWNER INFORMATION
Name of Property Owner: _________________________________
OR
Name of Person Having Charge of Property: _________________________________
Address:
_________________________________
_________________________________
City: _________________ State: NH ZIP: _________
SECTION 2: PROPERTY INFORMATION
Property Street Address:
_________________________________
_________________________________
City: _________________ County: _________________ ZIP: _________
Legal Description of Property:
_________________________________
_________________________________
_________________________________
SECTION 3: CLAIMANT INFORMATION
Claimant Name: _________________________________
Claimant Business Name (if different): _________________________________
Claimant Address:
_________________________________
_________________________________
City: _________________ State: _____ ZIP: _________
Phone: _________________________ Email: _________________________
Claimant Classification:
☐ Subcontractor
☐ Material Supplier
☐ Sub-subcontractor
☐ Design Professional (Architect/Engineer)
☐ Laborer
☐ Other: _________________________________
SECTION 4: CONTRACTING PARTY INFORMATION
Name of Agent, Contractor, or Subcontractor Who Hired Claimant:
_________________________________
Address:
_________________________________
_________________________________
City: _________________ State: _____ ZIP: _________
SECTION 5: DESCRIPTION OF WORK OR MATERIALS
General Description of Labor to be Performed or Materials to be Furnished:
_________________________________
_________________________________
_________________________________
_________________________________
Estimated Value of Labor/Materials: $__________________
SECTION 6: NOTICE OF CLAIM OF LIEN (RSA 447:5)
NOTICE TO PROPERTY OWNER
You are hereby notified that the undersigned will furnish or is furnishing labor, professional design services, and/or materials for improvements to your property located at:
_________________________________
The undersigned is performing this work pursuant to a contract with:
_________________________________
Under New Hampshire law (RSA Chapter 447), the undersigned hereby claims a lien on your property for the value of labor performed, professional design services provided, or materials furnished.
CLAIM AMOUNT: $__________________ (or value to be determined)
This notice is given in compliance with RSA 447:5-7.
SECTION 7: 30-DAY ACCOUNT REQUIREMENT (RSA 447:8)
IMPORTANT: Under RSA 447:8, any person giving this notice must, as often as once in 30 days, furnish to the owner or person having charge of the property an account in writing of the labor performed, professional design services provided, or materials furnished during the 30 days.
☐ Claimant acknowledges the 30-day account requirement and agrees to comply.
SECTION 8: SIGNATURE
Signature: _________________________________ Date: _________________
Printed Name: _________________________________
Title: _________________________________
SECTION 9: PROOF OF SERVICE
Service on Property Owner
Method of Service:
☐ Personal delivery
☐ Certified mail, return receipt requested
☐ First-class mail
Date Served/Mailed: _________________________________
Person Served (if personal delivery): _________________________________
Tracking Number (if certified mail): _________________________________
SECTION 10: NOTICE TO CONSTRUCTION LENDER (RSA 447:12-a)
If Construction Mortgage Exists
Within 10 business days of execution of construction mortgage, mortgagor must post on jobsite:
- Name, address, and telephone number of lending institution
Claimant Notice to Lender (Within 15 business days of posting or commencing to furnish - whichever is later):
☐ Notice provided to construction lender
Lender Name: _________________________________
Lender Address:
_________________________________
_________________________________
Date Notice Sent: _________________________________
NOTE: Failure to provide this notice does NOT alone invalidate the lien under RSA 447:2-7.
NEW HAMPSHIRE MECHANICS LIEN - LEGAL REQUIREMENTS SUMMARY
NOTICE REQUIREMENTS
| Who | Required? | Timing | Citation |
|---|---|---|---|
| Contractor (direct contract) | NO | N/A | RSA 447:2 |
| Subcontractor | YES | Before performing work (preferred) | RSA 447:5 |
| Subcontractor (late notice) | Allowed | After work, but lien limited | RSA 447:5 |
KEY DEADLINES
| Action | Deadline | Citation |
|---|---|---|
| Preliminary Notice (Subcontractor) | Before performing labor/furnishing materials | RSA 447:5 |
| 30-Day Account Statements | Every 30 days while work continues | RSA 447:8 |
| Notice to Construction Lender | 15 business days of posting or commencing | RSA 447:12-a |
| Lien Duration | 120 days after services/materials furnished | RSA 447:9 |
| Perfect Lien by Attachment | Within 120-day period through court | RSA 447:9 |
NOTICE CONTENT REQUIREMENTS (RSA 447:5)
The notice must:
- Be in writing
- State that claimant will claim a lien
- Be given before performing labor or furnishing materials (for full protection)
MINIMUM CLAIM AMOUNT
Lien rights exist for claims of $15 or more (RSA 447:5).
30-DAY ACCOUNT REQUIREMENT (RSA 447:8)
After giving preliminary notice, claimant must furnish to owner/person in charge:
- Written account of labor/materials furnished during each 30-day period
- Owner/person in charge must retain sufficient funds to pay such claims
LIEN PRIORITY (RSA 447:7)
The relative priority of mechanics liens is established:
1. In order of their accrual
2. If accruing simultaneously, in order of attachments made to secure them
PERFECTING THE LIEN
In New Hampshire, a lien is perfected by obtaining an "attachment" through the court system, NOT by recording a "notice of contract" as in some other states.
LIEN DURATION
The lien continues for 120 days after services performed or materials furnished, unless payment is made, and takes precedence over all prior claims except liens on account of taxes.
IMPORTANT DISCLAIMERS
This form is provided for informational purposes only and does not constitute legal advice. New Hampshire mechanics lien law has unique requirements, including court attachment for perfection. Consult with a New Hampshire-licensed attorney to ensure compliance with all statutory requirements.
VERIFICATION: Ensure all information is accurate. Timing of notice is critical for subcontractors.
New Hampshire Notice of Claim of Lien Template - Version 2026.01
Based on New Hampshire Revised Statutes Annotated Chapter 447
Do more with Ezel
This free template is just the beginning. See how Ezel helps legal teams draft, research, and collaborate faster.
AI that drafts while you watch
Tell the AI what you need and watch your document transform in real-time. No more copy-pasting between tools or manually formatting changes.
- Natural language commands: "Add a force majeure clause"
- Context-aware suggestions based on document type
- Real-time streaming shows edits as they happen
- Milestone tracking and version comparison
Research and draft in one conversation
Ask questions, attach documents, and get answers grounded in case law. Link chats to matters so the AI remembers your context.
- Pull statutes, case law, and secondary sources
- Attach and analyze contracts mid-conversation
- Link chats to matters for automatic context
- Your data never trains AI models
Search like you think
Describe your legal question in plain English. Filter by jurisdiction, date, and court level. Read full opinions without leaving Ezel.
- All 50 states plus federal courts
- Natural language queries - no boolean syntax
- Citation analysis and network exploration
- Copy quotes with automatic citation generation
Ready to transform your legal workflow?
Join legal teams using Ezel to draft documents, research case law, and organize matters — all in one workspace.