PRACTITIONER NOTES AND INSTRUCTIONS
Overview of Arkansas Mechanics' Lien Waiver Law
Arkansas does not prescribe statutory lien waiver forms. The state does not mandate specific language, formats, or templates for mechanics' lien waivers. Parties have flexibility to draft waiver documents as needed, provided the intent to waive is clearly expressed.
Key Arkansas Lien Law Provisions
| Requirement | Citation | Detail |
|---|---|---|
| Lien Right Established | § 18-44-110 | Any person who furnishes labor, services, material, fixtures, engines, boilers, machinery, or equipment for construction or improvement of real property |
| Notice to Owner (GC) | § 18-44-115 | General contractor must give written notice to owner before filing lien |
| Subcontractor Lien Rights | § 18-44-501 et seq. | Special provisions for residential real property subcontractors |
| Lien Filing Deadline | § 18-44-117 | Lien must be filed within 120 days after the last date labor or materials were furnished |
| Enforcement Deadline | § 18-44-118 | Action to enforce lien must be filed within fifteen (15) months from the filing date of the lien |
| Lien Amount Limitation | § 18-44-110 | Subcontractor liens limited to amount owing from owner to general contractor at time of notice |
Advance Waiver of Lien Rights
Arkansas does not expressly prohibit advance waivers of lien rights by statute. There is no specific statutory provision voiding "no-lien clauses" in construction contracts. However, any waiver must clearly express the intent to waive, and courts will interpret ambiguities against the party seeking to enforce the waiver.
Notarization
Arkansas lien waivers are not required to be notarized. Notarization is not a statutory requirement for the validity of a lien waiver in Arkansas. However, notarization is recommended for evidentiary purposes.
When to Use Each Waiver Form
-
Conditional Waiver on Progress Payment — Use when a progress payment check has been tendered but has not yet cleared. The waiver becomes effective only upon actual receipt and clearance of funds.
-
Unconditional Waiver on Progress Payment — Use after a progress payment has been received and cleared. This is an irrevocable waiver for the amount stated.
-
Conditional Waiver on Final Payment — Use when the final payment check has been tendered but not yet cleared. Full release conditioned on clearance.
-
Unconditional Waiver on Final Payment — Use after final payment has been received and cleared. Full and irrevocable release of all lien rights.
Important Warnings
WARNING: Arkansas distinguishes between liens filed by general contractors (who have a direct contract with the owner) and subcontractors. A subcontractor's lien is limited to the amount owing from the owner to the general contractor at the time of notice.
WARNING: For residential real property, special provisions under Ark. Code Ann. § 18-44-501 et seq. apply to subcontractors. Ensure compliance with applicable residential notice requirements.
WARNING: A lien waiver is not the same as a lien release. If a lien has already been filed, a separate release or satisfaction document must be recorded with the circuit clerk to clear the property record.
FORM 1: CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
(Arkansas — Effective Only Upon Clearance of Payment)
NOTICE: This document waives and releases lien rights only to the extent and through the date stated below, and only upon the condition that payment is actually received and the check clears. This document does not affect lien rights for labor, services, equipment, or materials furnished after the Through Date, nor does it affect lien rights for retainage, pending change orders, or claims not included in this waiver.
Project Information:
| Field | Entry |
|---|---|
| Property Owner | [________________________________] |
| Property Address | [________________________________] |
| Property Legal Description | [________________________________] |
| County | [________________________________] |
| Project Name/Number | [________________________________] |
Claimant Information:
| Field | Entry |
|---|---|
| Claimant Name | [________________________________] |
| Claimant Address | [________________________________] |
| Claimant Phone | [________________________________] |
| Arkansas Contractor License No. | [________________________________] |
| Claimant Role | ☐ General Contractor ☐ Subcontractor ☐ Material Supplier ☐ Laborer ☐ Other: [________________] |
Payment Information:
| Field | Entry |
|---|---|
| Hiring Party / Payor | [________________________________] |
| Check / Payment Reference No. | [________________________________] |
| Amount of Progress Payment | $ [________________________________] |
| Payment Date | [__/__/____] |
| Through Date (labor/materials) | [__/__/____] |
CONDITIONAL WAIVER AND RELEASE
Upon receipt and clearance of payment in the amount of $[________________________________] from [________________________________] (Payor), the undersigned Claimant hereby conditionally waives and releases any and all mechanics' lien rights and materialmen's lien rights arising under Arkansas Code Annotated § 18-44-101 et seq. for labor, services, equipment, or materials furnished to the above-described Property through the Through Date stated above, to the extent of the amount stated.
This waiver and release is expressly conditioned upon actual receipt of payment and clearance of the above-referenced check or instrument of payment. If payment is not received, or if the check or instrument fails to clear for any reason, this waiver and release shall be null and void, and the undersigned shall retain all lien rights as though this document had not been executed.
Exceptions. This waiver and release does NOT cover and the undersigned expressly reserves lien rights for:
☐ Retainage in the amount of $ [________________________________]
☐ Pending change orders, specifically: [________________________________]
☐ Disputed claims in the amount of $ [________________________________]
☐ Labor, services, equipment, or materials furnished after the Through Date
☐ Other: [________________________________]
Claimant Certification. The undersigned certifies that all debts owed to subcontractors, laborers, and material suppliers for work covered by this waiver through the Through Date have been paid or will be timely paid from the progress payment referenced herein.
Signature:
Claimant Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Date Signed: [__/__/____]
FORM 2: UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
(Arkansas — Irrevocable Upon Execution)
NOTICE: This document waives and releases lien rights unconditionally and irrevocably to the extent and through the date stated below. This document is effective immediately upon execution. The undersigned should NOT execute this document unless payment has actually been received and the check has cleared.
Project Information:
| Field | Entry |
|---|---|
| Property Owner | [________________________________] |
| Property Address | [________________________________] |
| Property Legal Description | [________________________________] |
| County | [________________________________] |
| Project Name/Number | [________________________________] |
Claimant Information:
| Field | Entry |
|---|---|
| Claimant Name | [________________________________] |
| Claimant Address | [________________________________] |
| Arkansas Contractor License No. | [________________________________] |
| Claimant Role | ☐ General Contractor ☐ Subcontractor ☐ Material Supplier ☐ Laborer ☐ Other: [________________] |
Payment Information:
| Field | Entry |
|---|---|
| Hiring Party / Payor | [________________________________] |
| Amount of Progress Payment Received | $ [________________________________] |
| Payment Date | [__/__/____] |
| Through Date (labor/materials) | [__/__/____] |
UNCONDITIONAL WAIVER AND RELEASE
The undersigned Claimant hereby unconditionally and irrevocably waives and releases any and all mechanics' lien rights and materialmen's lien rights arising under Arkansas Code Annotated § 18-44-101 et seq. for labor, services, equipment, or materials furnished to the above-described Property through the Through Date stated above, to the extent of the amount of $[________________________________] received.
This waiver and release is unconditional and effective immediately upon execution. It is binding regardless of any subsequent dispute, non-payment of other amounts, or other claim by the undersigned.
Exceptions. This waiver and release does NOT cover and the undersigned expressly reserves lien rights for:
☐ Retainage in the amount of $ [________________________________]
☐ Pending change orders, specifically: [________________________________]
☐ Labor, services, equipment, or materials furnished after the Through Date
☐ Other: [________________________________]
Claimant Certification. The undersigned certifies that payment in the amount stated above has been received in full and that the check or other instrument of payment has cleared. The undersigned further certifies that all debts owed to subcontractors, laborers, and material suppliers for work covered by this waiver through the Through Date have been paid or will be timely paid.
Signature:
Claimant Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Date Signed: [__/__/____]
FORM 3: CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
(Arkansas — Effective Only Upon Clearance of Final Payment)
NOTICE: This document waives and releases ALL lien rights on the project, conditioned upon actual receipt and clearance of the final payment. Upon clearance, this document shall constitute a full and final waiver of all lien rights. If payment is not received or does not clear, this document shall have no effect.
Project Information:
| Field | Entry |
|---|---|
| Property Owner | [________________________________] |
| Property Address | [________________________________] |
| Property Legal Description | [________________________________] |
| County | [________________________________] |
| Project Name/Number | [________________________________] |
Claimant Information:
| Field | Entry |
|---|---|
| Claimant Name | [________________________________] |
| Claimant Address | [________________________________] |
| Arkansas Contractor License No. | [________________________________] |
Payment and Contract Information:
| Field | Entry |
|---|---|
| Hiring Party / Payor | [________________________________] |
| Original Contract Amount | $ [________________________________] |
| Total Approved Change Orders (net) | $ [________________________________] |
| Adjusted Contract Amount | $ [________________________________] |
| Total Previously Received | $ [________________________________] |
| Final Payment Amount | $ [________________________________] |
| Check / Payment Reference No. | [________________________________] |
| Final Payment Date | [__/__/____] |
CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
Upon receipt and clearance of final payment in the amount of $[________________________________] from [________________________________] (Payor), the undersigned Claimant hereby conditionally waives and releases any and all mechanics' lien rights, materialmen's lien rights, bond rights, and any other lien rights arising under Arkansas Code Annotated § 18-44-101 et seq. for all labor, services, equipment, or materials furnished to the above-described Property in connection with the Project.
This waiver and release is conditioned upon actual receipt of payment and clearance of the above-referenced check or instrument of payment. If the final payment is not received, or if the check or instrument fails to clear for any reason, this waiver and release shall be null and void.
This waiver covers ALL work, labor, services, equipment, and materials furnished by the undersigned from commencement through completion, including retainage, change orders, and extras, with the following exceptions:
☐ No exceptions — full and final release of all amounts
☐ Disputed amounts totaling $ [________________________________], described as: [________________________________]
Claimant Certification. The undersigned certifies that upon receipt and clearance of the final payment, all debts owed to subcontractors, sub-subcontractors, laborers, and material suppliers for work on the Project will be paid in full.
Signature:
Claimant Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Date Signed: [__/__/____]
FORM 4: UNCONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
(Arkansas — Irrevocable Full and Final Release)
NOTICE: This document constitutes a full, final, unconditional, and irrevocable waiver and release of ALL lien rights on the project. The undersigned should NOT execute this document unless the final payment has been received in full and the check has cleared. Once signed, this waiver cannot be revoked.
Project Information:
| Field | Entry |
|---|---|
| Property Owner | [________________________________] |
| Property Address | [________________________________] |
| Property Legal Description | [________________________________] |
| County | [________________________________] |
| Project Name/Number | [________________________________] |
Claimant Information:
| Field | Entry |
|---|---|
| Claimant Name | [________________________________] |
| Claimant Address | [________________________________] |
| Arkansas Contractor License No. | [________________________________] |
Payment and Contract Information:
| Field | Entry |
|---|---|
| Hiring Party / Payor | [________________________________] |
| Total Contract Amount (as adjusted) | $ [________________________________] |
| Total Amount Received (including final) | $ [________________________________] |
| Date Final Payment Received | [__/__/____] |
UNCONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
The undersigned Claimant hereby unconditionally and irrevocably waives and releases any and all mechanics' lien rights, materialmen's lien rights, bond rights, and any other lien rights arising under Arkansas Code Annotated § 18-44-101 et seq. for all labor, services, equipment, or materials furnished to the above-described Property in connection with the Project.
This waiver and release is unconditional and irrevocable. It covers ALL work, labor, services, equipment, and materials furnished by the undersigned from commencement through final completion, including retainage, change orders, extras, and any other amounts due or claimed.
The undersigned acknowledges and represents that:
(a) The total contract price, including all approved change orders, was $[________________________________];
(b) The undersigned has received total payments of $[________________________________], constituting payment in full;
(c) No further amounts are due or owing to the undersigned in connection with the Project;
(d) All subcontractors, sub-subcontractors, laborers, and material suppliers engaged by the undersigned have been paid in full or will be paid in full from the final payment; and
(e) The undersigned has no outstanding claims, disputes, or demands against the Property Owner, Hiring Party, or Property.
Signature:
Claimant Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Date Signed: [__/__/____]
NOTARIZATION (OPTIONAL BUT RECOMMENDED)
State of Arkansas
County of [________________________________]
Before me, the undersigned Notary Public, on this [____] day of [________________________________], 20[____], personally appeared [________________________________], known to me (or proved to me on the basis of satisfactory evidence) to be the person whose name is subscribed to the within instrument, and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity.
WITNESS my hand and official seal.
Notary Public Signature: ______________________________
Printed Name: [________________________________]
My Commission Expires: [__/__/____]
[NOTARIAL SEAL]
CERTIFICATE OF DELIVERY
I hereby certify that a true and correct copy of the foregoing Mechanics' Lien Waiver and Release was delivered to:
| Recipient | Method | Date |
|---|---|---|
| [________________________________] | ☐ Personal Delivery ☐ Certified Mail ☐ Email | [__/__/____] |
| [________________________________] | ☐ Personal Delivery ☐ Certified Mail ☐ Email | [__/__/____] |
| [________________________________] | ☐ Personal Delivery ☐ Certified Mail ☐ Email | [__/__/____] |
Delivered by: ______________________________
Date: [__/__/____]
SOURCES AND REFERENCES
- Arkansas Code Annotated § 18-44-101 et seq. (Mechanics' and Materialmen's Liens)
- Arkansas Code Annotated § 18-44-501 et seq. (Residential Real Property Subcontractors)
- Arkansas Rules of Civil Procedure
- Arkansas Secretary of State — Notary Division
About This Template
Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.
Important Notice
This template is provided for informational purposes. It is not legal advice. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.
Last updated: March 2026
Get your Mechanics' Lien Waiver and Release, done and ready to use
Fill it in for your situation, adjust it for your state, and download the finished Word and PDF. Let the AI do it in about 5 minutes, or finish it yourself in the editor. Drafting this from scratch takes hours. Finish yours in about 5 minutes for $49, one time.