Federal agency decisions, searchable in plain English.

Workplace-safety cases from the Occupational Safety and Health Review Commission (OSHRC) and mine-safety cases from the Federal Mine Safety and Health Review Commission (FMSHRC), each with a plain-English summary, the standards it cites, and whether it counts as precedent. More agencies are coming.

5,593 decisions and counting · Latest decision July 17, 2026
5,593 decisions

No decisions match these filters

Try a different search term or clear the filters.

ALJ

Andrew Electric Company

Unsecured breaker-box key led to $6,900 in penalties

An Andrew Electric electrician was electrocuted while installing fluorescent light fixtures near an energized junction box at a Georgia dealership remodeling project. The judge found that the company's safety program lacked adequate electrical-safety rules and that the electrician did not receive…

February 25, 2009 ·Stephen J. Simko, Jr.
Citations affirmed
ALJ

WCI Steel, Inc.

Crane runway-support inspection violation drew a $2,000 penalty

A 40-ton overhead crane collapsed at WCI Steel's Ohio plant while moving steel slabs, but no one was injured. OSHA cited WCI for failing to inspect the crane's runway support structure, maintaining an improperly set hoist limit switch, and overloading the crane. The judge held that a complete…

February 23, 2009 ·Ken S. Welsch
Mixed result
ALJ

CPM Constructors

Flagger-sign citation failed under the incorporated traffic-control rules

CPM Constructors performed paving work in a busy pedestrian and retail area in Freeport, Maine. After moving its crew and flagger to another portion of the work zone, CPM left a Flagger Ahead sign about four-tenths of a mile from the remaining flagger for approximately 45 minutes. OSHA cited the…

February 23, 2009 ·G. Marvin Bober
Citations vacated
ALJ

FM Home Improvement, Inc.

Roofers were employees despite contractor documents

OSHA found seven roofers working without fall protection on a steep residential roof approximately 31 feet above the ground. FM Home Improvement did not dispute the unsafe condition, but argued that the workers belonged to an independent subcontractor and were not its employees. Applying the…

February 20, 2009 ·Dennis L. Phillips
Citations affirmed
ALJ

The Samuels Group, Inc.

Missing scaffold top rail resulted in a $1,000 penalty

The Samuels Group used a scaffold for masonry work approximately 60 feet above the ground. Its cross-bracing was about 32 inches high, which could not substitute for the required top rail, and stacked masonry blocks were neither high nor stable enough to serve as equivalent guarding. The judge…

February 13, 2009 ·James R. Rucker
Modified
COMM

United Parcel Service, Inc.

Affected-employee objections sent settlement issues back to the judge

UPS sought Commission review after an administrative law judge affirmed a serious citation with eight instances and assessed a $4,400 penalty. While review was pending, UPS and the Secretary negotiated a corporate-wide settlement, and affected employee Samuel Bucalo filed objections and several…

February 2, 2009
Remanded
ALJ

A. L. Grading Contractors, Inc.

Unsafe excavation and untrained flagger drew $25,500 in penalties

OSHA found an untrained employee directing traffic and two workers in a 9.2-foot excavation without cave-in protection or a safe means of egress at an Atlanta-area shopping-center project. The judge rejected the employee-misconduct defense to the training item because the company did not establish…

January 23, 2009 ·Ken S. Welsch
Modified
ALJ

Davis H. Elliot Construction Company, Inc.

Reenergization failures led to $11,300 in penalties

Davis H. Elliot rebuilt an Ohio electric distribution system while existing lines remained in service. After three workers failed to report a changed assignment, the foreman relied on an incomplete all-clear and ordered a line energized while one worker was still on a pole, causing his…

January 20, 2009 ·Stephen J. Simko, Jr.
Mixed result
ALJ

Kandey Company, Inc.

Cave-in violation reduced from willful to serious

Kandey employees worked in an excavation to connect a new building to a water main in Clarence, New York. The judge found that a portable ladder used for access did not extend three feet above the landing and that the excavation exceeded five feet, was not entirely stable rock, and lacked cave-in…

January 8, 2009 ·G. Marvin Bober
Modified
ALJ

Kone, Inc.

Fall protection was required on stationary elevator car tops

A Kone apprentice technician was found dead at the bottom of an elevator shaft after being assigned to clean and paint the tops of two elevator cars. The judge found that working on a stationary car top exposed the technician to a 30-foot fall through openings at the back and side, and that a…

January 8, 2009 ·Ken S. Welsch
Mixed result
ALJ

Standard Concrete Products, Inc.

Rotten dunnage was not reasonably discoverable before girder failure

Standard Concrete loaded an 86-ton precast bridge girder onto a barge when a timber supporting its pedestal failed, causing the girder to crack and strike an employee who died from his injuries. The judge held that the longshoring standard applied because the girder had already been landed on the…

December 26, 2008 ·Nancy J. Spies
Mixed result
ALJ

Guamcell Communications

Supervisor's parapet shortcut was unpreventable misconduct

An acting Guamcell supervisor stood without fall protection on the parapet of a ten-story building while adjusting a cellular antenna. Guamcell admitted the standard applied, the supervisor violated it, and a fall could cause death or serious injury. The judge found that the company nevertheless…

December 26, 2008 ·Nancy J. Spies
Citations vacated
ALJ

Stark Excavation, Inc.

Documented safety program proved supervisory misconduct defense

A Stark Excavation superintendent and two laborers stripped bridge forms without fall protection while exposed to a 14-foot, 10-inch drop to rocks below. The company did not dispute the unsafe condition but argued that the supervisor's lapse during a 10-to-15-minute task was unforeseeable…

December 22, 2008 ·James R. Rucker
Citations vacated
COMM

Beverly Healthcare-Hillview

Bloodborne-pathogen follow-up items affirmed after court remand

The Third Circuit vacated an earlier Commission decision that had thrown out two bloodborne-pathogens citation items against Beverly Healthcare-Hillview. The court determined that the employer had fair notice of the Secretary's interpretation of the cited post-exposure evaluation and follow-up…

December 3, 2008
Citations affirmed
COMM

Ernie's Tree Service

Commission approved settlement after directing review

Ernie's Tree Service petitioned for Commission review of the administrative law judge's disposition, and the Commission directed the case for review and requested briefing. The parties then signed a stipulation and settlement agreement that the Secretary submitted to the Commission. After reviewing…

December 2, 2008
Settled
COMM

A. G. Mazzocchi, Inc.

Altered blood-lead report supported willful violations and $105,000 in penalties

A. G. Mazzocchi employees torch-cut lead-painted steel while demolishing a large crane at the Philadelphia Navy Yard. The Commission held that the lead-in-construction standard's high-risk-task presumption and monitoring evidence established that the main torch-cutter was covered by…

November 17, 2008
Citations affirmed
COMM

WR Exterior Design Construction, Inc.

Late-answer dismissal set aside for further inquiry

An administrative law judge dismissed WR Exterior Design Construction's notice of contest after the company failed to answer the Secretary's complaint, affirming citations and $19,600 in proposed penalties. The Commission found that the pro se company apparently never received the show-cause order…

November 4, 2008
Remanded
COMM

The Metropolitan Museum of Art

Employee letter required review of possible party status

OSHA cited the Metropolitan Museum of Art for six violations with $7,500 in proposed penalties, and the Secretary and museum later submitted a settlement reducing the total penalty to $3,700. An affected employee had earlier sent a letter asking that his materials be considered and raising…

October 20, 2008
Remanded
COMM

StarTran, Inc.

Court's partial remand returned recordkeeping case for further proceedings

The Fifth Circuit reviewed the Commission's earlier decision affirming a StarTran citation under OSHA's recordkeeping-access rule. The court affirmed the Commission in part and remanded the case in part in an unpublished opinion. After receiving the court's mandate, the Commission remanded the…

October 10, 2008
Remanded
ALJ

Masonry Arts, Inc.

Scaffold planking, access, and repeat guardrail items totaled $12,500

Masonry Arts employees performed block repair work from a scaffold platform approximately 12.5 feet above the ground at a new Florida high school gymnasium. The judge found a five-inch gap between planks, no safe ladder access, and no guardrail or other fall protection on the platform. He rejected…

September 29, 2008 ·Ken S. Welsch
Mixed result
ALJ

Sanderson Farms, Inc.

Unstable freezer pallet storage resulted in a $6,300 penalty

Sanderson Farms stored 2,200-to-2,500-pound pallets of frozen chicken on an aging freezer rack system with frequently damaged legs and little margin for placement error. A maintenance employee died from smoke inhalation and burns after beginning to cut a damaged rack leg while loaded pallets…

September 24, 2008 ·Nancy J. Spies
Mixed result
COMM

FABI Construction Company, Inc., and PRO Management Group

Court required a factual basis for penalty increase

The D.C. Circuit reviewed the administrative law judge's decision after it became a final Commission order without discretionary review. The court granted review of the penalty for a concrete-formwork violation and found that the judge increased the Secretary's proposed $2,500 penalty to $7,000…

September 23, 2008
Remanded
COMM

Elan Lawn and Landscape Service, Inc.

One-day-late contest required an evidentiary record

Elan Lawn filed its notice of contest one day after the deadline calculated from a disputed certified-mail receipt, and the judge denied relief without a hearing. The Commission noted that the Secretary's dismissal request did not comply with the rule requiring a separate motion and consultation…

September 8, 2008
Remanded
ALJ

Wynnewood Refining Company

Delayed flare-line replacement was willful and drew a $63,000 penalty

Wynnewood Refining Company operated an Oklahoma petroleum refinery that used hydrofluoric acid in its alkylation unit. OSHA alleged that the company violated the process safety management standard by failing to correct deficiencies in the unit's flare line before further use or in a safe and timely…

September 8, 2008 ·Covette Rooney
Citations affirmed
COMM

PSP Monotech Industries

Inconsistent suspended-load training defeated the misconduct defense

PSP Monotech Industries operated a sheet-metal fabrication plant where employees used an overhead floor crane to move large panels. A 3,700-pound panel fell from a clamp, killing one employee and seriously injuring another. The Secretary cited PSP under the general duty clause for failing to keep…

August 14, 2008
Citations affirmed
ALJ

Pospiech Contracting, Inc.

Unprotected trench citation affirmed with a $5,000 penalty

Pospiech Contracting installed underground utilities at a Florida construction project. OSHA found employees had entered a vertical-sided Type C soil excavation measured at 6 to 6½ feet deep without a protective system. The company argued that the excavation was less than 5 feet deep, that it…

August 11, 2008 ·Ken S. Welsch
Modified
ALJ

Prime Roofing Corporation

Deficient roof warning lines led to a repeat citation and $7,500 penalty

Prime Roofing Corporation provided warning lines while workers removed roof ballast in preparation for replacing a low-slope roof about 20 feet above the ground. The warning lines ran down the center of the roof rather than at least 6 feet from the exposed edges, and workers were observed near the…

July 18, 2008 ·Covette Rooney
Modified
COMM

KS Energy Services, Inc.

Inadequate road-work warnings supported a serious citation

KS Energy Services installed a natural gas pipeline in a traffic-control zone along a Wisconsin county road with a 55 mph speed limit. The Commission found that the company failed to provide advance warning conveying highway conditions and how motorists should move through the work zone, as…

July 14, 2008
Citations affirmed
ALJ

Mustang Engineering Holdings, Inc.

Missing trench exit affirmed while cave-in item was vacated

Mustang Engineering employees entered a trench to survey a newly installed pipe. OSHA cited the company because the trench lacked a safe means of egress and was not sloped enough for its Class B soil. The judge found that the missing ladder or other exit was obvious to Mustang's foreman, so the…

July 7, 2008 ·James R. Rucker
Mixed result
ALJ

Burch Construction, Inc.

Climbing a scaffold guardrail led to a serious access citation

Burch Construction employees worked from a scaffold at a military facility in San Diego. An employee climbed between the scaffold and roof by stepping on a scaffold guardrail instead of using compliant access, exposing him to a potential 25-foot fall. The judge found the conduct foreseeable and…

May 19, 2008 ·Benjamin R. Loye
Citations affirmed
COMM

J.C. Watson Company

Onion packing operations were subject to general-industry standards

J.C. Watson Company grew onions and operated an Idaho facility that cleaned, sorted, graded, packaged, and prepared them for shipment. After an employee's arm was caught under a moving conveyor, OSHA cited the company under numerous general-industry standards. Watson argued that its packing work…

May 6, 2008
Citations affirmed
ALJ

SSA Cooper, LLC

Lashing rods across a vessel catwalk created a serious trip hazard

SSA Cooper performed stevedoring operations aboard a cargo container vessel near Savannah, Georgia. Longshoremen left heavy lashing rods across a 22-inch-wide catwalk while an SSA Cooper foreman repeatedly walked the area to check container placements. The judge found the catwalk was an active work…

May 5, 2008 ·Ken S. Welsch
Modified
ALJ

B&N&K Restoration Co., Inc.

Unsecured and unmarked skylight cover led to $3,000 in penalties

B&N&K Restoration served as a prime contractor on a school addition and placed two overlapping steel sheets over a skylight opening. The sheets were not adequately secured or marked, and a welder for another contractor mistook them for material intended to cover a nearby elevator shaft. When he…

May 5, 2008 ·Dennis L. Phillips
Citations affirmed
COMM

Cagle's, Inc.

Waste trailer was a confined space despite its intended use

Cagle's used a trailer to hold carbon dioxide-treated waste breading at its Alabama poultry plant. Two employees died of asphyxiation after entering the trailer, and OSHA cited the company for failing to inform employees of the permit-required confined space. After an Eleventh Circuit remand, the…

April 11, 2008
Citations affirmed
ALJ

D’Allessandro Corporation

Unprotected 5½-foot trench led to a serious citation

D’Allessandro Corporation employees entered a trench in South Boston to cut an existing pipe and install a fitting. OSHA measured the vertical-sided trench at 5½ feet deep where the employees were working, and the Type C soil was adjacent to a heavily traveled road. The company disputed the…

April 9, 2008 ·Irving Sommer
Citations affirmed
ALJ

Fern Valley Excavating, Inc.

All items vacated because the company was not the employer

Fern Valley Excavating was engaged in excavation contracting and landscaping. OSHA investigated an accident at an Ohio jobsite, and the threshold issue was whether Fern Valley employed the workers at the site on the accident date. The judge found that it did not. All four citation items were…

April 7, 2008 ·Stephen J. Simko, Jr.
Citations vacated
COMM

Martin Construction, Inc.

EAJA filing period began after the judicial-review window closed

Martin Construction prevailed when an administrative law judge vacated six excavation citation items. The company filed an Equal Access to Justice Act fee application 63 days after the merits decision became a final Commission order, and the judge dismissed it as untimely because neither party had…

January 25, 2008
Remanded
ALJ

Prime Roofing Corporation

Late amendment denied and repeat fall citation remained vacated

OSHA cited Prime Roofing under the general unprotected-edge fall standard after observing an employee working on a parapet wall about 22 feet above the ground. The judge initially found the employee was performing roofing work governed instead by the low-slope-roof standard and vacated the…

December 26, 2007 ·Covette Rooney
Citations vacated
ALJ

Standard Building Company, Inc., and Standard Systems, Inc.

Three items affirmed against one company and all items vacated against the other

Standard Building managed a restaurant renovation, and Standard Systems was identified as a related stucco contractor. The judge found that a subcontractor owner acted in part as Standard Building's site superintendent but lacked scaffold and powered-industrial-truck safety training. Standard…

December 20, 2007 ·Ken S. Welsch
Mixed result
COMM

MetWest, Inc.

Reusing blood-tube holders violated the contaminated-needle rule

MetWest used reusable blood-tube holders whose push-button mechanism let phlebotomists detach contaminated needles after drawing blood. OSHA cited the company under the bloodborne-pathogens rule that generally prohibits removing contaminated needles. The Commission held that the rule permits…

December 17, 2007
Citations affirmed
COMM

Contour Erection & Siding Systems, Inc.

Old building and visible debris put contractor on notice of asbestos

Contour employees cut, shoveled, and swept ceiling material while shoring a partially collapsed roof in a building constructed in 1960. OSHA cited 14 serious violations because the company provided none of the protections required for Class I asbestos work. The Commission found constructive…

December 13, 2007
Modified
COMM

Trinity Industries, Inc.

Asbestos violations remanded for a serious-violation penalty

Trinity hired a contractor to repair a furnace in a pre-1980 facility without first determining whether asbestos was present or warning the contractor about asbestos-containing material. The ALJ affirmed two asbestos hazard-communication violations but classified them as non-serious and assessed no…

December 5, 2007
Remanded
COMM

General Motors Corp., CPCG Oklahoma City Plant

Widespread lockout failures produced serious and willful violations

OSHA issued 57 lockout/tagout citation items after a millwright was killed when a motor rail conveyor activated during servicing work at General Motors' Oklahoma City plant. The Commission found that GM did not adequately implement or enforce its energy-control program, conduct the required annual…

December 4, 2007
Mixed result
ALJ

Africo Manufacturing, Inc.

Missing scissor-lift guardrails exposed workers to a 20-foot fall

Two Africo employees installed sprinkler piping from a scissor lift about 20 feet above a concrete floor with guardrails missing from one side and one end. The ALJ credited the OSHA officers' testimony and rejected the company president's claim that the employees had switched lifts without his…

November 23, 2007 ·Covette Rooney
Citations affirmed
ALJ

Huron Real Estate Associates, LLC

Exit-route obstruction affirmed, lockout item vacated

A condensate-induced water hammer ruptured a steam-system valve at Huron's facility, killing one worker and seriously injuring another. The ALJ vacated OSHA's lockout/tagout item because the cited release-from-lockout provision required replacement of parts removed during servicing and cleanup of…

November 23, 2007 ·G. Marvin Bober
Mixed result
COMM

Thomas Industrial Coatings, Inc.

Water cooler was inadequate for washing lead from workers' hands

Thomas sent a two-person crew to remove lead paint from a bridge while initial air-monitoring results were still pending. The Commission held that the lead standard's interim protections applied during that period, but its overlapping general protections did not yet apply. A water cooler and…

November 1, 2007
Mixed result
COMM

Prime Roofing Corporation

Amendment request returned to the judge for a ruling

The ALJ vacated a repeat fall-protection citation against Prime Roofing. Before the decision was docketed, the Secretary moved to amend the complaint to allege a different fall-protection provision in the alternative. The judge received the motion only one day before docketing and did not rule on…

October 31, 2007
Remanded
ALJ

Griffin Contracting, Inc.

One unprotected excavation wall was enough to violate the cave-in rule

Griffin employees worked in a six-foot-deep utility excavation where one wall was near vertical and lacked shoring, benching, or an adequate slope. OSHA's laboratory confirmed that the fissured soil was Type B, and an employee was observed within 18 inches of the unprotected wall. The ALJ rejected…

October 24, 2007 ·Ken S. Welsch
Modified
ALJ

St. Lawrence Food Corp., dba Primo Foods

Most dairy-plant health and safety citations affirmed

OSHA conducted health and safety inspections at Primo Foods, a kosher dairy, and cited hazards involving ammonia refrigeration, respirators, confined spaces, chemical training, noise, machine guarding, electrical work, lockout/tagout, powered industrial trucks, and recordkeeping. The ALJ found that…

October 15, 2007 ·G. Marvin Bober
Mixed result
ALJ

Harry C. Crooker & Sons, Inc.

Excavator had to maintain clearance from an energized service line

A foreman operated an excavator with its boom six to seven feet from an energized 240-volt service drop while performing street reconstruction work. The applicable construction standard required at least ten feet of clearance. The ALJ held that the general-industry electrical rule did not displace…

October 5, 2007 ·Covette Rooney
Citations affirmed
ALJ

J.E. Amorello, Inc.

Blocked ramp and missing cave-in protection led to two trench violations

Two employees worked in a trench that OSHA measured at 5 feet 4 inches deep. The ALJ found that a backhoe blocked access to the available ramp, leaving no safe means of egress, and that the trench lacked required cave-in protection. He credited OSHA's testimony over the employer's conflicting…

October 1, 2007 ·G. Marvin Bober
Citations affirmed
COMM

Cagle's Inc.

Confined-space issue remanded after court review

Two Cagle's employees died from an oxygen-deficient atmosphere caused by carbon dioxide inside a poultry plant's waste-breading trailer. The Commission had previously vacated a citation alleging that the company failed to inform employees about a permit-required confined space. The Eleventh Circuit…

September 28, 2007
Remanded
COMM

Otis Elevator Company

Fatal car-sling incident did not establish employer knowledge

An Otis employee died after riding on an elevator car sling that fell about 60 feet down a shaft while he removed rail-alignment clips. The Commission found that a falling load presented a recognized hazard, but the record did not establish employer knowledge of the employee's conduct. Otis had a…

September 27, 2007
Citations vacated
ALJ

C.D. Smith Construction

Unsupported plywood was not an intended work surface

A C.D. Smith employee suffered serious injuries after falling into a stairwell where unsupported plywood remained from partially dismantled concrete formwork. The plywood was behind a guardrail and danger tape, and the employee's assigned task could be performed directly from the vertical formwork…

September 21, 2007 ·Benjamin R. Loye
Citations vacated
COMM

Aluminum & Vinyl Products, Inc.

Undecided citation item returned to the judge

Aluminum & Vinyl Products contested one item from OSHA's citations and entered an informal settlement covering all other items. The ALJ approved the settlement but did not dispose of the still-contested item. The Commission directed review on its own motion. It remanded the case for the judge to…

August 30, 2007
Remanded
COMM

Saw Pipes USA, Inc.

Willful recordkeeping penalties remanded after court review

The ALJ affirmed 59 willful violations for failing to properly record occupational injuries and illnesses at Saw Pipes' steel-pipe facility. He grouped the separately cited violations and assessed one $70,000 penalty. The Fifth Circuit held that this grouping produced a penalty below the statutory…

August 16, 2007
Remanded
COMM

Jindal United Steel Corp.

Recordkeeping penalties remanded after court review

The ALJ affirmed 110 violations for failing to properly record occupational injuries and illnesses at Jindal's steel facility. He treated 82 violations as willful and 28 as other-than-serious, but grouped the willful items into a single $70,000 penalty and assessed $7,000 for the remaining items…

August 16, 2007
Remanded
ALJ

New Blue Shield Construction Inc.

Six-month filing delay was not excusable neglect

OSHA inspected a New Blue Shield Construction work site in the Bronx and issued a citation on August 8, 2006. The company did not file a notice of contest by the 15-working-day deadline, then waited nearly six months after OSHA explained the late-contest procedure before writing to the Commission…

August 10, 2007 ·Irving Sommer
Procedural
ALJ

Praxair Distribution, Inc.

Liftgate citation vacated for lack of employer knowledge

Praxair Distribution supplied cylinder gases to customers and used delivery trucks equipped with hydraulic liftgates. A driver was killed when a liftgate suddenly fell while he was making a delivery at a Veterans' Administration medical center in Cleveland. OSHA cited Praxair under the general duty…

August 10, 2007 ·Stephen J. Simko, Jr.
Citations vacated
ALJ

J. B. Coxwell Contracting, Inc.

Two excavation violations affirmed and two vacated

J. B. Coxwell Contracting was building an underground concrete junction box for a highway storm drain system in Florida. OSHA cited the company for four excavation violations after employees worked in an excavation about 6 feet 8 inches deep. The judge affirmed a serious violation because the…

August 6, 2007 ·Ken S. Welsch
Mixed result

What these documents are

  • Commission decisions: Rulings by the Occupational Safety and Health Review Commission itself, the highest level of agency review. These are citable as Commission precedent, though a decision may have been appealed to a U.S. Court of Appeals after issuance.
  • ALJ decisions: Rulings by OSHRC Administrative Law Judges after a hearing. When no Commissioner directs review, an ALJ decision becomes a final order under 29 U.S.C. § 661(j): it binds the parties in that case but is not binding precedent in other cases.
  • Why finality matters: Every page here says which kind of decision you are reading, so you know whether it is precedent you can cite or a final order that only shows how one judge ruled on one set of facts.
  • Where they come from: Every page links the official OSHRC public release, and the full text on the page is that release. The plain-English summaries are written by Ezel.