CERTIFICATE OF MECHANIC'S LIEN

Connecticut — Conn. Gen. Stat. § 49-34

Use gate: Section 49-34 makes timely recording and service conditions of lien validity. Confirm eligibility, claimant status, notice duties, the lienable amount, and town recording practice with Connecticut counsel before signing or filing.

1. Eligibility and Deadline Check

Under § 49-33, the claimant must have a claim of more than $10 for qualifying materials furnished or services rendered by agreement with or consent of the owner or an authorized person.

Check Entry
Claimant first performed services or furnished materials [__/__/____]
Claimant ceased performing services or furnishing materials [__/__/____]
Final day of § 49-34 ninety-day recording period [__/__/____]
Amount justly due, as nearly as ascertainable $[________________]

☐ Property, improvement, and claimant's materials/services fall within § 49-33.

☐ Claim exceeds $10 and is for qualifying materials or services.

☐ Owner agreement/consent or authorized-person basis confirmed.

☐ Amount has been tested against §§ 49-33 and 49-36, including subcontractor and aggregate limits and the effect of good-faith owner payments.

Section 49-35 Notice-of-Intent Status

☐ Claimant is the original contractor and is exempt from § 49-35 notice.

☐ Claimant is a subcontractor whose written contract with the original contractor was assented to in writing by the other party to the original contract and is exempt.

☐ Claimant is not exempt and served the statutory notice after commencing and no later than 90 days after ceasing to furnish materials or services.

Notice record Entry
Each owner served [________________________________]
Original contractor served if § 49-35 required it [________________________________]
Date and statutory service method [________________________________]
Server return retained [________________________________]

2. Recording Information

Town Clerk / land records of: [________________________________], Connecticut

Return recorded instrument to:

[NAME]

[ADDRESS]

3. Certificate

The undersigned claimant, being duly sworn, states:

  1. Claimant. [CLAIMANT LEGAL NAME], of [ADDRESS], performed services or furnished materials described below.

  2. Person or persons against whom the lien is filed. [________________________________].

  3. Owner or owners of record. [________________________________].

  4. Person who engaged claimant. [________________________________], whose relationship to the project is ☐ owner ☐ original contractor ☐ subcontractor ☐ other: [________________].

  5. Premises. The lien concerns the building, lot, or plot of land located at [STREET ADDRESS], in the Town of [________________], Connecticut, more particularly described as follows or in attached Exhibit A:

[LEGAL DESCRIPTION SUFFICIENT TO IDENTIFY THE PREMISES]

  1. Materials or services. Claimant furnished:

[DESCRIPTION]

  1. Commencement date. Claimant began performing services or furnishing materials on [__/__/____].

  2. Cessation date. Claimant ceased performing services or furnishing materials on [__/__/____].

  3. Amount claimed. The amount claimed as a lien is $[________________]. That amount is justly due, as nearly as it can be ascertained, after credits and payments and subject to the limitations of §§ 49-33 and 49-36.

4. Subscription and Oath

I have read this Certificate and swear that its statements are true and that the amount claimed is justly due, as nearly as it can be ascertained.

Claimant or authorized signer: ________________________________

Printed name and title: [________________________________]

Date: [__/__/____]

STATE OF CONNECTICUT
COUNTY OF [________________]

Subscribed and sworn to before me on [__/__/____] by [________________________________].

Officer administering oath: ________________________________

Commission expiration, if applicable: [__/__/____]

5. Post-Recording Owner-Copy Service

Section 49-34 requires a true and attested copy of the recorded certificate to be served on each owner no later than 30 days after lodging the certificate, using the service method provided in § 49-35.

Item Entry
Certificate lodged/recorded [__/__/____]
Final day for owner-copy service [__/__/____]
Each owner and service address [________________________________]
Indifferent person, state marshal, or other proper officer [________________________________]
Statutory method and completion date [________________________________]

☐ True and attested copy served on every owner.

☐ Server's return and proof of registered/certified mail or publication, if applicable, retained.

6. Enforcement Calendar

Under § 49-39, preserving the lien beyond the statutory period generally requires both commencement of a foreclosure action and recording a notice of lis pendens in the town land records within one year from recording, or within the statute's later 60-day period following final disposition of a § 49-35a application and appeal.

Item Entry
Lien recording date [__/__/____]
One-year foreclosure/lis-pendens date [__/__/____]
§ 49-35a/49-35c later-period review, if any [________________________________]

Official Sources

Insert Image

Insert Table

Watch Ezel in action (sample case)Choose a plan

All changes saved
Save
Export
Export as DOCX
Export as PDF
Generating PDF...
mechanics_lien_claim_ct.pdf
Ready to export as PDF or Word
AI is editing...
Chat
Review

Draft it in the editor

The AI drafts each section from your answers and you review every word. Drafting from scratch takes hours; finish yours for $99 one time.

  • Built on this template
    Uses the Connecticut version and the statutes it cites.
  • Formatted like the template
    Captions, numbering and layout stay intact.
  • AI editing
    Rewrite any section from your own notes.
  • Export as PDF and Word
    Yours to review, sign, or file.
Secure checkout via Stripe
Need to customize this document?

About this template

Last updated
August 2, 2026
Citations checked
August 2, 2026
Jurisdiction
Connecticut
Category
Real Estate

Legal authority

  • Conn. Gen. Stat. § 49-33 (lien eligibility, property, priority, and subcontractor limits)
  • Conn. Gen. Stat. § 49-34 (certificate contents, 90-day recording, and owner-copy service)
  • Conn. Gen. Stat. § 49-35 (notice-of-intent exemptions, timing, recipients, and service)
  • Conn. Gen. Stat. § 49-36 (aggregate lien limits, apportionment, and good-faith payments)
  • Conn. Gen. Stat. § 49-39 (foreclosure and lis pendens deadline)

Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.

Not legal advice

This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.

Checked against the law it cites

A reviewer verified this template's legal citations against the official source on August 2, 2026.

Draft your Mechanics Lien Claim in the editor

Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.