Mechanics Lien Filing Package — Texas

Texas Real Estate Updated September 5, 2026 Free Word and PDF

Mechanics Lien Filing Package (Texas)

Quick-Reference Summary

Item Texas Rule (post-1/1/2022)
Governing statute Tex. Prop. Code Ch. 53; Tex. Const. art. XVI, § 37
Who must give pre-lien notice Subcontractors and suppliers (all tiers, no distinction). Original contractors are exempt from pre-lien notice (but must still file the affidavit). Design professionals (licensed architects, engineers, surveyors) have lien rights under § 53.021(c).
Pre-lien notice deadline (claimant other than original contractor) Residential: 15th day of the second month after each unpaid furnishing month. Other projects: 15th day of the third month. Apply the same rule to the normal-delivery month for undelivered specially fabricated materials (§ 53.056).
Pre-lien notice for retainage The earlier of (i) the 30th day after the claimant's agreement is completed / terminated / abandoned, or (ii) the 30th day after the original contract is terminated / abandoned (§ 53.057).
Lien affidavit recording deadline — Original (Prime) contractor — non-residential Not later than the 15th day of the fourth month after the month in which the original contract was completed, terminated, or abandoned (§ 53.052(a)).
Lien affidavit recording deadline — Subcontractor / supplier — non-residential Not later than the 15th day of the fourth month after the last month in which labor or materials were furnished (§ 53.052(a)).
Lien affidavit recording deadline — Residential project Not later than the 15th day of the third month after the month of completion / termination / abandonment (§ 53.052(b)).
Lien affidavit recording deadline — Retainage Not later than the 15th day of the third month after the month in which the original contract was completed, terminated, or abandoned (§ 53.052(d)).
Service of recorded lien on owner Send copy of recorded affidavit to owner (for original contractor) or owner AND original contractor (for sub / supplier) not later than the FIFTH day after filing (§ 53.055).
Foreclosure suit deadline First anniversary of the last day on which the affidavit may be filed (§ 53.158(a)). Extendable to second anniversary by written, recorded agreement with then-current owner (§ 53.158(a-2)).
Trust-fund / bond alternative Yes — Texas Construction Trust Fund Act (Prop. Code Ch. 162); payment-bond claims under Ch. 53 Subch. I (§§ 53.201–53.260) for residential & "transfer to bond" discharge under § 53.171.
Public works bond claim Tex. Gov't Code Ch. 2253 (McGregor Act) — separate statute, NOT Chapter 53.

Part A — Pre-Lien Notice (Texas Notice of Claim, Tex. Prop. Code § 53.056)

A.1 Recipients

For claims governed by the post-January 1, 2022 law, a claimant other than an original contractor sends the § 53.056 notice to:

  • Owner (or reputed owner per current deed of record);
  • Original contractor (the GC in privity with owner).

Original contractors are not required to send a pre-lien notice prior to filing their lien affidavit.

A.2 Required Statutory Form (§ 53.056(a-2))

The notice must be substantially in this form:

NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS

WARNING: This notice is provided to preserve lien rights.

Owner's property may be subject to a lien if sufficient funds are not withheld from future payments to the original contractor to cover this debt.

Date: [__/__/____]

Project description and/or address: [________________________________]

Claimant's name: [________________________________]

Type of labor or materials provided: [________________________________]

Original contractor's name: [________________________________]

Party with whom claimant contracted if different from original contractor: [________________________________]

Claim amount: $[________________________________]

[________________________________] (Claimant's contact person)

[________________________________] (Claimant's address)

An invoice or billing statement may accompany the notice under § 53.056(a-3).

A.3 Service Method (§ 53.003)

Unless another subsection controls, delivery may be in person to the entitled party or agent, by certified mail, or by another traceable private delivery or mailing service that can confirm proof of receipt. Certified-mail deposit or mailing in the required form constitutes compliance unless receipt is required; the statute does not provide the same deposit rule for every private carrier.

A.4 Deadline Calculation

For each month in which the claimant furnished unpaid labor or materials:

Residential construction project: send by the 15th day of the second month after the furnishing month. Other project: send by the 15th day of the third month.

For undelivered specially fabricated materials, use the month in which delivery normally would have occurred. Calculate each month separately; a consolidated notice is effective only for amounts whose deadlines have not passed.

If the deadline falls on a Saturday, Sunday, or legal holiday, current § 53.003(e) extends the period through the next day that is not one of those days.

Part B — Affidavit Claiming Mechanic's Lien (Tex. Prop. Code §§ 53.052, 53.054)

Caption / Header

Filed with the County Clerk of [____________________] County, Texas (real-property records). Texas does not use a court caption for the affidavit itself — it is filed as a recorded instrument.


AFFIDAVIT CLAIMING MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
(Tex. Prop. Code §§ 53.052, 53.054)

After being recorded, return to:

[_______________________________________________]
[_______________________________________________]

I. Claimant Identification (§ 53.054(a)(7))

Claimant (sworn affiant): [_________________________________________________________]
Mailing address: [____________________________________________________]
Physical address, if different: [____________________________________________________]
Capacity (original contractor / subcontractor / supplier / design professional): [____________]
Texas contractor license / registration (if applicable; e.g., TDLR or TBPLS): [____________]

II. Property Owner Identification (§ 53.054(a)(2))

Owner or reputed owner (per current deed of record in [____________] County): [________________________________________________]
Mailing address: [____________________________________________________]

III. Property Description (§ 53.054(a)(6))

Street address: [____________________________________________________]
City / County: [____________________________________________________]
Legal description sufficient to identify the property:

[_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________]

IV. Labor, Services, Equipment, or Material Furnished (§ 53.054(a)(3))

General description of work performed and / or materials furnished by claimant:

[_______________________________________________________________________
_______________________________________________________________________]

Individual work or material items are not required by § 53.054(c). Attach invoices or statements as Exhibit A only if useful to support the general description and amount.

For a claimant other than an original contractor, identify each month in which work was done or materials were furnished for which payment is requested:

Furnishing Month Work or Materials for Which Payment Is Requested
[____/____] [________________________________]
[____/____] [________________________________]

V. Hiring Party / Contract Identification (§ 53.054(a)(4))

Name of party with whom claimant contracted (the original contractor, subcontractor, owner, or owner's agent): [________________________________________________]

If claimant is a subcontractor or supplier — identify each subcontractor above claimant in the contracting chain through to the original contractor, to the extent known.

VI. Original Contractor Identification (§ 53.054(a)(5))

Original contractor name: [________________________________________________]

Original contractor last known address: [________________________________________________]

VII. Amount Owed (§ 53.054(a)(1))

Component Amount
Total contract / order amount (incl. approved change orders) $ [____________]
Less payments received $ ([____________])
Less just credits and offsets $ ([____________])
Principal balance unpaid and claimed $ [____________]
Contractual finance charges $ [____________]
Contractual retainage claimed $ [____________]

Total amount of lien: $ [____________]

VIII. First and Last Date of Furnishing

Date claimant first furnished labor or materials to the project: [__/__/____]
Date claimant last furnished labor or materials to the project: [__/__/____]
Date of completion / termination / abandonment of original contract (if known): [__/__/____]

IX. Notice Compliance Statement (§ 53.054(a)(8))

Claimant gave the notice(s) required by § 53.056 (and, if applicable, § 53.057 for retainage) to the owner and original contractor as follows:

Notice Month Notice Sent Date Method Recipient(s)
[____/____] [__/__/____] [Certified mail / in person / traceable private delivery] Owner; Original contractor
[____/____] [__/__/____] [Certified mail / in person / traceable private delivery] Owner; Original contractor

Attach the certified-mail record, signed delivery acknowledgment, carrier tracking, or other proof applicable to the selected § 53.003 method as Exhibit B.

X. Verification / Notarization (§ 53.054(a))

State of Texas
County of [____________________]

Before me, the undersigned notary, on this [____] day of [____________________], 20[____], personally appeared [_________________________], known to me, who being by me duly sworn, deposed and said the foregoing affidavit is true and correct to the best of his/her knowledge.

Signature of affiant: [_________________________________________________________]
Print name & title: [_______________________________________________]

___________________________________
Notary Public, State of Texas
My commission expires: [__/__/____]
[Notary seal]

Part C — Notice of Filed Lien Affidavit to Owner (Tex. Prop. Code § 53.055)

Not later than the fifth day after the date the affidavit is filed with the county clerk, the claimant must send a copy of the filed affidavit (with file-stamp / clerk's recording data) by certified mail to:

  • Original contractors: the owner or reputed owner.
  • Subcontractors / suppliers: the owner or reputed owner AND the original contractor.
NOTICE OF FILED AFFIDAVIT CLAIMING LIEN
(Tex. Prop. Code § 53.055)

Date: [__/__/____]

VIA CERTIFIED MAIL, RETURN RECEIPT REQUESTED

[Owner name and address]
[Original contractor name and address, if subcontractor/supplier claimant]

Re: Mechanic's Lien Affidavit — [Project address]
    Filed [__/__/____] in the Official Public Records of
    [____________] County, Texas, as Instrument No. [____________]

Enclosed is a file-stamped copy of the Affidavit Claiming Mechanic's
Lien, filed pursuant to Tex. Prop. Code § 53.052. The unpaid amount
secured by the lien is $[____________]. This notice is given pursuant
to § 53.055.

The lien may be discharged by payment, by indemnity bond filed under
§ 53.171, or by court order.

Sincerely,
[Claimant signatory]

Part D — Suit to Foreclose Mechanic's Lien (Tex. Prop. Code § 53.158)

D.1 Caption

CAUSE NO. [____________]

IN THE DISTRICT COURT
[____________________] COUNTY, TEXAS
[____] JUDICIAL DISTRICT
Party Role
[CLAIMANT NAME], Plaintiff
v.
[OWNER NAME]; [ORIGINAL CONTRACTOR]; [ANY LIENHOLDER OF RECORD], Defendants

PLAINTIFF'S ORIGINAL PETITION FOR FORECLOSURE OF MECHANIC'S LIEN AND BREACH OF CONTRACT

D.2 Discovery Level

Plaintiff intends to conduct discovery under [__ Level 1 / __ Level 2 / __ Level 3] of Tex. R. Civ. P. 190.

D.3 Jurisdiction and Venue

This Court has subject-matter jurisdiction; the amount in controversy exceeds the minimum jurisdictional limits of this Court. Venue is mandatory in [____________________] County under Tex. Civ. Prac. & Rem. Code § 15.011 because this suit is for foreclosure of a lien on real property situated in this County.

D.4 Lis Pendens

Plaintiff is filing a notice of lis pendens against the subject property in the real-property records of [____________] County contemporaneously with the filing of this petition (Tex. Prop. Code § 12.007).

D.5 Necessary and Permissive Defendants

  • Necessary: the record owner of the subject property; the original contractor (if claimant is a subcontractor / supplier); any other lien claimant of record who could be affected by foreclosure.
  • Permissive but recommended: all subordinate-lien holders, judgment-lien creditors, deed-of-trust beneficiaries, and tenants of record per a current title report.

D.6 Foreclosure Deadline Statement (§ 53.158)

The last day on which plaintiff could file the lien affidavit under § 53.052 was [__/__/____]. This suit is filed within one year of that date, as required by § 53.158(a). [If applicable: Plaintiff and the then-current record owner have executed a written agreement extending the limitations period to the second anniversary of the date of filing, recorded as Instrument No. [____________].]

D.7 Relief Requested

  1. Judgment that plaintiff holds a valid mechanic's, contractor's, or materialman's lien on the subject property in the amount of $[____________], plus contractual and statutory interest.
  2. Order of foreclosure and sale of the subject property by the sheriff or constable to satisfy the lien.
  3. Personal judgment for breach of contract against the hiring party for $[____________].
  4. Reasonable and necessary attorney's fees under Tex. Prop. Code § 53.156 and Tex. Civ. Prac. & Rem. Code § 38.001.
  5. Costs of court and post-judgment interest.

Part E — Pre-Filing Checklist

☐ Original contract, change orders, purchase orders, invoices, and statements of account gathered and reconciled by month.
☐ Daily logs, delivery tickets, photographs, weather logs, and crew sign-in sheets preserved.
☐ Hiring chain documented from claimant through to the original contractor and owner.
☐ Project type confirmed (residential vs. non-residential; homestead vs. non-homestead) — affects deadlines and notice content.
☐ Original-contract effective date confirmed (pre- or post-1/1/2022) — determines which Chapter 53 version applies.
☐ Current record owner identified from a deed search or current title report (NOT just the hiring party).
☐ § 53.056 deadline calculated for each unpaid furnishing month: second month for residential; third month for other projects; delivery proof preserved.
☐ § 53.057 Retainage Notice sent (if claimant has contractual retainage) within 30 days of agreement completion / termination / abandonment.
☐ Last day to file the lien affidavit under § 53.052 calculated and diaried.
☐ Lien affidavit drafted to verbatim § 53.054 content.
☐ Property described by legal description (not just street address); APN/parcel attached.
☐ Lien amount audited — no inclusion of items not lienable (e.g., delay damages, lost-profit overhead beyond statute).
☐ Affidavit sworn before a Texas notary; original signature and seal.
☐ Affidavit filed with the county clerk of the county where the property is located; instrument number diaried.
☐ § 53.055 post-filing notice (with file-stamped copy of affidavit) sent by certified mail within 5 days of filing to owner (and original contractor if claimant is sub/supplier).
☐ Foreclosure deadline (1-year anniversary of last day to file under § 53.158(a)) calendared.
☐ Lis pendens drafted under § 12.007 for contemporaneous filing with foreclosure suit.
☐ Payment-bond search performed (§ 53.171 bond to discharge; § 53.201 et seq. residential bond claims; Ch. 2253 public-works bond if applicable).
☐ Trust-fund claim under Ch. 162 evaluated for personal liability of officers / directors of insolvent contractor.
☐ Lien-release form prepared in escrow for settlement.

Sources and References

  • Tex. Prop. Code Ch. 53 (full text): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm
  • Tex. Prop. Code § 53.052 (Filing of Affidavit): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm#53.052
  • Tex. Prop. Code § 53.054 (Contents of Affidavit): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm#53.054
  • Tex. Prop. Code § 53.056 (Notice of Claim): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm#53.056
  • Tex. Prop. Code § 53.158 (Limitations): https://statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm#53.158
  • Texas Real Estate Research Center — Mechanic's & Materialman's Liens: https://trerc.tamu.edu/article/mechanics-and-materialmans-liens-2402/
  • Texas Department of Licensing and Regulation (contractor registration): https://www.tdlr.texas.gov
  • Texas Constitution Art. XVI, § 37: https://statutes.capitol.texas.gov/Docs/CN/htm/CN.16.htm#16.37

Insert Image

Insert Table

Watch Ezel in action (sample case)Choose a plan

All changes saved
Save
Export
Export as DOCX
Export as PDF
Generating PDF...
mechanics_lien_filing_package_tx.pdf
Ready to export as PDF or Word
AI is editing...
Chat
Review

Draft it in the editor

The AI drafts each section from your answers and you review every word. Drafting from scratch takes hours; finish yours for $99 one time.

  • Built on this template
    Uses the Texas version and the statutes it cites.
  • Formatted like the template
    Captions, numbering and layout stay intact.
  • AI editing
    Rewrite any section from your own notes.
  • Export as PDF and Word
    Yours to review, sign, or file.
Secure checkout via Stripe
Need to customize this document?

About this template

Last updated
September 5, 2026
Jurisdiction
Texas
Category
Real Estate

Legal authority

  • Tex. Prop. Code Ch. 53 (Mechanic's, Contractor's, or Materialman's Lien)
  • Tex. Prop. Code § 53.052 (Filing of Affidavit — recording deadlines)
  • Tex. Prop. Code § 53.054 (Contents of Affidavit)
  • Tex. Prop. Code § 53.056 (Notice of Claim for Unpaid Labor or Materials)
  • Tex. Prop. Code § 53.057 (Notice for Contractual Retainage Claim)
  • Tex. Prop. Code § 53.158 (One-year period to bring suit to foreclose)
  • Tex. Prop. Code §§ 53.201–53.260 (Residential construction projects, homestead)
  • Tex. Const. art. XVI, § 37 (Constitutional lien)

Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.

Not legal advice

This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.

Checked against the law it cites

The statutes this template relies on are listed under Legal authority.

Tex. Prop. Code § 53.054(a), (c) (checked September 5, 2026): "The affidavit must be signed by the person claiming the lien or by another person on the claimant's behalf and must contain substantially: [the sworn amount; owner; work and materials, including each payment-request month for a non-original contractor; hiring party; original contractor; property description; claimant mailing and any different physical address; and, for a non-original contractor, the date and method of each claim notice] ... The affidavit is not required to set forth individual items of work done or material furnished or specially fabricated."

Draft your Mechanics Lien Filing Package — Texas in the editor

Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.