Mechanics Lien Filing Package — California
Mechanics Lien Filing Package (California)
Quick-Reference Summary
| Item | California Rule |
|---|---|
| Governing statute | Cal. Civ. Code §§ 8000–9566 (private works); §§ 9000–9566 (public works) |
| Who must give preliminary notice | All claimants EXCEPT (i) direct contractors (must still serve construction lender if any) and (ii) laborers. Subs, suppliers, equipment lessors, design professionals must serve. |
| Preliminary notice deadline | Within 20 days after first furnishing labor, materials, services, or equipment to the work of improvement (Civ. Code § 8204). Late notice covers only the 20 days immediately preceding service plus all work thereafter. |
| Lien recording deadline — direct contractor | Normally 90 days after completion, shortened to 60 days after a recorded Notice of Completion / Notice of Cessation only when effective for that contractor. Check the owner’s 10-day copy duty and exceptions under Civ. Code § 8190. |
| Lien recording deadline — subcontractor / supplier | Normally 90 days after completion, shortened to 30 days after a recorded Notice of Completion / Notice of Cessation only when effective for that claimant. Check Civ. Code § 8190 notice duty and owner exceptions. |
| Service of claim of lien | Serve a copy, including the statutory notice, on the owner or reputed owner by a method in Civ. Code § 8416(c); if that method cannot serve the owner, mail it to the construction lender or original contractor. Include the signed proof-of-service affidavit required by § 8416(a)(7). Failure to serve as prescribed makes the lien unenforceable under § 8416(e). |
| Foreclosure suit deadline | Commence the enforcement action within 90 days after recording the claim of lien; otherwise it expires and is unenforceable, subject to the recorded extension-of-credit exception in Civ. Code § 8460(b). Recording a lis pendens is not a condition in § 8460. |
| Stop Payment Notice (alternative) | Yes — served on owner and construction lender (private works) before expiration of lien recording deadline (Civ. Code §§ 8500–8560). |
| Payment Bond claim (alternative) | Yes — within 15 days after recordation of Notice of Completion, or 75 days after actual completion if no such notice (Civ. Code §§ 8600–8614). |
| Trust-fund obligation | No general statutory trust-fund statute (compare NY Lien Law Art. 3-A); progress payment misapplication is addressed via Bus. & Prof. Code § 7108 (CSLB discipline) and Penal Code § 484b. |
Part A — Pre-Lien Notice (California Preliminary Notice, Civ. Code §§ 8200–8216)
A.1 Recipients
Every preliminary notice on a private work of improvement must be served on all three of the following (Civ. Code § 8200(a)):
- The owner or reputed owner.
- The direct (general) contractor or reputed direct contractor.
- The construction lender, if any (or reputed construction lender).
Exceptions (Civ. Code § 8200(e)):
- A laborer is not required to give preliminary notice.
- A claimant with a direct contractual relationship with the owner must give preliminary notice only to the construction lender (if any).
A.2 Required Content (Civ. Code §§ 8102, 8202)
PRELIMINARY NOTICE (CALIFORNIA CIV. CODE § 8202)
YOU ARE HEREBY NOTIFIED THAT . . .
(1) Name and address of claimant:
[_______________________________________________]
Contractor's License No. (if applicable): [____________]
(2) Description of labor, services, equipment, or materials furnished or to be furnished:
[_______________________________________________]
(3) Name and address of person who contracted for purchase of labor / materials:
[_______________________________________________]
(4) Description of jobsite sufficient for identification (street + APN + legal description):
[_______________________________________________]
(5) Estimated total price of labor, services, equipment, or materials:
$ [____________]
(5a) Owner or reputed owner — name and address: [_______________________]
(5b) Direct contractor — name and address: [___________________________]
(5c) Construction lender, if any — name and address: [__________________]
(5d) Claimant's relationship to the parties: [_________________________]
(5e) Claimant's demand after credits and offsets, if any: $[__________]
(5f) For a subcontractor with unpaid laborer compensation, names and
addresses required by § 8202(b): [______________________________]
(6) NOTICE TO PROPERTY OWNER required by Civ. Code § 8202(a)(3) —
reproduce the following statutory statement in boldface type:
NOTICE TO PROPERTY OWNER
EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm
that has given you this notice is not paid in full for labor, service,
equipment, or material provided or to be provided to your construction
project, a lien may be placed on your property. Foreclosure of the lien
may lead to loss of all or part of your property. You may wish to protect
yourself against this by (1) requiring your contractor to provide a signed
release by the person or firm that has given you this notice before making
payment to your contractor, or (2) any other method that is appropriate
under the circumstances.
This notice is required by law to be served by the undersigned as a
statement of your legal rights. This notice is not intended to reflect
upon the financial condition of the contractor or the person employed by
you on the construction project.
If you record a notice of cessation or completion of your construction
project, you must within 10 days after recording, send a copy of the
notice of completion to your contractor and the person or firm that has
given you this notice. The notice must be sent by registered or certified
mail. Failure to send the notice will extend the deadline to record a
claim of lien. You are not required to send the notice if you are a
residential homeowner of a dwelling containing four or fewer units.
A.3 Service Method (Civ. Code §§ 8106, 8110, 8118)
Service is effected by any of:
- Personal delivery.
- Leaving the notice and mailing a copy in the manner provided by Code Civ. Proc. § 415.20.
- Mailing by registered or certified mail, express mail, or overnight delivery by an express service carrier under § 8110.
Mail service is complete on deposit in the manner provided by § 8116(b); service by leaving and mailing is complete five days after mailing under § 8116(c).
Retain the proof-of-notice declaration, a copy of the notice, and one of the mailing or delivery records permitted by § 8118(b). A return receipt is one permitted form of proof, but is not mandatory.
A.4 Deadline Calculation
- "First furnishing" = first day actual labor performed or materials/equipment delivered to the jobsite, NOT the date of the contract or purchase order.
- Count the 20 days by excluding the first day under Code Civ. Proc. § 12. If the last day is a Saturday, Sunday, or other statutory holiday, § 12a extends the period to the next nonholiday day. Civ. Code § 8116 separately determines when a notice is complete after delivery or mailing.
- Late notice is not fatal, but the lien is limited to work / materials supplied within the 20-day window preceding service plus all later work (Civ. Code § 8204(a)).
Part B — Claim of Mechanics Lien (Civ. Code §§ 8400–8424)
Caption / Header
Recorded with the County Recorder of [____________________] County, California. Use the recorder's standard cover sheet plus the following form (Civ. Code § 8416(a)):
MECHANICS LIEN — CALIFORNIA CIVIL CODE § 8416
Recording requested by and when recorded return to:
[_______________________________________________]
[_______________________________________________]
APN: [_______________]
Space above for Recorder's Use Only
I. Claimant Identification
Claimant: [_________________________________________________________]
Mailing address: [____________________________________________________]
CSLB Contractor's License No. (if applicable): [____________]
Capacity (direct contractor / subcontractor / supplier / design professional / equipment lessor / laborer): [________________________________]
II. Property Owner Identification
Owner or reputed owner of fee interest (per current deed of record): [________________________________________________]
Address: [____________________________________________________]
If owner of the work of improvement is different (e.g., tenant under TIA), name and address: [________________________________________________]
III. Property Description (Civ. Code § 8416(a)(5))
Street address: [____________________________________________________]
City / County: [____________________________________________________]
Assessor's Parcel Number (APN): [_______________]
Legal description (sufficient for identification):
[_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________]
IV. Labor, Services, Equipment, or Material Furnished
General statement of the kind of labor, services, equipment, or materials furnished by claimant (Civ. Code § 8416(a)(3)):
[_______________________________________________________________________
_______________________________________________________________________]
V. Contract Identification
Name of person by whom claimant was employed or to whom the claimant furnished the work (Civ. Code § 8416(a)(4)):
[____________________________________________________________]
VI. Amount Owed (Civ. Code § 8416(a)(1))
| Component | Amount |
|---|---|
| Total contract / order amount (incl. approved change orders) | $ [____________] |
| Less payments received and credits | $ ([____________]) |
| Less offsets known to claimant | $ ([____________]) |
| Principal balance due after deducting all just credits and offsets | $ [____________] |
| Finance / interest charges per written contract (if any) | $ [____________] |
| Retainage withheld but earned | $ [____________] |
Total amount of lien claim: $ [____________]
VII. First and Last Date of Furnishing
Date claimant first furnished labor / materials / services / equipment to the work of improvement: [__/__/____]
Date claimant last furnished labor / materials / services / equipment: [__/__/____]
VIII. Statutory "Notice of Mechanics Lien" Required by Civ. Code § 8416(a)(8)
The recorded claim of lien MUST contain the following verbatim statutory NOTICE, in at least 10-point boldface type:
NOTICE OF MECHANICS LIEN
ATTENTION!
Upon the recording of the enclosed MECHANICS LIEN with the county recorder’s office of the county where the property is located, your property is subject to the filing of a legal action seeking a court-ordered foreclosure sale of the real property on which the lien has been recorded. That legal action must be filed with the court no later than 90 days after the date the mechanics lien is recorded.
The party identified in the enclosed mechanics lien may have provided labor or materials for improvements to your property and may not have been paid for these items. You are receiving this notice because it is a required step in filing a mechanics lien foreclosure action against your property. The foreclosure action will seek a sale of your property in order to pay for unpaid labor, materials, or improvements provided to your property. This may affect your ability to borrow against, refinance, or sell the property until the mechanics lien is released.
BECAUSE THE LIEN AFFECTS YOUR PROPERTY, YOU MAY WISH TO SPEAK WITH YOUR CONTRACTOR IMMEDIATELY, OR CONTACT AN ATTORNEY, OR FOR MORE INFORMATION ON MECHANICS LIENS GO TO THE CONTRACTORS’ STATE LICENSE BOARD WEB SITE AT www.cslb.ca.gov.
IX. Verification (Civ. Code § 8416(a))
I, the undersigned, declare under penalty of perjury under the laws of the State of California that I am [the claimant / an officer of claimant / claimant's agent], that I have read the foregoing Claim of Mechanics Lien, and that the contents thereof are true of my own knowledge.
Executed at [____________________], California, on [__/__/____].
Signature: [_______________________________________________]
Print name: [_______________________________________________]
Title: [____________________]
X. Proof of Service Affidavit (Civ. Code § 8416(a)(7), (c))
Serve a copy of the claim of lien, including the statutory notice, on the owner or reputed owner by registered or certified mail, or first-class mail evidenced by a certificate of mailing. If the owner cannot be served by that method, mail it to the construction lender or original contractor as § 8416(c)(2) provides. The lien must include a signed affidavit showing the date, place, manner, recipient name and address, and service facts (§ 8416(a)(7)).
PROOF OF SERVICE AFFIDAVIT
I, [____________________], declare that I am over 18 years of age and
not a party to this lien. On [__/__/____] I served a true copy of the
attached Claim of Mechanics Lien, including its statutory notice, by
[__ registered / __ certified / __ first-class mail with certificate
of mailing], postage prepaid, deposited at [CITY, STATE]: [__________].
Recipient name: [______________________________________________]
Recipient address: [___________________________________________]
Recipient title or capacity: [________________________________]
Recipient is: [__ owner or reputed owner / __ construction lender /
__ original contractor (owner could not be served by statutory method)]
Facts showing service under Civ. Code § 8416(c): [_______________]
I declare under penalty of perjury under the laws of California that
the foregoing is true and correct.
Date: [__/__/____] Signature: [____________________]
Part C — Notice of Filing Lien Claim to Owner
In California, the proof-of-service affidavit attached to the recorded lien (Part B.X) satisfies the post-recording notice obligation. There is no separate post-recording notice statute (contrast Florida § 713.08(4)(c) which requires a 15-day post-recording delivery). However, claimants frequently send a courtesy cover letter to the owner enclosing the recorded lien with recording-data stamp:
[Claimant letterhead] Date: [__/__/____]
VIA CERTIFIED MAIL, RETURN RECEIPT REQUESTED
[Owner name and address]
Re: Recorded Mechanics Lien — [Project address] — Recorder's
Instrument No. [____________], recorded [__/__/____], in the
Official Records of [______] County, California
Dear [Owner]:
Enclosed please find a conformed copy of the Mechanics Lien recorded
against the above-referenced property under California Civil Code
§§ 8400 et seq. The total amount of the lien is $[____________].
A foreclosure action must be commenced within 90 days of recordation
(Civ. Code § 8460). To avoid that action and the recordation of a lis
pendens, please contact the undersigned at [phone / email] to arrange
payment or to discuss a release.
Sincerely,
[Signature]
Part D — Suit to Foreclose Mechanics Lien (Civ. Code §§ 8460–8494)
D.1 Caption
SUPERIOR COURT OF THE STATE OF CALIFORNIA
COUNTY OF [____________________]
Case classification: ☐ Limited civil — amount in controversy does not exceed $35,000 and all other CCP § 85 conditions are met. ☐ Unlimited civil.
| Party | Role |
|---|---|
| [CLAIMANT NAME], | Plaintiff |
| v. | |
| [OWNER NAME]; [DIRECT CONTRACTOR]; [CONSTRUCTION LENDER]; all persons unknown claiming any legal or equitable right, title, estate, lien, or interest in the property described in the complaint adverse to plaintiff's lien, DOES 1–50 inclusive, | Defendants |
Case No.: [____________]
COMPLAINT TO FORECLOSE MECHANICS LIEN (Civ. Code § 8460); FOR BREACH OF CONTRACT; FOR COMMON COUNTS
D.2 Jurisdiction and Venue
This Court has original jurisdiction over this lien foreclosure action under Cal. Const. art. VI, § 10. The foreclosure claim is brought under Civ. Code § 8460. Venue is proper in [____________________] County under Code Civ. Proc. § 392(a) because the real property that is the subject of this action is situated in this County.
D.3 Lis Pendens
After filing this Complaint, plaintiff shall serve the Notice of Pendency of Action (lis pendens) on each adverse party and owner of record by registered or certified mail, return receipt requested, before recording it (Code Civ. Proc. § 405.22). Plaintiff shall record the notice with proof of that service in the official records of [____________________] County; otherwise the notice is void as to an unserved adverse party or owner (§ 405.23). After recording, file a copy with the Court showing the recording data.
D.4 Necessary and Permissive Defendants
- Necessary: the record owner; the direct contractor (under whom claimant worked, if a subcontractor); the construction lender (if any). Identify and join each party whose interest must be adjudicated; § 8460 addresses the filing deadline, not the effect of service on absent parties.
- Permissive: prior recorded lienholders, junior lienholders, subsequent purchasers of record, lessees of record. Best practice: name all parties of record per a current preliminary title report.
D.5 Foreclosure Deadline Statement
Plaintiff recorded its Mechanics Lien on [__/__/____] as Instrument No. [____________]. This action is commenced within 90 days of recordation, as required by Civ. Code § 8460(a). Absent a recorded extension of credit meeting § 8460(b), failure to commence within 90 days causes the lien to expire and become unenforceable.
D.6 Relief Requested
- Judgment that plaintiff's lien is valid and in the amount of $[____________], plus prejudgment interest and reasonable attorney's fees if provided by contract.
- Order of sale of the subject property to satisfy the lien.
- Personal judgment against [direct contractor / hiring party] for breach of contract and common counts.
- Costs of suit.
Part E — Pre-Filing Checklist
☐ Contract, purchase orders, change orders, invoices, statements of account gathered and reconciled.
☐ Daily logs, delivery tickets, time records, photographs of work in place preserved.
☐ Last date of furnishing verified against jobsite records (not punch-list / warranty work).
☐ Current record owner identified from a preliminary title report or county recorder grantor-grantee index (not just the contract counterparty).
☐ Construction lender or reputed construction lender (if any) identified from the recorded construction deed of trust, owner or direct contractor records, or a title search (Civ. Code § 8200(a)(3)).
☐ Preliminary notice (Civ. Code § 8202) served within 20 days of first furnishing on owner, direct contractor, and construction lender; certified-mail receipts and certificate of mailing retained.
☐ For unlicensed claimants — confirmed lien rights exist (laborer? supplier-only? otherwise Bus. & Prof. Code § 7031 bars enforcement).
☐ Completion / cessation date confirmed; relevant recording-deadline branch (60 / 30 / 90 days) calculated.
☐ Notice of Completion / Notice of Cessation searched in county records.
☐ Claim of lien drafted to verbatim Civ. Code § 8416 content, with NOTICE OF MECHANICS LIEN in 10-point boldface.
☐ Lien amount audited; willful overstatement avoided (Civ. Code § 8422).
☐ Claim of lien verified under penalty of perjury by claimant or authorized officer.
☐ Copy of lien, including statutory notice, served by a method in Civ. Code § 8416(c); signed proof-of-service affidavit with required details included in lien under § 8416(a)(7).
☐ Lien recorded with county recorder of the county where property is situated; recording instrument number diaried.
☐ 90-day foreclosure deadline calendared from date of recording (Civ. Code § 8460); litigation budget approved.
☐ Lis pendens drafted; adverse parties and record owners served before recording; proof of service ready to record with the notice (Code Civ. Proc. §§ 405.22–405.23).
☐ Stop-payment-notice option evaluated (Civ. Code §§ 8500–8560) — particularly if construction loan funds remain undisbursed.
☐ Payment-bond search performed; bond-claim deadlines (Civ. Code § 8612) calendared if bond exists.
☐ Lien release / partial release form prepared in escrow for settlement (Civ. Code §§ 8120–8138).
Sources and References
- California Civil Code §§ 8000–9566 (full text): https://leginfo.legislature.ca.gov/faces/codesTOCSelected.xhtml?tocCode=CIV
- Civ. Code § 8200 (Preliminary Notice): https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=CIV§ionNum=8200
- Civ. Code § 8416 (Contents of Claim of Lien): https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=CIV§ionNum=8416
- Civ. Code § 8460 (Foreclosure Suit Deadline): https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=CIV§ionNum=8460
- Contractors State License Board (CSLB) — Mechanics Lien Information: https://www.cslb.ca.gov/Consumers/Filing_A_Complaint/Mechanics_Lien.aspx
- California State Association of Counties (CSAC) — County Recorder directory and fees: https://www.csac.counties.org
About this template
- Last updated
- November 1, 2026
- Jurisdiction
- California
- Category
- Real Estate
Legal authority
- Cal. Code Civ. Proc. §§ 12, 12a (time computation and holiday extension)
- Cal. Civ. Code §§ 8000–9566 (Mechanics Lien Law; Works of Improvement)
- Cal. Civ. Code § 8200 (Preliminary Notice — 20-day requirement)
- Cal. Civ. Code §§ 8412, 8414 (Lien recording deadlines)
- Cal. Civ. Code § 8416 (Required content of claim of lien)
- Cal. Civ. Code § 8460 (90-day foreclosure suit deadline)
- Cal. Civ. Code §§ 8500–8560 (Stop Payment Notice)
- Cal. Civ. Code §§ 8600–8614 (Payment bond claims, private works)
Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.
Not legal advice
This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.
Checked against the law it cites
The statutes this template relies on are listed under Legal authority.
Cal. Code Civ. Proc. § 12 (checked November 1, 2026): "The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded."
Cal. Code Civ. Proc. § 12a(a) (checked November 1, 2026): "(a) If the last day for the performance of any act provided or required by law to be performed within a specified period of time is a holiday, then that period is hereby extended to and including the next day that is not a holiday. For purposes of this section, “holiday” means all day on Saturdays, all holidays specified in Section 135 and, to the extent provided in Section 12b, all days that by terms of Section 12b are required to be considered as holidays."
Cal. Code Civ. Proc. §§ 405.22–405.23 (applied in Hernandez v. LoanDepot.com, LLC, Sonoma Cty. Super. Ct., Aug. 19, 2026) (checked October 30, 2026): "CCP § 405.22 requires the claimant to serve a copy of the notice of pendency of action to the adverse party by registered or certified mail with return receipt requested prior to recordation."
Cal. Civ. Code § 8190(d)(1) (checked October 29, 2026): "A person that occupies the real property as a personal residence, if the dwelling contains four or fewer residential units."
Draft your Mechanics Lien Filing Package — California in the editor
Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.