Mechanics Lien Filing Package — Mississippi

Mississippi Real Estate Updated August 25, 2026 Free Word and PDF

Mechanics Lien Filing Package (MISSISSIPPI)


Quick-Reference Summary

Item Mississippi Authority
Governing Statute Miss. Code Ann. §§ 85-7-401 to 85-7-433 (eff. Apr. 11, 2014)
Filing Office Chancery Clerk of the county where the property is located (§ 85-7-405(1)(b))
Who May File Contractors, subcontractors, materialmen, registered architects, professional engineers, and registered land surveyors that satisfy § 85-7-403
Thirty-Day Notice (§ 85-7-407) Except on single-family residential construction, a claimant without privity with the contractor—or with the owner if there is no contractor—must give the statutory information within 30 days following first delivery; failure forfeits lien rights
Single-Family Pre-Lien Notice (§ 85-7-409) A subcontractor, materialman, or design professional not in privity with the owner must give the owner the statutory notice at least 10 days before filing
Lien Filing Deadline Within 90 days of last work performed or last labor/services/materials furnished (§ 85-7-405(1)(b))
Required Form Statutory form in § 85-7-405(1)(b) — must include "THIS CLAIM OF LIEN EXPIRES AND IS VOID 180 DAYS FROM THE DATE OF FILING OF THE CLAIM OF LIEN IF A PAYMENT ACTION IS NOT FILED BY THE CLAIMANT WITHIN THAT TIME PERIOD" and "NOTICE TO OWNER OF PROPERTY: You have the right to contest this claim of lien pursuant to Mississippi law"
Service of Filed Lien on Owner Within 2 business days of filing, copy to owner by registered/certified mail or statutory overnight delivery (§ 85-7-405(1)(b))
Service of Filed Lien on Contractor (when claimant is not GC) Within 2 business days of filing (§ 85-7-405(1)(b))
Payment Action (Foreclosure) Deadline Within 180 days of filing the lien (§ 85-7-405(1)(c), § 85-7-421); lis pendens required at commencement
Notice of Contest of Lien — Effect Reduces payment-action deadline to 90 days from the date of the owner's filing (§ 85-7-423)
Priority Among Lien Claimants All construction liens share equal priority (§ 85-7-405(3)(d))
Bond to Discharge § 85-7-415 — 110% cash or approved surety bond; notice obligations follow filing
Knowing False Lien / Expungement § 85-7-429 — treble-damages exposure and a seven-day-notice route to seek expungement or vacatur
Payment-Bond Substitution § 85-7-431 — qualifying public- or private-project payment bond substitutes for subcontractor/material-supplier liens
Form Update / Amendments Lien amount may be amended only as expressly permitted by statute; payments and credits must be reflected

Part A — Pre-Lien Notice

A.1 — Thirty-Day Notice for Claimant Without Contractor Privity — Miss. Code Ann. § 85-7-407(2)

Except on single-family residential construction, this notice is required where the claimant does not have privity with the contractor—or, if there is no contractor, with the owner. It must be delivered within 30 days following the claimant's first delivery of labor, services, or materials. Failure to give it forfeits the lien right.

NOTICE TO GENERAL CONTRACTOR

TO: [CONTRACTOR NAME AND ADDRESS]

[IF THERE IS NO CONTRACTOR: OWNER NAME AND ADDRESS]

(Pursuant to Miss. Code Ann. § 85-7-407(2))

The undersigned is performing labor or supplying materials on the construction project located at [PROJECT ADDRESS]. This notice is given within 30 days of first furnishing such labor/materials.

Field Entry
Name of Sub-Subcontractor / Claimant [________________________________]
Address / Phone / Email [________________________________]
Name of Subcontractor with Whom Claimant Contracted [________________________________]
Description of Work to be Performed / Materials to be Furnished [________________________________]
Anticipated Costs $[__________]
Date Work Began [__/__/____]
Project Address [________________________________]

Method of delivery: ☐ Certified mail RRR — Article No. [_______________] ☐ Personal delivery

Date served: [__/__/____]

Signature: ________________________________ Name / Title: [________________________________]


A.2 — Single-Family Residential Pre-Lien Notice to Owner — Miss. Code Ann. § 85-7-409

Required only for single-family residential construction where claimant is a subcontractor, materialman, or design professional not in privity with the owner. It must be provided to the owner by a reliable means at least 10 days before filing the Claim of Lien.

PRE-LIEN NOTICE TO OWNER (Residential)

TO: [OWNER NAME]
[OWNER ADDRESS]

(Pursuant to Miss. Code Ann. § 85-7-409)

You are hereby notified that the undersigned has performed labor or supplied materials in connection with the improvement of the residential property described below, and that the undersigned has not been paid. Unless the amount owed is paid within ten (10) days from the date of this notice, the undersigned intends to file a Claim of Lien against the property with the Chancery Clerk of [_______________] County, Mississippi.

Field Entry
Claimant Name and Address [________________________________]
Property Address [________________________________]
Description of Labor / Materials [________________________________]
Date Last Labor / Materials Furnished [__/__/____]
Person Who Hired Claimant [________________________________]
Amount Due $[__________]

Date: [__/__/____]

________________________________
[CLAIMANT NAME], [TITLE]

Method of service: ☐ Certified mail RRR — Article No. [_______________] ☐ Personal delivery


Part B — Claim of Mechanics Lien

CLAIM OF CONSTRUCTION LIEN

STATE OF MISSISSIPPI
COUNTY OF [________________]

Filed with the Chancery Clerk of [_______________] County, Mississippi pursuant to Miss. Code Ann. § 85-7-405.

[CLAIMANT NAME], a mechanic, contractor, subcontractor, materialman, machinist, manufacturer, registered architect, registered forester, registered land surveyor, registered professional engineer, or other person entitled to a lien under Miss. Code Ann. § 85-7-403, claims a lien in the amount of $[__________] on the building, structure, house, factory, mill, machinery, or improvements (and the premises or real estate on which they are erected or built) of [OWNER NAME], described as follows:

Item Entry
Property Street Address [________________________________]
County [________________________________]
Legal Description (attach Exhibit A if lengthy) [________________________________]
Parcel ID [________________________________]
Description of Improvement [________________________________]

for satisfaction of a claim which became due on [__/__/____], being the same as the last date labor, services, or materials were supplied to the premises, for [DESCRIBE WORK / LABOR / MATERIALS / SERVICES PROVIDED].

Lien Details Entry
Claimant Name and Mailing Address [________________________________]
Claimant Phone / Email [________________________________]
Claimant's Role ☐ Contractor ☐ Subcontractor ☐ Materialman ☐ Architect ☐ Engineer ☐ Surveyor ☐ Other: [_______________]
Person With Whom Claimant Contracted [________________________________]
Name of General Contractor (if claimant is not GC) [________________________________]
Owner of Record [________________________________]
Owner Mailing Address [________________________________]
Date First Labor / Materials Furnished [__/__/____]
Date Last Labor / Materials Furnished [__/__/____]
Contract Amount $[__________]
Payments Received $[__________]
Amount of Lien (after credits and offsets) $[__________]

THIS CLAIM OF LIEN EXPIRES AND IS VOID ONE HUNDRED EIGHTY (180) DAYS FROM THE DATE OF FILING OF THE CLAIM OF LIEN IF A PAYMENT ACTION IS NOT FILED BY THE CLAIMANT WITHIN THAT TIME PERIOD.

NOTICE TO OWNER OF PROPERTY: You have the right to contest this claim of lien pursuant to Mississippi law.


Verification / Affidavit

STATE OF MISSISSIPPI, COUNTY OF [_______________], ss.

I, [_______________], being first duly sworn, depose and state: I am [the Claimant / [TITLE] of the Claimant] and am authorized to make this verification. I have read the foregoing Claim of Lien. The facts stated therein are true and correct to the best of my knowledge, information, and belief. The amount of $[__________] is justly due and owing to the Claimant after allowance of all just credits and offsets. The labor, services, and/or materials described above were furnished in substantial compliance with the Claimant's contract, subcontract, or purchase order for the improvement of the Property described.

________________________________
Affiant Signature

Print Name / Title: [________________________________]

Subscribed and sworn to before me on [__/__/____] by [_______________].

________________________________
Notary Public — State of Mississippi
My commission expires: [__/__/____]

[NOTARY SEAL]

Attached Exhibits:

  • Exhibit A — Legal Description
  • Exhibit B — Itemized Statement of Account / Invoices

Part C — Notice of Filing Lien Claim to Owner — Miss. Code Ann. § 85-7-405(1)(b)

[CLAIMANT LETTERHEAD]

Date: [__/__/____]

TO: [OWNER NAME]
[OWNER ADDRESS / REGISTERED AGENT ADDRESS]

Via: ☐ Registered mail — Article No. [_______________] ☐ Certified mail RRR — Article No. [_______________] ☐ Statutory overnight delivery (tracking No. [_______________])

Re: Claim of Construction Lien filed against [PROPERTY ADDRESS], County of [_______________], Mississippi

You are hereby notified, pursuant to Miss. Code Ann. § 85-7-405(1)(b), that on [__/__/____] the undersigned filed a Claim of Construction Lien against the above-described property with the Chancery Clerk of [_______________] County, Mississippi, in the amount of $[__________]. A true and correct copy of the filed Claim of Lien is enclosed.

THIS CLAIM OF LIEN EXPIRES AND IS VOID ONE HUNDRED EIGHTY (180) DAYS FROM THE DATE OF FILING OF THE CLAIM OF LIEN IF A PAYMENT ACTION IS NOT FILED BY THE CLAIMANT WITHIN THAT TIME PERIOD.

NOTICE TO OWNER OF PROPERTY: You have the right to contest this claim of lien pursuant to Mississippi law (Miss. Code Ann. § 85-7-423).

Demand is hereby made for payment of the amount due. Failure to pay may result in a payment action being filed in court to enforce the lien, and to sale of the Property to satisfy the lien.

Sincerely,

________________________________
[CLAIMANT NAME], [TITLE]
[CLAIMANT ADDRESS / PHONE / EMAIL]

[If claimant is not the General Contractor, send a separate copy of this notice and the filed lien to the GC at:]
[GENERAL CONTRACTOR NAME / REGISTERED AGENT]
[ADDRESS]


Part D — Suit to Foreclose (Payment Action) — Miss. Code Ann. § 85-7-405(1)(c)

IN THE CHANCERY COURT OF [_______________] COUNTY, MISSISSIPPI

Party Role
[CLAIMANT NAME], Plaintiff
v.
[OWNER NAME]; [GENERAL CONTRACTOR]; [OTHER LIEN CLAIMANTS, MORTGAGEES, OR LIENHOLDERS OF RECORD]; JOHN DOES 1–10, Defendants

Cause No.: [____________]

COMPLAINT FOR PAYMENT, ENFORCEMENT, AND FORECLOSURE OF CONSTRUCTION LIEN

COMES NOW Plaintiff [CLAIMANT NAME], by and through undersigned counsel, and for its Complaint states:

Parties, Jurisdiction, and Venue

  1. Plaintiff is a [ENTITY TYPE] organized under the laws of [_______________] and qualified to do business in Mississippi.

  2. Defendant [OWNER NAME] is, upon information and belief, the record owner of the Property at issue, located in [_______________] County, Mississippi.

  3. Jurisdiction is proper under Miss. Const. art. 6, § 159, Miss. Code Ann. § 9-5-81, and Miss. Code Ann. § 85-7-405(1)(c). Venue is proper because the Property is located in this county.

General Allegations

  1. On or about [__/__/____], Plaintiff entered into a [written / oral] contract with [HIRING PARTY] under which Plaintiff agreed to furnish [DESCRIBE LABOR/MATERIALS] in substantial compliance with said contract for the improvement of the Property commonly known as [PROPERTY ADDRESS] and legally described as:

[LEGAL DESCRIPTION]

  1. Plaintiff substantially complied with its contract by furnishing labor, services, and/or materials from [__/__/____] (first date) to [__/__/____] (last date).

  2. The reasonable value of labor/materials furnished is $[__________]. Plaintiff has been paid $[__________]. The balance due and unpaid, after all just credits and offsets, is $[__________].

  3. [Single-family claimant not in owner privity only] On [__/__/____], Plaintiff, as a subcontractor, materialman, or design professional, provided the Owner the Pre-Lien Notice required by Miss. Code Ann. § 85-7-409, as evidenced by Exhibit A; at least 10 days passed before the lien was filed.

  4. [Non-single-family claimant lacking contractor privity only] On [__/__/____], within 30 days following first delivery, Plaintiff gave the written notice required by Miss. Code Ann. § 85-7-407(2) to the Contractor [or, because there was no contractor, to the Owner], as evidenced by Exhibit B.

  5. On [__/__/____], within 90 days of the last labor or materials furnished, Plaintiff filed a Claim of Construction Lien against the Property with the Chancery Clerk of [_______________] County, Mississippi, in the amount of $[__________]. A copy of the filed lien is attached as Exhibit C.

  6. Within two (2) business days of filing, Plaintiff served a copy of the filed lien on the Owner [and on the General Contractor, if applicable] by [registered/certified mail or statutory overnight delivery], as evidenced by Exhibit D.

  7. This action is commenced within 180 days of the filing of the Claim of Lien as required by Miss. Code Ann. §§ 85-7-405(1)(c), 85-7-421 [— or — within 90 days of the Owner's Notice of Contest of Lien filed/served on [__/__/____] per Miss. Code Ann. § 85-7-423].

  8. Concurrently with the filing of this Complaint, Plaintiff has filed a Lis Pendens Notice and is delivering copies to the Owner and Contractor as required by § 85-7-405(1)(c)(i).

Count I — Payment Action / Enforcement of Construction Lien

  1. Plaintiff incorporates the preceding paragraphs.

  2. Plaintiff has a valid and enforceable construction lien against the Property in the amount of $[__________], plus interest, costs, and attorney's fees as allowed by Mississippi law.

  3. Plaintiff is entitled to a judgment establishing the lien, enforcing it against the Property, and ordering sale of the Property and improvements to satisfy the lien.

Count II — Breach of Contract

  1. Plaintiff incorporates the preceding paragraphs.

  2. [HIRING PARTY] breached the contract by failing to pay $[__________]. Plaintiff is entitled to judgment in that amount, plus prejudgment interest at the statutory or contract rate, costs, and attorney's fees if provided by contract.

Count III — Unjust Enrichment (alternative)

  1. Plaintiff incorporates the preceding paragraphs.

  2. Plaintiff conferred a benefit upon Defendant Owner by its labor and materials, the reasonable value of which is $[__________]. Equity requires restitution.

Prayer for Relief

WHEREFORE, Plaintiff prays for:

A. Adjudication that Plaintiff holds a valid construction lien against the Property in the amount of $[__________], plus interest, costs, and attorney's fees;
B. Enforcement and foreclosure of the lien, and sale of the Property and improvements to satisfy the lien;
C. Determination of priority among parties claiming an interest in the Property pursuant to Miss. Code Ann. § 85-7-405(3)(d);
D. Judgment against [HIRING PARTY] for breach of contract in the amount of $[__________], plus interest, costs, and attorney's fees;
E. Costs of suit and prejudgment interest at the lawful rate;
F. Such other relief, legal or equitable, as the Court deems just.

Dated: [__/__/____]

Respectfully submitted,

________________________________
[ATTORNEY NAME], MSB No. [_____]
[FIRM NAME]
[ADDRESS / PHONE / EMAIL]
Attorney for Plaintiff

[Concurrently file LIS PENDENS NOTICE per Miss. Code Ann. § 85-7-405(1)(c)(i) and Miss. Code Ann. § 11-47-3]


Part E — Pre-Filing Checklist

Eligibility & Project Classification

☐ Confirmed claimant qualifies under Miss. Code Ann. § 85-7-403 (contractor, sub, materialman, machinist, manufacturer, registered architect/engineer/surveyor/forester)
☐ Determined whether project is residential or commercial
☐ Determined whether claimant has direct contract with GC or owner (affects 30-day sub-sub notice)

Pre-Lien Notices

☐ Single-family subcontractor, materialman, or design professional not in owner privity: Pre-Lien Notice provided at least 10 days before filing (§ 85-7-409)
☐ Non-single-family claimant without contractor privity: 30-day notice given to contractor, or owner if no contractor, within 30 days following first delivery (§ 85-7-407(2))
☐ Method of service: ☐ Certified mail RRR ☐ Personal delivery ☐ Statutory overnight delivery
☐ Affidavits / proofs of service retained

Timing

☐ Calculated 90-day filing deadline from last labor/materials (§ 85-7-405(1)(b))
☐ Calendared 180-day payment-action deadline from anticipated filing date
☐ Confirmed substantial compliance with contract by claimant

Lien Contents (§ 85-7-405(1)(b))

☐ Substantial conformity with statutory form
☐ Lien-expiration notice ("180 DAYS . . .") included verbatim
☐ Owner right-to-contest notice included verbatim
☐ Lien amount accurate after credits/offsets
☐ Claimant name, address, role identified
☐ Owner of record verified (chancery clerk, tax assessor)
☐ Hiring party named
☐ Legal description verified
☐ First and last furnishing dates documented
☐ Verification notarized

Filing

☐ Filed with Chancery Clerk of correct county
☐ Filing fee paid
☐ File-stamped copy retained
☐ Filing date within 90-day window confirmed

Post-Filing Notices (within 2 business days)

☐ True and accurate copy mailed to Owner by registered/certified mail or statutory overnight delivery
☐ If owner is registered entity, sent to recorded address or registered agent
☐ If claimant is not GC, copy also sent to GC or GC's registered agent
☐ Tracking / RRR retained

Foreclosure Calendar

☐ 180-day deadline (or 90 days post-Notice of Contest) calendared
☐ Lis pendens template prepared
☐ Necessary parties identified for joinder: owner, GC, hiring party, mortgagees, other lien claimants

Documentation Retained

☐ Contract / subcontract / purchase orders
☐ Change orders
☐ Itemized invoices, delivery tickets, time sheets
☐ Photographs of work
☐ All correspondence with owner / GC / hiring party regarding payment
☐ All notices, affidavits of service, mailing receipts
☐ File-stamped Claim of Lien


Sources and References

  • Public-domain Official Mississippi Code release 78 — Title 85: https://unicourt.github.io/cic-code-ms/transforms/ms/ocms/r78/gov.ms.code.title.85.html
  • Miss. Code Ann. § 85-7-405 (Creation and declaration): https://unicourt.github.io/cic-code-ms/transforms/ms/ocms/r78/gov.ms.code.title.85.html#t85c07s85-7-405
  • SB 2622 (2014 Reg. Sess.) — Original enactment: https://billstatus.ls.state.ms.us/documents/2014/html/SB/2600-2699/SB2622SG.htm
  • HB 869 (2019 Reg. Sess.) — Current payment-bond substitution text in §§ 85-7-431 and 85-7-432: https://billstatus.ls.state.ms.us/documents/2019/html/HB/0800-0899/HB0869SG.htm
  • Butler Snow — Deadlines for Mechanics' Liens in Mississippi: https://www.butlersnow.com/news-and-events/deadlines-for-mechanics-liens-and-construction-liens-mississippi
  • Mississippi Bar — Robert P. Wise paper on construction liens: https://www.msbar.org/media/3218/rpw-bio-and-paper-for-mba-cle-july-17-2017.pdf
  • Mississippi Secretary of State — Business Services (registered-agent lookup): https://www.sos.ms.gov/business-services
  • Noatex Corp. v. King Constr. of Houston, LLC, 732 F.3d 479 (5th Cir. 2013) — invalidation of former stop-notice statute

Insert Image

Insert Table

Watch Ezel in action (sample case)Choose a plan

All changes saved
Save
Export
Export as DOCX
Export as PDF
Generating PDF...
mechanics_lien_filing_package_ms.pdf
Ready to export as PDF or Word
AI is editing...
Chat
Review

Draft it in the editor

The AI drafts each section from your answers and you review every word. Drafting from scratch takes hours; finish yours for $99 one time.

  • Built on this template
    Uses the Mississippi version and the statutes it cites.
  • Formatted like the template
    Captions, numbering and layout stay intact.
  • AI editing
    Rewrite any section from your own notes.
  • Export as PDF and Word
    Yours to review, sign, or file.
Secure checkout via Stripe
Need to customize this document?

About this template

Last updated
August 25, 2026
Jurisdiction
Mississippi
Category
Real Estate

Legal authority

  • Miss. Code Ann. §§ 85-7-401 et seq. (Construction Liens; created by SB 2622, 2014 Reg. Sess., effective Apr. 11, 2014, replacing former Stop-Notice/Special-Materialmen's-Lien regime)
  • Miss. Code Ann. § 85-7-403 (Persons entitled to lien; substantial compliance with contract)
  • Miss. Code Ann. § 85-7-405 (Creation and declaration; 90-day filing with chancery clerk; required form; 180-day payment-action deadline; owner-notice within 2 business days of filing)
  • Miss. Code Ann. § 85-7-407 (30-day notice for a claimant lacking privity with the contractor; single-family exclusion)
  • Miss. Code Ann. § 85-7-409 (single-family residential Pre-Lien Notice to Owner)
  • Miss. Code Ann. § 85-7-421 (Expiration of lien; 180-day payment-action limitation)
  • Miss. Code Ann. § 85-7-423 (Notice of Contest of Lien — shortens enforcement deadline to 90 days)
  • Miss. Code Ann. § 85-7-415 (Bond to discharge lien)
  • Miss. Code Ann. § 85-7-429 (Knowing false lien; treble-damages and expungement remedies)
  • Miss. Code Ann. § 85-7-431 (Payment-bond substitution for subcontractor and material-supplier liens)

Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.

Not legal advice

This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.

Checked against the law it cites

The statutes this template relies on are listed under Legal authority.

Miss. Code Ann. § 85-7-405(1)(b) (checked August 25, 2026): "The claim must be filed with the chancery clerk of the property county within ninety days after the claimant's last qualifying work or furnishing, and a true and accurate copy must be sent to the owner and, when applicable, the contractor no later than two business days after filing."

Miss. Code Ann. § 85-7-407(2), (4) (checked August 25, 2026): "A claimant without privity with the contractor, or with the owner if there is no contractor, must give the specified notice within thirty days following first delivery; the section does not apply to single-family residential construction."

Miss. Code Ann. §§ 85-7-409(2)-(3) and 85-7-433(5) (checked August 25, 2026): "For single-family residential construction, a subcontractor, materialman, or design professional not in privity with the owner must give the owner a pre-lien written notice at least ten days before filing, substantially in the statutory form."

Draft your Mechanics Lien Filing Package — Mississippi in the editor

Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.