MECHANICS LIEN STATEMENT

State of Kansas

County of [________________________________]


IMPORTANT FILING NOTICE

Kansas mechanics liens are filed with the Clerk of the District Court in the county where the property is located. Under K.S.A. 60-1102, original contractors generally must file within 4 months; under K.S.A. 60-1103, subcontractors and suppliers generally must file within 3 months of the last date of work or materials. For nonresidential property, each statute allows a filing within 5 months if a timely notice of extension is filed and mailed as that statute directs. The lien statement must be verified and include a reasonably itemized claim or an eligible written instrument or promissory note.


I. CLAIMANT INFORMATION

Full Legal Name of Claimant: [________________________________]

Claimant Entity Type:

☐ Individual / Sole Proprietor
☐ Corporation
☐ Limited Liability Company (LLC)
☐ Partnership
☐ Joint Venture
☐ Other: [________________________________]

Claimant Mailing Address (sufficient for service of process):

[________________________________]
[________________________________]
City: [________________________________] State: KS ZIP: [____]

Claimant Phone: [________________________________]

Claimant Email: [________________________________]

Kansas Contractor License (if applicable): [________________________________]

Claimant's Role in the Project:

☐ Original / General Contractor (direct contract with Owner)
☐ Subcontractor
☐ Sub-subcontractor
☐ Material Supplier
☐ Equipment Supplier / Lessor
☐ Laborer
☐ Architect / Engineer
☐ Other: [________________________________]


II. PROPERTY OWNER INFORMATION

Full Legal Name of Property Owner: [________________________________]

Owner Mailing Address:

[________________________________]
[________________________________]
City: [________________________________] State: [____] ZIP: [____]

Owner Phone (if known): [________________________________]


III. GENERAL CONTRACTOR INFORMATION

(If Claimant is not the General Contractor)

General Contractor Name: [________________________________]

General Contractor Address:

[________________________________]
[________________________________]
City: [________________________________] State: [____] ZIP: [____]


IV. HIRING PARTY INFORMATION

(Complete if Claimant was not hired directly by Owner)

Name of Party Who Hired Claimant: [________________________________]

Hiring Party's Relationship:

☐ General Contractor
☐ Subcontractor
☐ Agent / Trustee / Spouse of Owner
☐ Other: [________________________________]

Hiring Party Address:

[________________________________]
[________________________________]
City: [________________________________] State: [____] ZIP: [____]


V. PROPERTY DESCRIPTION

Property Street Address:

[________________________________]
[________________________________]
City: [________________________________], Kansas [____]

County: [________________________________], Kansas

Property Type:

☐ New Residential (to which K.S.A. 60-1103b may apply)
☐ Existing Residential
☐ Commercial
☐ Industrial
☐ Agricultural
☐ Other: [________________________________]

Legal Description of Real Property:

[________________________________]
[________________________________]
[________________________________]
[________________________________]

(Attach Exhibit A for full legal description if additional space is needed)

☐ Exhibit A — Legal Description is attached hereto and incorporated by reference.

Under K.S.A. 60-1103, the lien statement must include a description of the real property.


VI. LIEN STATEMENT

A. Basis for Lien

The undersigned Claimant claims a lien upon the above-described real property for the labor, equipment, material, and/or supplies identified below. Select the applicable basis:

☐ Original contractor under K.S.A. 60-1101: Claimant contracted with the owner or the owner's trustee, agent, or spouse.

☐ Supplier, subcontractor, or other claimant under K.S.A. 60-1103(a): Claimant furnished the work or items under an agreement with the contractor, a subcontractor, or an owner contractor identified above.

B. Nature of Work Performed / Materials Furnished

Type of Improvement:

☐ New Construction
☐ Alteration / Renovation
☐ Repair
☐ Demolition
☐ Other: [________________________________]

C. Reasonably Itemized Statement of Claim

Under K.S.A. 60-1103, the verified statement must show "a reasonably itemized statement and the amount of the claim."

Item / Description of Labor, Equipment, Material, or Supplies Amount
[________________________________] $[________________________________]
[________________________________] $[________________________________]
[________________________________] $[________________________________]
[________________________________] $[________________________________]
[________________________________] $[________________________________]
[________________________________] $[________________________________]
Subtotal $[________________________________]
Less: Payments Received ($[________________________________])
Less: Credits/Offsets ($[________________________________])
TOTAL AMOUNT OF LIEN CLAIMED $[________________________________]

D. Contract Information

Type of Contract:

☐ Written Instrument (attach copy if applicable under K.S.A. 60-1103)
☐ Oral Contract
☐ Implied Contract

If the claim is evidenced by a written instrument, a copy of the written instrument may be attached in lieu of an itemized statement.

Original Contract Price: $[________________________________]

Approved Change Orders: $[________________________________]

Total Adjusted Contract Price: $[________________________________]


VII. DATES OF WORK / FURNISHING

Date Claimant First Furnished Labor, Equipment, Material, or Supplies: [__/__/____]

Date Claimant Last Furnished Labor, Equipment, Material, or Supplies: [__/__/____]


VIII. PRE-LIEN NOTICE COMPLIANCE

A. Notice of Intent to Perform — New Residential Property (K.S.A. 60-1103b)

For new residential property, a lien claimant may only file a lien after title passes to a good-faith purchaser if the claimant has filed a Notice of Intent to Perform prior to the recording of the deed transferring title.

☐ This is new residential property — Notice of Intent to Perform was filed

  • Date Filed: [__/__/____]
  • Filed with: Clerk of the District Court, [________________________________] County

☐ This is new residential property — Notice of Intent to Perform was NOT filed (Lien may not be enforceable against good-faith purchaser)

☐ This is NOT new residential property — K.S.A. 60-1103b does not apply

B. Residential Warning Statement (K.S.A. 60-1103a)

For a covered supplier or subcontractor residential claim exceeding $250, the claimant must have mailed the conforming warning statement to an owner or possess the signed and dated owner acknowledgment described in § 60-1103a. Attach the claimant's affidavit that the warning was properly given.

☐ Section 60-1103a does not apply

☐ Warning mailed to an owner on [DATE]

☐ Signed and dated owner acknowledgment retained

☐ Affidavit of proper warning attached

C. Claimant Role

Subcontractor and supplier lien procedure is governed by K.S.A. 60-1103.

☐ Claimant has a direct contract with the Owner
☐ Claimant is a subcontractor or supplier — K.S.A. 60-1103 applies


IX. FILING DEADLINE COMPLIANCE

Claimant Type Filing Deadline
Original contractor (contract with Owner) Generally 4 months after last furnishing; 5 months for nonresidential property if a compliant notice of extension is filed within 4 months and mailed to the owner by certified and regular mail (K.S.A. 60-1102(c))
Subcontractor or supplier Generally 3 months after last furnishing; 5 months for nonresidential property if a compliant notice of extension is filed within 3 months and mailed to the general contractor or construction manager by certified and regular mail, with a regular-mail copy to the owner if known (K.S.A. 60-1103(e))

Claimant's Applicable Deadline: [__/__/____]

Date of This Filing: [__/__/____]

☐ Claimant confirms this lien statement is being filed within the applicable statutory deadline.


X. VERIFICATION

Verified Statement Under Oath

I, [________________________________], being first duly sworn upon oath, state:

  1. I am the Claimant named above (or the [________________________________] of the Claimant entity).
  2. I have read the foregoing Mechanics Lien Statement and know the contents thereof.
  3. The statements of fact contained therein are true and correct to the best of my knowledge, information, and belief.
  4. The amount claimed, $[________________________________], is justly due and owing after allowing all just credits and offsets.
  5. The itemized statement above is a reasonably accurate accounting of the labor, equipment, material, and/or supplies furnished.

Under K.S.A. 60-1103, the statement must be signed under oath and notarized.

Signature: ________________________________

Printed Name: [________________________________]

Title (if entity): [________________________________]

Date: [__/__/____]


XI. NOTARY ACKNOWLEDGMENT

State of Kansas
County of [________________________________]

Subscribed and sworn to before me this [____] day of [________________], 20[____], by [________________________________], who is personally known to me or who has produced [________________________________] as identification.

Notary Public Signature: ________________________________

Printed Name: [________________________________]

My Commission Expires: [__/__/____]

[NOTARY SEAL]


XII. ENFORCEMENT DEADLINES

CRITICAL: Under K.S.A. 60-1105(a), an action to foreclose the lien generally must be brought within ONE (1) YEAR after the lien statement was filed. If a promissory note was attached to the lien statement in lieu of an itemized statement, the one-year period runs from the note's maturity.

Action Deadline Statute
File Notice of Intent to Perform (new residential only) Before deed is recorded K.S.A. 60-1103b
File lien statement with Clerk of District Court Generally 4 months (original contractor) / 3 months (subcontractor or supplier) after last furnishing; eligible nonresidential extension to 5 months requires the timely notice and mailing described above K.S.A. 60-1102(a), (c); 60-1103(a), (e)
File foreclosure action Generally 1 year after filing lien statement; note-in-lieu exception described above K.S.A. 60-1105(a)

XIII. LIEN RELEASE AND BONDING PROVISIONS

A. Release or Satisfaction After Payment

After a filed lien claim is paid or settled, the parties should obtain and file the release or satisfaction document accepted by the Clerk of the District Court where the lien was filed. K.S.A. Chapter 60, Article 11 does not label § 60-1110 as a general lien-release statute. If the filing being released is a Notice of Intent to Perform for new residential property, K.S.A. § 60-1103b(d) expressly requires the paid or discharged claimant to file a release of the notice and waiver of lien.

B. Bond to Secure Payment and Discharge Lien (K.S.A. 60-1110)

The contractor or owner may execute a bond to the State of Kansas for the use of persons whose lien claims might accrue. Under K.S.A. § 60-1110, the bond is conditioned for payment of all claims in a sum not less than the contract price, or for payment of a disputed claimant's claim in the amount of that claim. The bond must have good and sufficient sureties, be approved by a district judge, and be filed with the clerk. Once approved and filed, covered liens do not attach and already-filed covered liens are discharged. The statute does not prescribe a blanket 150% of lien amount rule.

C. Partial Release

If partial payment is received, document the payment and check with the Clerk of the District Court about the accepted method for recording a partial satisfaction. Identify exactly what claim amount or property is released.


XIV. PRIORITY OF LIEN

Under K.S.A. 60-1101, the lien is preferred to liens or encumbrances subsequent to the claimant's commencement of furnishing at the site. When multiple contracts concern the same improvement, the statute uses the earliest unsatisfied lien's date, changing to the next earliest if that lien is discharged. Check the actual competing interests before stating priority in a foreclosure filing.


XV. ADDITIONAL NOTICES AND DISCLOSURES

  1. Filing Location: Kansas lien statements are filed with the Clerk of the District Court, not the Register of Deeds.
  2. Reasonably Itemized Statement: The lien must include a reasonably itemized statement of the claim or a copy of the written contract.
  3. Address Requirement: The lien statement must include an address sufficient for service of process on the claimant.
  4. Owner Liability: K.S.A. 60-1103(d) generally limits the owner's liability to the original contract price, subject to its specified payment exceptions; do not assume the current unpaid balance is the limit.
  5. New Residential Property: The Notice of Intent to Perform requirement under K.S.A. 60-1103b governs preservation against a good-faith purchaser after title passes.
  6. Claim Accuracy: Confirm the work, amount due, credits, and contracting chain before filing a verified statement.

FILING INSTRUCTIONS

  1. Complete all sections of this Mechanics Lien Statement
  2. Have the Claimant sign under oath before a Notary Public
  3. File the original with the Clerk of the District Court in the county where the property is located
  4. For a claim under K.S.A. 60-1103, serve or mail a copy to an owner, any holder of a recorded equitable interest, and any party obligated to pay, using a method allowed by § 60-1103(c); document delivery or a permitted posting. For residential foreclosure, confirm notice to the recorded equitable-interest holder.
  5. Retain copies for your records
  6. Calendar the 1-year enforcement deadline from the date of filing
  7. Consult with an attorney regarding enforcement well in advance of the deadline

SOURCES AND REFERENCES

  • Kansas Statutes Annotated (K.S.A.) Chapter 60, Article 11 — Liens of Contractors, Subcontractors, and Laborers
  • K.S.A. 60-1101 — Liens of Contractors, Subcontractors, and Laborers
  • K.S.A. 60-1102 — Original-contractor lien statement (four-month period)
  • K.S.A. 60-1103 — Subcontractor and supplier lien statement (three-month period)
  • K.S.A. 60-1103a — Residential Warning Statement
  • K.S.A. 60-1103b — Notice of Intent to Perform (new residential)
  • K.S.A. 60-1105 — Enforcement of Lien (1-year deadline)
  • K.S.A. 60-1110 — Bond to secure payment and discharge covered private-project liens
  • Kansas Judicial Branch: https://www.kscourts.org
  • Kansas Legislature: https://ksrevisor.gov/statutes/chapters/ch60/060_011_0001.html

Insert Image

Insert Table

Watch Ezel in action (sample case)Choose a plan

All changes saved
Save
Export
Export as DOCX
Export as PDF
Generating PDF...
mechanics_lien_claim_ks.pdf
Ready to export as PDF or Word
AI is editing...
Chat
Review

Draft it in the editor

The AI drafts each section from your answers and you review every word. Drafting from scratch takes hours; finish yours for $99 one time.

  • Built on this template
    Uses the Kansas version and the statutes it cites.
  • Formatted like the template
    Captions, numbering and layout stay intact.
  • AI editing
    Rewrite any section from your own notes.
  • Export as PDF and Word
    Yours to review, sign, or file.
Secure checkout via Stripe
Need to customize this document?

About this template

Last updated
November 6, 2026
Citations checked
November 6, 2026
Jurisdiction
Kansas
Category
Real Estate

Legal authority

  • K.S.A. 60-1101 (liens of original contractors)
  • K.S.A. 60-1102 (original-contractor lien statement and filing period)
  • K.S.A. 60-1103 (subcontractor and supplier lien statement and filing period)
  • K.S.A. 60-1103a (residential warning statement)
  • K.S.A. 60-1103b (notice of intent to perform for new residential property)
  • K.S.A. 60-1105 (enforcement of lien)
  • K.S.A. 60-1110 (bond to secure payment and discharge private-project liens)

Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.

Not legal advice

This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.

Checked against the law it cites

A reviewer verified this template's legal citations against the official source on November 6, 2026.

K.S.A. 60-1101 (checked November 6, 2026): "Any person furnishing labor, equipment, material, or supplies used or consumed for the improvement of real property, under a contract with the owner or with the trustee, agent or spouse of the owner, shall have a lien upon the property"

K.S.A. 60-1102(a), (c) (checked November 6, 2026): "within four months after the date material, equipment or supplies, used or consumed was last furnished or last labor performed under the contract a verified statement showing"

K.S.A. 60-1102(c) (checked November 6, 2026): "within five months only if the claimant has filed a notice of extension within four months since last furnishing labor, equipment, materials or supplies to the job site"

K.S.A. 60-1103(a), (c), (e) (checked November 6, 2026): "The lien statement must state the name of the contractor and be filed within three months after the date supplies, material or equipment was last furnished or labor performed by the claimant"

Draft your Mechanics Lien Claim - Kansas in the editor