Mechanic's Lien Deadlines & Notice Requirements in South Carolina
At a glance
| Governing law | S.C. Code Title 29, Ch. 5, "Mechanics' Liens" (§§ 29-5-10 to -440); a statutory scheme tracing to 1869-era acts, amended piecemeal (notice-of-project-commencement and payment-bond provisions added in 1992-2014), not a modern recast lien code |
|---|---|
| Who can claim a lien | Anyone owed a debt for labor performed or materials furnished and actually used in erecting, altering, or repairing a building or structure, or boring/equipping wells, by agreement with or consent of the owner or someone rightfully acting for the owner (§ 29-5-10(a)); separately extended to surveyors (§ 29-5-21(A)), private security guards on-site (§ 29-5-25), construction/demolition debris haulers (§ 29-5-27), landscape-service providers under a written agreement over $5,000 (§ 29-5-26), and equipment/tool renters for reasonable rental value (§ 29-5-22); a contractor must be able to show a required license or registration to file at all (§ 29-5-15(A)) |
| Preliminary notice | No single mandatory pre-work notice for every claimant. A subcontractor, laborer, or materialman with no direct contract with the owner must give the owner written notice of the labor or materials furnished and their value just for the lien to attach against the true owner at all, capped at what the owner still owes the contractor (§ 29-5-40); a sub-subcontractor or supplier one tier further removed must send a more detailed certified/registered-mail notice to avoid having its lien capped at what the contractor owes its own hiring subcontractor (§ 29-5-20(B)); separately, a prime contractor may (but need not) file a Notice of Project Commencement within 15 days of starting work, and skipping it strips the sub-subcontractor notice of its full effect (§ 29-5-23) |
| Deadline to file the lien | 90 days after the claimant's own last day of labor or last materials furnished to both serve the owner and file a sworn statement of account, or the lien is dissolved (§ 29-5-90); one flat deadline for every claimant tier |
| Notice of completion effect | None. Chapter 5 has no owner-recorded notice of completion or substantial completion that shortens any claimant's 90-day deadline; a separate tool, the owner's "notice of nonresponsibility" (§ 29-5-80), only disclaims liability for work the owner didn't authorize and does not shorten any filing deadline |
| Serving the lien on the owner | Bundled into the same 90-day deadline as filing, not a separate later step: the claimant must serve the owner (or, if the owner can't be found, the person in possession, or proceed by sheriff's affidavit of diligent search) within the same 90 days as filing the sworn statement (§ 29-5-90) |
| Deadline to sue to foreclose | 6 months after the claimant ceased laboring on or furnishing labor or material for the project to both commence suit and file a notice of pendency of the action (lis pendens), or the lien is dissolved (§ 29-5-120(A)) |
| Homestead/residential extras | No heightened execution formality for homestead property in Chapter 5 itself. The one residential-specific rule is a narrower carve-out for a single claimant category: a real estate licensee's special commercial-marketing lien under § 29-5-21(B) explicitly cannot attach to residential real estate at all (§ 29-5-21(B)(3)) |
Requirements one by one
Governing law
South Carolina's mechanic's lien statute is Title 29, Chapter 5, "Mechanics' Liens" (§§ 29-5-10 to 29-5-440). Its core provisions trace back to 19th-century acts, and it has been amended piecemeal since, most notably by 1990s-era additions creating the sub-subcontractor notice regime and the Notice of Project Commencement, and by a 2000s-2010s payment-bond statute (§ 29-5-440). It is not built on a modern recast or uniform lien code.
Who can claim
Section 29-5-10(a) gives a lien to anyone "to whom a debt is due for labor performed or furnished or for materials furnished and actually used" in erecting, altering, or repairing a building or structure, or boring and equipping wells, done "by virtue of an agreement with, or by consent of, the owner" or someone rightfully acting for the owner. Later sections extend that reach: surveyors (§ 29-5-21(A)), private security guards on site (§ 29-5-25), construction and demolition debris haulers (§ 29-5-27), landscape-service providers under a written agreement exceeding $5,000 (§ 29-5-26), and anyone renting out tools, machinery, or equipment, to the extent of its reasonable rental value (§ 29-5-22). There's a licensing gate on top: § 29-5-15(A) requires a contractor to prove a required license or registration and record that number on the lien document just to file one.
Preliminary notice
South Carolina doesn't have one universal pre-work notice. Instead, the notice requirement depends on how far removed the claimant is from the owner. A subcontractor, laborer, or materialman working through a contractor rather than directly for the owner must give the owner written notice of "the furnishing of such labor or material and the amount or value thereof" before the lien "shall attach ... as against the true owner" at all — and even then it's capped at "the amount due by the owner on the contract price of the improvement" (§ 29-5-40). A sub-subcontractor or supplier one tier further removed faces a separate, more detailed notice: without a certified- or registered-mail notice covering six specific items (who's claiming, who hired them, what was furnished, the project, the dates, and the amount owed), its lien is capped at whatever the contractor still owes the subcontractor who hired it (§ 29-5-20(B)). Layered on top of both is an optional step for the prime contractor: filing a Notice of Project Commencement within 15 days of starting work (§ 29-5-23). Nothing requires it, but skipping it "render[s] the provisions of Sections 29-5-20(B) and 29-5-60(B) inapplicable" — undercutting the sub-subcontractor notice regime and the proration rules that depend on it.
Deadline to file the lien
Section 29-5-90 gives every claimant, regardless of tier, the same 90 days "after he ceases to labor on or furnish labor or materials for such building or structure" to act, or "such a lien shall be dissolved." Within that window the claimant must file "a statement of a just and true account of the amount due," sworn to and describing the property "sufficiently accurate for identification."
Notice of completion effect
South Carolina has no owner-recorded notice of completion or substantial completion that shortens this deadline. A different tool exists — the owner's "notice of nonresponsibility" under § 29-5-80 — but it does something else entirely: it lets an owner who isn't the one who contracted for particular labor or materials disclaim liability for work "not at the time performed or materials not then furnished," by notifying the person doing that work in writing. It doesn't touch anyone's filing deadline.
Serving the lien on the owner
Service isn't a separate step that follows filing — both happen inside the same 90-day window under § 29-5-90. The claimant must serve "upon the owner or, in the event the owner cannot be found, upon the person in possession," and if neither can be located after a diligent search, the statute lets the claimant substitute a sheriff's affidavit confirming that search in place of service.
Deadline to sue to foreclose
Section 29-5-120(A) gives the claimant six months, measured from the same event that started the 90-day filing clock — when the claimant "ceases to labor on or furnish labor or material for the building or structure" — to both "commence[]" a suit enforcing the lien and file "notice of pendency of the action." Missing either one means "the lien must be dissolved."
Homestead/residential extras
Chapter 5 doesn't add any extra execution formality for homestead property generally — no special written-contract, notarization, or witness rule tied to a residence. The one place residential status changes the outcome at all is narrower than that: the special lien South Carolina gives a real estate licensee for marketing or leasing commercial property under § 29-5-21(B) explicitly "shall not acquire a lien ... upon residential real estate" — a carve-out for that one claimant category, not a rule that touches contractors, subcontractors, or suppliers working on a home.
What trips people up
Because the sub-subcontractor notice under § 29-5-20(B) and the prime contractor's optional Notice of Project Commencement under § 29-5-23 are linked, a sub-subcontractor or supplier can do everything right on their own notice and still find it worth less than expected if the prime contractor never filed the commencement notice — § 29-5-23 says skipping it makes § 29-5-20(B)'s protection "inapplicable." Separately, claimants sometimes assume the 90-day filing deadline and the six-month foreclosure deadline both run from the filing date; they don't — both are measured independently from the claimant's own last day of labor or last materials furnished, not from when the lien statement was recorded.
Common questions
Do I need to send a notice before I even start the job, like in some other states? Not automatically. South Carolina's notices depend on your position in the chain: if you're working through a contractor rather than directly for the owner, § 29-5-40 requires written notice of the work and its value for your lien to attach against the owner at all, and a more removed sub-subcontractor or supplier has its own separate notice under § 29-5-20(B).
Does the 90-day filing deadline run from when the whole project finished, or just from my own work? From your own last day of labor or last materials furnished — § 29-5-90 runs the clock separately for each claimant, not from any project-wide completion date, and South Carolina has no notice-of-completion mechanism that would change that.
I'm a sub-subcontractor — can my lien exceed what the contractor still owes my subcontractor? Only if you sent the certified- or registered-mail notice required by § 29-5-20(B). Without it, your lien is capped at whatever the contractor still owes the subcontractor who hired you, even if you're owed more.
Statutes and sources
- S.C. Code § 29-5-10(a) (who has lien rights) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-15(A) (licensing prerequisite to file) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-21(A) (surveyors) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-21(B)(3) (real estate licensee lien excludes residential real estate) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-22 (equipment rental) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-25 (site security guards) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-26 (landscape services) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-27 (construction debris disposal) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-40 (notice for lien to attach against true owner) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-20(B) (sub-subcontractor/supplier notice, payment cap) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-23 (optional Notice of Project Commencement) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-90 (90-day filing and service deadline) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-80 (owner's notice of nonresponsibility) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
- S.C. Code § 29-5-120(A) (6-month deadline to sue and file lis pendens) — https://www.scstatehouse.gov/code/t29c005.php (accessed 2026-10-06)
Source links
Every statute quoted above, linked, with the date we checked it.
What does South Carolina law mean for your facts?
You just read the general rule. Ask your own question and see which parts of current South Carolina law apply to your situation, with citations you can check.
Opens in Ezel Pro.
- Starts from the statutes this survey is built on
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace