Ohio: Mechanic's Lien Deadlines & Notice Requirements

verified against the statute 2026-07-04 10 statute sources

The short answer

Ohio runs its lien process off an owner-filed 'Notice of Commencement,' not a claimant-filed preliminary notice: once an owner records one, most subcontractors and suppliers must serve a 'Notice of Furnishing' within 21 days of first furnishing labor or material to keep their lien rights. The affidavit of mechanics' lien itself is due within 60 days of last furnishing for a one- or two-family home, or 75 days for anything else, then a copy has to be served on the owner within 30 days after filing. The lien then continues for 6 years, though the owner can force an earlier fight by serving a demand to sue, which cuts that down to 60 days. Home construction and home purchase contracts run on a separate, more owner-protective track.

Governing lawMechanics' and Materialmen's Liens, R.C. Chapter 1311, §§ 1311.01-1311.22 (private-improvement lien scheme; other sections of the same chapter cover public improvements and unrelated lien types)
Who can claim a lien'Original contractor' has a direct contract with the owner (includes a construction manager in privity with the owner); 'subcontractor' is anyone who undertakes any part of the improvement under contract with someone other than the owner, with no fixed tier cap; 'material supplier' and 'laborer' also have lien rights (§ 1311.01, § 1311.02)
Preliminary noticeNo claimant-filed notice before work starts. Instead, the OWNER may record a 'Notice of Commencement' before work begins (§ 1311.04); once one is recorded, most subcontractors and material suppliers (not original contractors, not laborers, not suppliers in direct privity with the owner) must serve a 'Notice of Furnishing' within 21 days of first furnishing labor or material to preserve lien rights (§ 1311.05); if the owner never records a Notice of Commencement, no Notice of Furnishing is required at all
Deadline to file the lien60 days after last furnishing labor or material for a one- or two-family dwelling or a residential condominium unit; 75 days for any other private improvement; 120 days for an oil or gas well lien under § 1311.021 (§ 1311.06(B))
Notice of completion effectNo owner filing shortens any claimant's deadline. The Notice of Commencement is filed BEFORE work starts, not after completion, and only triggers the subcontractor's Notice of Furnishing duty; an owner's post-completion 'affidavit of completion' merely marks the Notice of Commencement expired in the county records and by its own terms does not affect any lien-filing time period (§ 1311.04(T)(4))
Serving the lien on the ownerThe claimant must serve a copy of the recorded lien affidavit on the owner or the owner's designee within 30 days after filing; if service can't be made under the Act's general service-of-process section, the claimant must instead post the copy in a conspicuous place on the property within 10 days after that 30-day period ends (§ 1311.07)
Deadline to sue to forecloseA lien continues in force for 6 years after the affidavit is filed, or until final adjudication if suit is brought within that time (§ 1311.13(C)). The owner or another interested party can force an earlier deadline by serving a written notice to commence suit; the lienholder then has 60 days after completion of that service to sue, or the lien is void (§ 1311.11)
Homestead/residential extrasA 'home construction contract' (improving an owner-occupied single- or double-family dwelling or condo unit) or 'home purchase contract' runs on an entirely separate track: no Notice of Commencement/Notice of Furnishing procedure applies at all, and no contractor, subcontractor, supplier, or laborer has any lien if the owner or purchaser paid the original contractor in full before receiving a copy of the lien affidavit (§ 1311.011); short of full payment, a subcontractor's lien is capped at whatever the owner still owes the original contractor. The 60-day (vs. 75-day) filing deadline for one-/two-family dwellings under § 1311.06(B)(1) is the other residential-specific rule

Compare this rule across all 50 states + DC →

The short answer

Ohio's lien scheme is built around a document the owner files, not one the
claimant sends. Before work starts, an owner may record a "Notice of
Commencement" naming the project, the original contractor, and any lender.
Once one is on file, most subcontractors and material suppliers have to
respond with their own "Notice of Furnishing" within 21 days of first
showing up on the job, or risk losing lien rights for work done before
that window. If the owner never records a Notice of Commencement, no
Notice of Furnishing is required at all. From there, the actual lien
affidavit is due within 60 days of last furnishing on a one- or two-family
home, or 75 days on anything else, and a copy has to reach the owner within
30 days after filing. The lien then sits for up to 6 years unless the owner
speeds things up with a formal demand to sue.

Requirements one by one

Governing law

Ohio's private-improvement lien statute is R.C. Chapter 1311, the
"Mechanics' and Materialmen's Liens" chapter, running from § 1311.01 to §
1311.22. The same numbered chapter also covers public-improvement liens,
animal liens, and several unrelated lien types in later sections, but this
survey covers only the private-works sections.

Who can claim

An "original contractor" has a direct contract with the owner and includes
a "construction manager" who has that same direct privity. A
"subcontractor" is defined broadly as "any person who undertakes to
construct, alter, erect, improve, repair, demolish, remove, dig, or drill
any part of any improvement under a contract with any person other than
the owner" — no fixed tier limit. Material suppliers and laborers get
their own lien rights directly under § 1311.02 as well.

Preliminary notice

Ohio flips the usual script: instead of a claimant sending an early
warning, the owner may record a Notice of Commencement before work begins,
listing the project, the original contractor, and any construction lender.
If one is recorded, most subcontractors and material suppliers — but not
original contractors, laborers, or suppliers already in direct privity
with the owner — must serve a Notice of Furnishing "within twenty-one days
after performing the first labor or work or furnishing the first
materials" to preserve lien rights. And if the owner skips recording a
Notice of Commencement altogether, the statute says plainly that "no
subcontractor or material supplier... has to serve a notice of furnishing
... in order to preserve" lien rights at all — the whole notice step
disappears.

Deadline to file the lien

The affidavit of mechanics' lien is due within one of three windows
depending on the property: 60 days after last furnishing for "a one- or
two-family dwelling or... a residential unit of condominium property," 120
days for an oil or gas well lien, and 75 days for everything else. All
three run from the claimant's own last date of labor, work, or material
furnished — the same trigger regardless of claimant tier.

Notice of completion effect

Ohio has no owner filing that shortens a claimant's deadline. The Notice
of Commencement runs the opposite direction in time — it's filed before
work starts, not after completion — and only starts the subcontractor's
21-day notice clock. An owner can later file an "affidavit of completion"
to mark the Notice of Commencement expired in the county's records, but
the statute says outright that doing so does not "extend the rights of any
party seeking to file an affidavit of mechanic's lien" or "affect any time
periods... set forth in this chapter."

Serving the lien on the owner

Once the affidavit is filed, the claimant "shall serve a copy of the
affidavit on the owner, part owner, or lessee of the improved property or
his designee, within thirty days after filing the affidavit." If service
can't be completed under the Act's general service-of-process rules, the
fallback is to post the copy "in some conspicuous place on the premises of
the improved property within ten days after the expiration of the thirty
days."

Deadline to sue to foreclose

A recorded lien "continue[s] in force for six years after an affidavit is
filed," or until final judgment if suit starts within that time. An owner
or any other interested party can cut that short by formally serving a
"notice to commence suit"; if the lienholder then fails to sue "within
sixty days after completion of service... the lien is void and the
property wholly discharged from the lien."

Homestead/residential extras

Two separate rules apply to residential work. First, the general filing
deadline itself is shorter — 60 days instead of 75 — for "a one- or
two-family dwelling or... a residential unit of condominium property."
Second, and more significant, an owner-occupied "home construction
contract" or a "home purchase contract" is pulled out of the ordinary
scheme entirely: the Notice of Commencement/Notice of Furnishing machinery
doesn't apply at all, and no one — original contractor, subcontractor,
supplier, or laborer — has any lien if the owner or purchaser paid the
original contractor in full before ever receiving a copy of a lien
affidavit. Short of full payment, a subcontractor's lien on a home
construction job is capped at whatever the owner still owes the original
contractor, not the subcontractor's own unpaid balance.

What trips people up

Because Ohio's Notice of Commencement is optional for the owner to file,
subcontractors sometimes assume no notice was filed and skip checking —
but if one was recorded and they miss the 21-day Notice of Furnishing
window, they don't lose the lien outright; the statute only cuts off lien
rights for work performed more than 21 days before the late notice was
served, while work from that point forward stays protected. People also
tend to treat a home renovation the same as any other private job, but the
home-construction track removes the owner's exposure entirely once they've
paid the general contractor in full — a homeowner who pays their
contractor and never gets a lien affidavit copy owes nothing more to an
unpaid subcontractor down the chain.

Common questions

Do I have to send a notice before I start work on a private job in
Ohio?

Only indirectly. There's no claimant-sent pre-work notice. Whether you
need to act at all depends on whether the owner recorded a Notice of
Commencement — if they did, you generally have 21 days from first
furnishing labor or material to send a Notice of Furnishing; if they
didn't, nothing is due.

What if I'm working on someone's house and they paid the general
contractor already?

If it's a "home construction contract" and the owner paid the original
contractor in full before receiving a copy of a lien affidavit, no
subcontractor, supplier, or laborer has any lien at all against that
property for that job.

Can the owner force me to sue faster than the 6-year window?
Yes. Serving a formal notice to commence suit cuts the deadline to 60 days
from completed service; missing that shortened window voids the lien
entirely.

Statutes and sources

  • R.C. 1311.01(D)-(E) (subcontractor/original contractor defined) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.01
    (accessed 2026-07-04)
  • R.C. 1311.02 (who has a lien) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.02
    (accessed 2026-07-04)
  • R.C. 1311.05(A) (21-day Notice of Furnishing) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.05
    (accessed 2026-07-04)
  • R.C. 1311.05(H) (no notice needed if no Notice of Commencement recorded) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.05
    (accessed 2026-07-04)
  • R.C. 1311.06(B) (60/75/120-day filing deadlines) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.06
    (accessed 2026-07-04)
  • R.C. 1311.04(T)(4) (completion affidavit doesn't affect lien deadlines) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.04
    (accessed 2026-07-04)
  • R.C. 1311.07 (30-day service of affidavit on owner) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.07
    (accessed 2026-07-04)
  • R.C. 1311.13(C) (6-year lien duration) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.13
    (accessed 2026-07-04)
  • R.C. 1311.11(B) (60-day notice-to-commence-suit deadline) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.11
    (accessed 2026-07-04)
  • R.C. 1311.011(B)(1) (home construction/purchase contract no-lien-if-paid
    rule) —
    https://codes.ohio.gov/ohio-revised-code/section-1311.011
    (accessed 2026-07-04)

Source links

Every statute quoted above, linked, with the date we checked it.

R.C. 1311.01(D)-(E) · accessed 2026-07-04
R.C. 1311.02 · accessed 2026-07-04
R.C. 1311.05(A) · accessed 2026-07-04
R.C. 1311.05(H) · accessed 2026-07-04
R.C. 1311.06(B) · accessed 2026-07-04
R.C. 1311.04(T)(4) · accessed 2026-07-04
R.C. 1311.07 · accessed 2026-07-04
R.C. 1311.13(C) · accessed 2026-07-04
R.C. 1311.11(B) · accessed 2026-07-04
R.C. 1311.011(B)(1) · accessed 2026-07-04
This page is general legal information about statutory lien deadlines and notice requirements, not legal advice about your situation. Lien statutes are construed strictly and courts routinely enforce their deadlines to the day; missing one step can forfeit lien rights entirely even if the underlying debt is real. Verified against the official statute text on the date shown; confirm current law or consult a licensed attorney in the state before relying on it.