Mechanic's Lien Deadlines & Notice Requirements in New Hampshire

Short answer New Hampshire gives a statutory lien for qualifying labor, design services, or materials under an owner contract (§ 447:2). A person working through an agent, contractor, or subcontractor gives written owner notice under §§ 447:5-6; on construction-mortgage projects, § 447:12-b also calls for notice to the lender. The lien continues for 120 days after services or materials are furnished and may be secured by attachment while it continues (§§ 447:9-10).
State
New Hampshire
Statute checked
October 6, 2026
Sources
10 statutes

At a glance

Governing lawRSA ch. 447, especially §§ 447:5-12-b, governs private building liens; attachment secures the lien under § 447:10.
Who can claim a lienOwner-contract claimants furnishing labor, professional design services, or $15 or more of material (§ 447:2); intermediated claimants under an agent, contractor, or subcontractor subject to notice (§ 447:5).
Preliminary noticeFor an intermediated claimant, give written owner notice before work or materials (§ 447:5); later notice limits the lien to sums then or later due to the intermediary (§ 447:6). Supply a written account as often as every 30 days (§ 447:8); § 447:12-b adds construction-lender notice within 15 business days after the later of posting or starting to furnish.
Deadline to file the lienNo separate lien-recording step in §§ 447:2-10; the lien continues for 120 days after services or materials are furnished and may be secured by attachment while it continues (§§ 447:9-10).
Notice of completion effectSection 447:9 measures the 120-day duration from performance or furnishing; Chapter 447 supplies no owner-recorded completion-notice trigger.
Serving the lien on the ownerIntermediated claimants give the written notice under §§ 447:5-6 and periodic accounts under § 447:8; § 447:12-b adds construction-lender notice, and the chapter prescribes attachment, not service of a recorded lien (§ 447:10).
Deadline to sue to forecloseSecure the lien by attachment while it continues, generally within 120 days after services or materials are furnished (§§ 447:9-10); § 447:11 and § 447:12-a address attachment priority.
Homestead/residential extrasSection 447:2 expressly covers a house or other building; Chapter 447 states no separate homestead filing or notice period for this lien.

Requirements one by one

Who can claim and give notice

Section 447:2(I) gives a lien for qualifying labor, professional design services, and material of at least $15 under a contract with the owner. Subsection II identifies the covered licensed or certified design professions. A person working by contract with the owner's agent, contractor, or subcontractor may claim the same lien by giving the owner or person in charge written notice before furnishing (§ 447:5). Section 447:6 permits later notice, but then limits the lien to amounts then due or later becoming due to the intermediary. A notice-giver must also furnish a written account as often as every 30 days (§ 447:8).

Construction-mortgage lender notice

If a construction mortgage funds the project, § 447:12-b(I) requires the mortgagor or agent to post the lender’s contact details at the jobsite within 10 business days of the mortgage. Under subsection II, a lien claimant must notify that lender in writing within 15 business days after the later of the posting or commencement of furnishing. The notice names the jobsite; failure to give it does not alone invalidate the lien.

Duration and attachment

The lien under §§ 447:2-7 continues for 120 days after services are performed or materials furnished, unless paid sooner (§ 447:9). While it continues, it may be secured by attachment of the property, with the writ and return stating that purpose (§ 447:10). Those sections provide no separate lien-statement recording step or owner-recorded completion-notice trigger.

Attachment priority

Section 447:11 gives an attachment priority over later lien claims, subject to its existing-contract and property-preservation exceptions. Section 447:12-a gives qualified priority over a construction mortgage, with exceptions for specified loan disbursements and affidavits.

Residential property

The building lien in § 447:2 expressly includes a house. The cited chapter does not prescribe a separate residential notice or attachment period. It also covers different claims, including vessel liens in § 447:1 and bond petitions in § 447:18, outside this private building-lien question.

What trips people up

For a claimant working through an intermediary, notice before furnishing under § 447:5 and later notice under § 447:6 protect different amounts. The account duty in § 447:8 continues as often as every 30 days after notice. The 120-day duration in § 447:9 is a window for securing the lien by attachment under § 447:10, rather than a deadline to record a conventional lien statement.

Common questions

Can I give the owner notice after finishing work? Section 447:6 permits later notice, but limits the lien to sums then or later due to the contractor, agent, or subcontractor.

Do I file a lien statement in the land records? Chapter 447 instead describes a lien arising from qualifying work and its preservation through attachment while the lien continues (§§ 447:2, :9-:10).

Statutes and sources

  • RSA 447:1 and RSA 447:18 (other chapter claims): https://gc.nh.gov/rsa/html/XLI/447/447-mrg.htm (accessed 2026-10-06)
  • RSA 447:2 (building lien): https://gc.nh.gov/rsa/html/XLI/447/447-2.htm (accessed 2026-10-06)
  • RSA 447:5 (intermediated claimant notice): https://gc.nh.gov/rsa/html/XLI/447/447-5.htm (accessed 2026-10-06)
  • RSA 447:6 (later notice): https://gc.nh.gov/rsa/html/XLI/447/447-6.htm (accessed 2026-10-06)
  • RSA 447:8 (accounts): https://gc.nh.gov/rsa/html/XLI/447/447-8.htm (accessed 2026-10-06)
  • RSA 447:9 (lien duration): https://gc.nh.gov/rsa/html/XLI/447/447-9.htm (accessed 2026-10-06)
  • RSA 447:10 (attachment): https://gc.nh.gov/rsa/html/XLI/447/447-mrg.htm (accessed 2026-10-06)
  • RSA 447:11 (later liens): https://gc.nh.gov/rsa/html/XLI/447/447-11.htm (accessed 2026-10-06)
  • RSA 447:12-a (mortgage priority): https://gc.nh.gov/rsa/html/XLI/447/447-12-a.htm (accessed 2026-10-06)
  • RSA 447:12-b (construction-mortgage lender notice): https://gc.nh.gov/rsa/html/XLI/447/447-12-b.htm (accessed 2026-10-06)

Source links

Every statute quoted above, linked, with the date we checked it.

RSA 447:1 and RSA 447:18 · accessed 2026-10-06
RSA 447:2 · accessed 2026-10-06
RSA 447:5 · accessed 2026-10-06
RSA 447:6 · accessed 2026-10-06
RSA 447:8 · accessed 2026-10-06
RSA 447:9 · accessed 2026-10-06
RSA 447:10 · accessed 2026-10-06
RSA 447:11 · accessed 2026-10-06
RSA 447:12-a · accessed 2026-10-06
RSA 447:12-b · accessed 2026-10-06
This page is general legal information about statutory lien deadlines and notice requirements, not legal advice about your situation. Lien statutes are construed strictly and courts routinely enforce their deadlines to the day; missing one step can forfeit lien rights entirely even if the underlying debt is real. Verified against the official statute text on the date shown; confirm current law or consult a licensed attorney in the state before relying on it.

What does New Hampshire law mean for your facts?

You just read the general rule. Ask your own question and see which parts of current New Hampshire law apply to your situation, with citations you can check.

Opens in Ezel Pro.

  • Starts from the statutes this survey is built on
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace