Mechanic's Lien Deadlines & Notice Requirements in Massachusetts

Short answer Massachusetts usually requires a recorded notice of contract followed by a recorded statement of account. For contractors and subcontractors, the notice is due by the earliest of 60 days after a substantial-completion notice, 90 days after a termination notice, or 90 days after the specified last work; the account has a separate later deadline. Design professionals and personal laborers follow different filing clocks. A claimant must sue within 90 days after the statement and record an attested complaint within 30 days after filing suit.
State
Massachusetts
Statute checked
October 6, 2026
Sources
15 statutes
Pending legislation could change this.
MA H.1870 (2025–2026) (Accompanied a study order on March 26, 2026; no later action shown): Would add a five-year-from-notice-of-contract clause for one-to-four-unit dwellings to § 8’s statement-of-account deadline list, subject to a homeowner affidavit. track it Status checked October 6, 2026.

At a glance

Governing lawM.G.L. c. 254, §§ 1-33; recorded notices and statements establish and preserve private construction liens
Who can claim a lienWritten owner-contract claimants (§ 2), design professionals (§ 2C), written-contract subcontractors (§ 4), and personal laborers on a limited § 1 route
Preliminary noticeNo universal prework notice; a lower-tier claimant without a direct prime-contractor contract may send a notice of identification within 30 days to avoid the narrower § 4 lien cap
Deadline to file the lienContractor/sub notice: earliest of 60 days after completion notice, 90 after termination notice, or 90 after specified last work (§§ 2, 4); account: 90/120/120 days (§ 8). Design and labor routes differ (§§ 1, 2C, 8)
Notice of completion effectOwner and contractor record a substantial-completion notice (§ 2A); it starts the 60-day contractor/sub/design notice clock and 90-day contractor/sub account clock (§§ 2, 2C, 4, 8)
Serving the lien on the ownerSubcontractor lien attaches after recording its notice of contract and giving the owner actual notice (§ 4); record an attested complaint within 30 days after suit (§ 5)
Deadline to sue to forecloseSue within 90 days after filing the § 8 statement or lien dissolves (§ 11); record attested complaint within 30 days after suit or lien dissolves (§ 5)
Homestead/residential extrasThe cited current filing clocks do not set a separate dwelling-unit period (§§ 2, 4, 8); H.1870 proposes one for statements of account

Requirements one by one

Claimants and first filing

M.G.L. c. 254, §§ 1-33 governs these liens. Section 1 gives a personal laborer a limited lien for up to 30 days of work in the 90 days before the statement is filed (§ 1). A person with a written owner contract may record a notice of contract under § 2; a design professional with a written contract uses § 2C; and a written-contract subcontractor uses § 4. The subcontractor's lien attaches on recording only after the owner receives actual notice of that filing (§ 4).

Notice and statement deadlines

For the § 2 contractor and § 4 subcontractor, the notice of contract is due by the earliest of three events: 60 days after a recorded substantial-completion notice, 90 days after a recorded termination notice, or 90 days after the work specified in the relevant section. Their statement of account has a separate earliest-of clock: 90 days after substantial completion, 120 after termination, or 120 after specified last work (§ 8).

Design professionals have a different notice clock under § 2C: the earlier of 60 days after a recorded substantial-completion notice or 90 days after their last professional services. Section 8 then gives a § 2C claimant 30 days after the last day its notice of contract could be filed to record its statement. A § 1 personal laborer follows that section's 90-day statement window instead of the contractor/subcontractor two-filing timetable (§§ 1, 8).

Notice of identification and completion

Under § 4, a claimant without a direct contract with the original contractor may give that contractor a notice of identification by certified mail within 30 days after starting performance. Without it, the lien is capped by the amount due under the intermediate subcontract when the claimant records its notice. Section 2A has the owner and contractor record a notice of substantial completion and send copies to the listed downstream parties; failure to send copies does not prejudice a good-faith third party relying on the recorded notice.

Enforcement

Section 11 dissolves the lien unless suit starts within 90 days after the § 8 statement. Section 5 also requires an attested copy of the complaint to be recorded within 30 days after suit begins, or the lien dissolves.

What trips people up

The § 8 statement deadline can arrive before the longest last-work period when a completion or termination notice has been recorded. Design professionals should use § 2C and the separate 30-day-after-notice-window statement rule in § 8.

Common questions

Does a lower-tier subcontractor lose its entire lien by missing notice of identification? Section 4 instead limits its amount to what remains due under the intermediate subcontract, if the claimant lacks a direct prime-contractor contract.

Is filing the enforcement lawsuit enough? No. Section 5 also requires the attested complaint to be recorded within 30 days.

Statutes and sources

  • M.G.L. c. 254, §§ 1-33 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254 (accessed 2026-10-06)
  • M.G.L. c. 254, § 1 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section1 (accessed 2026-10-06)
  • M.G.L. c. 254, § 2 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section2 (accessed 2026-10-06)
  • M.G.L. c. 254, § 2A — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section2A (accessed 2026-10-06)
  • M.G.L. c. 254, § 2C — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section2C (accessed 2026-10-06)
  • M.G.L. c. 254, § 4 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section4 (accessed 2026-10-06)
  • M.G.L. c. 254, § 5 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section5 (accessed 2026-10-06)
  • M.G.L. c. 254, § 8 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section8 (accessed 2026-10-06)
  • M.G.L. c. 254, § 11 — https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section11 (accessed 2026-10-06)

Source links

Every statute quoted above, linked, with the date we checked it.

M.G.L. c. 254, §§ 1-33 · accessed 2026-10-06
M.G.L. c. 254, § 1 · accessed 2026-10-06
M.G.L. c. 254, § 2 · accessed 2026-10-06
M.G.L. c. 254, § 2 · accessed 2026-10-06
M.G.L. c. 254, § 2A · accessed 2026-10-06
M.G.L. c. 254, § 2A · accessed 2026-10-06
M.G.L. c. 254, § 2C · accessed 2026-10-06
M.G.L. c. 254, § 2C · accessed 2026-10-06
M.G.L. c. 254, § 4 · accessed 2026-10-06
M.G.L. c. 254, § 4 · accessed 2026-10-06
M.G.L. c. 254, § 4 · accessed 2026-10-06
M.G.L. c. 254, § 4 · accessed 2026-10-06
M.G.L. c. 254, § 5 · accessed 2026-10-06
M.G.L. c. 254, § 8 · accessed 2026-10-06
M.G.L. c. 254, § 11 · accessed 2026-10-06
This page is general legal information about statutory lien deadlines and notice requirements, not legal advice about your situation. Lien statutes are construed strictly and courts routinely enforce their deadlines to the day; missing one step can forfeit lien rights entirely even if the underlying debt is real. Verified against the official statute text on the date shown; confirm current law or consult a licensed attorney in the state before relying on it.

What does Massachusetts law mean for your facts?

You just read the general rule. Ask your own question and see which parts of current Massachusetts law apply to your situation, with citations you can check.

Opens in Ezel Pro.

  • Starts from the statutes this survey is built on
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace