District of Columbia: Mechanic's Lien Deadlines & Notice Requirements

verified against the statute 2026-07-05 8 statute sources

The short answer

In the District of Columbia, the notice that perfects a mechanic's lien and the lien filing itself are the same act: a 'notice of intent' recorded in the land records during construction or within 90 days after the earlier of the project's completion or termination. Only a general contractor in privity with the owner, or a subcontractor, materialman, or laborer directly employed by that contractor, can claim a lien — a sub-subcontractor or a supplier to a supplier cannot. Within 5 business days after recording, the claimant must mail a copy to the owner by certified mail (posting on the property if that mail bounces back); an older, still-valid provision separately lets a subcontractor deliver or post a copy instead, and only lets the owner keep paying the contractor if the subcontractor skips this step. Once recorded, the claimant has 180 days to sue to enforce the lien and must also record a notice of pendency of action within 10 days of filing suit, or the lien dies. D.C.'s homestead exemption protects a resident's entire home from most creditors but expressly does not block a mechanic's lien.

Governing lawD.C. Code Title 40, ch. 3, 'Mechanics, Materialmen, and Contractors' — Subchapter I (General, §§ 40-301.01 to .03) creates the lien and its perfection mechanism; Subchapter II (Subcontractor's Lien, §§ 40-303.01 to .20a) extends and conditions it for subcontractors. An 1901 act, substantially rewritten in 2002 and 2005 to unify the general-contractor and subcontractor notice procedure into one 'notice of intent' filing
Who can claim a lienSection 40-301.01 creates a lien for the contractor who contracted directly with the owner. Section 40-303.01 extends the same rights to anyone directly employed by that contractor — a subcontractor, materialman, or laborer — but only one tier down; a sub-subcontractor or a supplier to a supplier has no lien rights. A subcontractor's lien is capped at what the owner still owes the prime contractor (§ 40-303.02(a)) and is defeated if the owner already paid the prime contractor in full in good faith, unless the subcontractor gave written notice of the amount due first (§ 40-303.02(b)). Chapter 3 itself doesn't bar an unlicensed contractor from claiming a lien
Preliminary noticeNone separate from the lien itself. The 'notice of intent' that perfects the lien (§ 40-301.02) doubles as the only notice D.C. requires — there is no earlier, distinct warning that must go out before or during the work
Deadline to file the lienA notice of intent must be recorded during construction or within 90 days after the earlier of the project's completion or termination (§ 40-301.02(a)(1)) — measured from the whole project's end, not the individual claimant's own last day of work, and the same rule applies to subcontractors, materialmen, and laborers via § 40-303.01. Missing the window terminates the lien by operation of law, and a notice missing any required content item is void outright
Notice of completion effectNone. Chapter 3 has no owner-recorded notice of completion, substantial completion, or termination mechanism; the filing clock runs from the project's actual completion or termination, not from anything the owner files
Serving the lien on the ownerTwo overlapping requirements are both still in force. The modern rule (§ 40-301.02(a)(2)) requires mailing the owner a copy of the recorded notice of intent by certified mail within 5 business days of recording, posting a copy on the property if that mail is returned unclaimed or undelivered. A separate, unamended 1966-era provision for subcontractors specifically (§ 40-303.03) instead requires leaving a copy with the owner or the owner's agent, or posting it if neither can be found; missing that step doesn't forfeit the lien outright — it only lets the owner keep paying the prime contractor, discharging the lien to that extent
Deadline to sue to foreclose180 days after the notice of intent is recorded to file suit enforcing the lien, plus recording a notice of pendency of action within 10 days of filing suit (§ 40-303.13(a)(1)). Missing either deadline terminates the lien, and the statute states the period cannot be extended
Homestead/residential extrasChapter 3 imposes one residential-specific formality: if the project is done under a 'home improvement contract' (a written, Department-of-Buildings-approved-form agreement between the same contractor and homeowner for residential repair or remodeling, § 40-301.03(2)), the claimant must attach a copy to the notice of intent (§ 40-301.02(b)(8)). D.C.'s general homestead exemption shields a debtor's entire residence from attachment, levy, or execution with no dollar cap (§ 15-501(a)(14)) — but the same paragraph expressly exempts mechanic's liens from that protection

Compare this rule across all 50 states + DC →

The short answer

In the District of Columbia, the notice that perfects a mechanic's lien and
the lien filing itself are the same act: a "notice of intent" recorded in
the land records during construction or within 90 days after the earlier of
the project's completion or termination. Only a general contractor in
privity with the owner, or a subcontractor, materialman, or laborer directly
employed by that contractor, can claim a lien — a sub-subcontractor or a
supplier to a supplier cannot. Within 5 business days after recording, the
claimant must mail a copy to the owner by certified mail, posting on the
property if that mail bounces back; a separate, older provision lets a
subcontractor instead deliver or post a copy, and only lets the owner keep
paying the contractor if the subcontractor skips this step. Once recorded,
the claimant has 180 days to sue to enforce the lien and must also record a
notice of pendency of action within 10 days of filing suit, or the lien
dies. D.C.'s homestead exemption protects a resident's entire home from most
creditors but expressly does not block a mechanic's lien.

Requirements one by one

Governing law

D.C.'s mechanic's lien law is D.C. Code Title 40, Chapter 3, "Mechanics,
Materialmen, and Contractors." Subchapter I (§§ 40-301.01 to 40-301.03)
creates the lien and its perfection mechanism; Subchapter II (§§ 40-303.01
to 40-303.20a) extends and conditions it for subcontractors, materialmen,
and laborers. It traces back to an 1901 act of Congress, but 2002 and 2005
amendments substantially rewrote it, unifying what used to be two separate
notice procedures (one for general contractors, one for subcontractors)
into a single "notice of intent" filing that both now share.

Who can claim

Section 40-301.01 creates a lien for "the contractor who contracted with
the owner" — a general or prime contractor in direct privity with the
owner. Section 40-303.01 extends "the same rights... and subject to the
same obligations" to anyone "directly employed by" that contractor: a
subcontractor, materialman, or laborer. That's only one tier down — a
sub-subcontractor or a supplier to a supplier has no lien rights under this
chapter. A subcontractor's lien is capped at whatever the owner still owes
the prime contractor at the time (§ 40-303.02(a)), and is defeated entirely
if the owner already paid the prime contractor in full in good faith,
unless the subcontractor gave the owner written notice of the amount due
while a balance remained (§ 40-303.02(b)). Chapter 3 itself doesn't
independently bar an unlicensed contractor from claiming a lien; it only
requires attaching license and good-standing documentation when perfecting
the notice, "to the extent available under applicable law."

Preliminary notice

None, separate from the lien itself. D.C. doesn't require any warning
before or during the work. The "notice of intent" under § 40-301.02 that
perfects the lien is the only notice the chapter requires, and it's
recorded during or after the work — not before it starts.

Deadline to file the lien

A notice of intent must be recorded "during the construction or within 90
days after the earlier of the completion or termination of the project"
(§ 40-301.02(a)(1)). That's a project-wide deadline, not an individual
one: it runs from when the WHOLE project wraps up, not from any one
claimant's own last day of work, and the same 90-day rule applies to
subcontractors, materialmen, and laborers through § 40-303.01. Missing the
window terminates the lien automatically, and a notice of intent that
doesn't include all the required content — the parties' names and
addresses, the amount claimed, dates of work and material delivery, a
property description, license/good-standing documentation where
applicable, and a sworn statement — is void outright.

Notice of completion effect

None. Chapter 3 gives owners no mechanism to record a notice of completion,
substantial completion, or termination that would shorten anyone's filing
deadline. The 90-day clock runs only from the project's actual completion
or termination, whichever the facts show came first.

Serving the lien on the owner

Two different provisions are both still in force here. The modern rule,
§ 40-301.02(a)(2), requires the claimant to mail the owner a copy of the
recorded notice of intent by certified mail within 5 business days after
recording, and to post a copy on the property if that certified mail comes
back unclaimed or undelivered. A separate, unamended 1966-era provision for
subcontractors specifically, § 40-303.03, instead calls for leaving a copy
with the owner or the owner's agent, or posting it if neither can be found.
Neither provision says that missing this service step — as opposed to
missing the 90-day recording deadline — kills the lien outright; § 40-303.03
says only that until the subcontractor complies, the owner may keep paying
the prime contractor, and the lien is discharged to the extent of those
payments.

Deadline to sue to foreclose

The claimant has 180 days after the notice of intent is recorded to file
suit enforcing the lien, and must also record a notice of pendency of
action within 10 days of filing that suit (§ 40-303.13(a)(1)). Missing
either the 180-day deadline or the 10-day lis pendens deadline terminates
the lien, and the statute says this period cannot be extended.

Homestead/residential extras

Chapter 3 adds one residential-specific formality: if the project is done
under a "home improvement contract" — a written, Department-of-Buildings-
approved-form agreement between the same contractor and homeowner covering
repair or remodeling of residential property, aggregating all such
contracts within any 12-month period (§ 40-301.03(2)) — the claimant must
attach a copy of that contract to the notice of intent (§ 40-301.02(b)(8)).
Separately, D.C.'s general homestead exemption is unusually strong: it
shields a debtor's entire interest in their residence from attachment,
levy, or execution, with no dollar cap at all (§ 15-501(a)(14)). But the
same paragraph carves out exactly this situation by name: "nothing
relative to these exemptions shall impair the following debt instruments
on real property: deed of trust, mortgage, mechanic's lien, or tax lien."

What trips people up

A commercial lien-form template circulating for D.C. cites "D.C. Code
§ 40-303.06" for the 180-day suit deadline and the 10-day notice-of-pendency
requirement — but § 40-303.06 is actually titled "Advance payments" and has
nothing to do with enforcement deadlines; the real provision is § 40-303.13.
Second, the two overlapping service-on-owner rules can be confusing: the
newer certified-mail rule and the older personal-delivery-or-posting rule
for subcontractors are both still on the books, and only the certified-mail
route is spelled out for a general contractor. Third, the 90-day filing
deadline is measured from the WHOLE PROJECT's completion or termination, not
from an individual subcontractor's own last day of work — a sub who
finished early still gets the benefit of the full project timeline. Fourth,
the 180-day enforcement deadline and its 10-day lis pendens companion
cannot be extended for any reason once they start running.

Common questions

Do I need to send a notice before I start work in D.C.?
No. D.C. has no preliminary notice separate from the lien-perfecting notice
of intent, which is recorded during or after the work, not before.

How long do I have to record my lien?
During construction, or within 90 days after the earlier of the project's
completion or termination — whichever comes first for the project as a
whole.

Do I have to serve my lien on the property owner?
Yes. Send a certified-mail copy of the recorded notice of intent within 5
business days of recording, and post a copy on the property if that mail is
returned unclaimed or undelivered.

Can a lien reach an owner's home in D.C.?
Yes. D.C.'s homestead exemption protects a resident's entire home from most
creditors, but it expressly does not block a mechanic's, mortgage, deed of
trust, or tax lien.

Statutes and sources

  • D.C. Code § 40-301.01 (mechanic's lien) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-i/section-40-301-01/
    (accessed 2026-07-05)
  • D.C. Code § 40-303.01 (subcontractor's lien — generally) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-ii/section-40-303-01/
    (accessed 2026-07-05)
  • D.C. Code § 40-303.02 (conditions and limitations; defense of payment) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-ii/section-40-303-02/
    (accessed 2026-07-05)
  • D.C. Code § 40-301.02 (notice of intent; 90-day deadline; contents;
    service) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-i/section-40-301-02/
    (accessed 2026-07-05)
  • D.C. Code § 40-301.03 (definitions, incl. "home improvement contract") —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-i/section-40-301-03/
    (accessed 2026-07-05)
  • D.C. Code § 40-303.03 (notice to owner) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-ii/section-40-303-03/
    (accessed 2026-07-05)
  • D.C. Code § 40-303.13 (when suit to be commenced) —
    https://law.justia.com/codes/district-of-columbia/title-40/chapter-3/subchapter-ii/section-40-303-13/
    (accessed 2026-07-05)
  • D.C. Code § 15-501 (exempt property of householder; homestead) —
    https://code.dccouncil.gov/us/dc/council/code/sections/15-501
    (accessed 2026-07-05)

Source links

Every statute quoted above, linked, with the date we checked it.

D.C. Code § 40-301.01 · accessed 2026-07-05
D.C. Code § 40-303.01 · accessed 2026-07-05
D.C. Code § 40-303.02 · accessed 2026-07-05
D.C. Code § 40-301.02 · accessed 2026-07-05
D.C. Code § 40-301.03 · accessed 2026-07-05
D.C. Code § 40-303.03 · accessed 2026-07-05
D.C. Code § 40-303.13 · accessed 2026-07-05
D.C. Code § 15-501 · accessed 2026-07-05
This page is general legal information about statutory lien deadlines and notice requirements, not legal advice about your situation. Lien statutes are construed strictly and courts routinely enforce their deadlines to the day; missing one step can forfeit lien rights entirely even if the underlying debt is real. Verified against the official statute text on the date shown; confirm current law or consult a licensed attorney in the state before relying on it.