Mechanic's Lien Deadlines & Notice Requirements in District of Columbia

Short answer Record a notice of intent during construction or within 90 days after the earlier of project completion or termination. Direct contractors and people directly employed by them may claim a lien. The recorded notice needs the statutory contents, including applicable license and good-standing documents. Mail the owner a copy by certified mail within 5 business days; a separate provision also directs subcontractors to deliver or post notice and governs later owner payments. Sue within 180 days of recording and record a notice of pendency within 10 days after suit. For home improvement, attach the contract; proof that the owner paid the person engaged for the work can defeat a lien.
State
District of Columbia
Statute checked
October 6, 2026
Sources
12 statutes

At a glance

Governing lawD.C. Code Title 40, Chapter 3, §§ 40-301.01–40-303.20a, provides the private construction lien and its notice and enforcement procedure. Sections 40-301.01 and 40-303.01 cover direct contractors and people directly employed by them; § 47-2883.03 adds a home-improvement payment defense.
Who can claim a lienThe contractor who contracted with the owner may claim under § 40-301.01. Section 40-303.01 gives the same rights and obligations, subject to chapter limits, to a subcontractor, materialman, or laborer directly employed by that contractor. Section 40-303.02(a) limits those downstream liens to the unpaid amount due or to become due to the original contractor. Good-faith full payment to the original contractor bars a downstream lien under § 40-303.02(b); a downstream claimant's written notice of an amount due while sufficient owner funds remain is prima facie evidence that later payment to the original contractor was not in good faith. Under § 40-301.02(b)(7), the recorded notice must include applicable current business-license and good-standing documents to the extent available under applicable law; § 40-301.02(a)(1) voids a notice that fails subsection (b).
Preliminary noticeSections 40-301.02 and 40-303.01 establish no separate prework notice as a condition for recording the lien: the notice of intent is recorded during construction or within 90 days after the earlier of completion or termination. A subcontractor, materialman, or supplier may separately notify the owner in writing of an amount due while sufficient funds remain; § 40-303.02(b) makes that notice prima facie evidence against good faith for later payments to the original contractor.
Deadline to file the lienRecord the notice of intent during construction or within 90 days after the earlier of completion or termination of the project (§ 40-301.02(a)(1)). The same obligation applies to directly employed subcontractors, materialmen, and laborers through § 40-303.01. A late recording terminates the lien; a notice lacking the subsection (b) content is void.
Notice of completion effectSection 40-301.02(a)(1) measures the 90 days from actual project completion or termination and prescribes no owner-recorded notice that shortens that period.
Serving the lien on the ownerUnder § 40-301.02(a)(2), mail a copy of the recorded notice of intent to the owner by certified mail within 5 business days of recording; post a copy at the property if the mail is returned unclaimed or undelivered. Section 40-303.01 subjects direct subcontractors to that same obligation. Section 40-303.03 additionally directs a subcontractor or other person employed by the contractor to leave a copy with the owner or resident agent, or post it if neither can be found. Until that step is done, the owner may pay the original contractor under the contract and reduce the downstream lien to the extent of those payments.
Deadline to sue to forecloseFile suit to enforce the lien within 180 days after recording a valid notice of intent, then record a notice of pendency of action within 10 days after filing suit (§ 40-303.13(a)(1)). Failure to meet either deadline terminates the lien (§ 40-303.13(a)(2)).
Homestead/residential extrasIf work is under a home improvement contract as defined in § 40-301.03(2), attach a copy to the recorded notice (§ 40-301.02(b)(8)). For home improvement work, proof that the owner or occupant paid the person offering to perform or arrange the work is a defense that voids a lien under § 47-2883.03. Section 15-501(a)(14) exempts the debtor's residential real-property interest from execution but expressly preserves a mechanic's lien.

Requirements one by one

Governing law

D.C. Code Title 40, Chapter 3 creates and governs these liens. Section 40-301.01 covers the contractor who contracted with the owner. Section 40-303.01 extends the chapter's rights and obligations to people directly employed by that contractor. Section 47-2883.03 adds a payment defense for home-improvement work.

Who can claim

The owner-contracting contractor may claim a lien (§ 40-301.01). A subcontractor, materialman, or laborer directly employed by that contractor has the same chapter rights and obligations (§ 40-303.01). A downstream lien is limited to the amount due or to become due but unpaid to the original contractor (§ 40-303.02(a)). Good-faith payment of the original contractor in full defeats a downstream lien; a claimant's written notice of an amount due while sufficient owner funds remain supplies prima facie evidence that later payment was not in good faith (§ 40-303.02(b)).

The recorded notice must include applicable current business-license and good-standing documents, to the extent available under applicable law (§ 40-301.02(b)(7)). A notice that does not comply with subsection (b) is void (§ 40-301.02(a)(1)).

Preliminary notice

The cited filing provisions impose no separate prework notice before recording the notice of intent during construction or within 90 days after the earlier of completion or termination (§§ 40-301.02(a)(1), 40-303.01). A subcontractor, materialman, or supplier may give the owner a written notice of the amount due while sufficient funds remain. That notice affects the good-faith payment defense for later owner payments (§ 40-303.02(b)).

Deadline to file the lien

Record a notice of intent during construction or within 90 days after the earlier of project completion or termination (§ 40-301.02(a)(1)). This chapter-wide obligation reaches direct subcontractors through § 40-303.01. Missing the recording window terminates the lien; omitting required subsection (b) contents makes the notice void.

Notice of completion effect

Section 40-301.02(a)(1) uses project completion or termination as the trigger. It provides no owner-recorded notice that shortens the 90-day period.

Serving the lien on the owner

Section 40-301.02(a)(2) requires certified mailing of a copy of the recorded notice to the owner within 5 business days after recording. If returned unclaimed or undelivered, post a copy where generally visible from an entry point. Direct subcontractors share that duty under § 40-303.01.

Section 40-303.03 also directs a subcontractor or other person employed by the original contractor to leave a copy with the owner or resident agent, or post it if neither can be found. Until that step is completed, the owner may continue contractual payments to the original contractor, reducing the downstream lien to that extent. The section does not make personal delivery an alternative to § 40-301.02(a)(2)'s certified mailing.

Deadline to sue to foreclose

File suit within 180 days after recording the valid notice of intent, then record a notice of pendency within 10 days after filing suit. Missing either step terminates the lien (§ 40-303.13(a)).

Homestead/residential extras

If the project is under a home improvement contract, attach that contract to the notice (§§ 40-301.02(b)(8), 40-301.03(2)). For home improvement work, proof that the owner or occupant paid the person offering to perform or arrange the work is a defense that voids the lien (§ 47-2883.03). Section 15-501(a)(14) exempts residential real-property interests from execution but expressly preserves mechanic's liens.

What trips people up

The recorded notice has required contents beyond the amount and property description, including applicable license and good-standing documents (§ 40-301.02(b)). Direct subcontractors share the certified-mail obligation and have the separate § 40-303.03 delivery or posting rule. The enforcement deadline is in § 40-303.13; § 40-303.06 addresses advance payments.

Common questions

When must I record the notice? During construction or within 90 days after the earlier of project completion or termination (§ 40-301.02(a)(1)).

Must I notify the owner after recording? Yes. Certified-mail a copy within 5 business days; post it if the mail is returned. Direct subcontractors should also account for § 40-303.03's delivery or posting rule (§§ 40-301.02(a)(2), 40-303.01, 40-303.03).

Can a home-improvement lien survive payment to the person engaged for the work? Section 47-2883.03 makes proof of that payment a defense that voids the lien.

Statutes and sources

  • D.C. Code § 40-301.01 — https://code.dccouncil.gov/us/dc/council/code/sections/40-301.01 (accessed 2026-10-06)
  • D.C. Code § 40-303.01 — https://code.dccouncil.gov/us/dc/council/code/sections/40-303.01 (accessed 2026-10-06)
  • D.C. Code § 40-303.02 — https://code.dccouncil.gov/us/dc/council/code/sections/40-303.02 (accessed 2026-10-06)
  • D.C. Code § 40-301.02 — https://code.dccouncil.gov/us/dc/council/code/sections/40-301.02 (accessed 2026-10-06)
  • D.C. Code § 40-301.02(b)(7) — https://code.dccouncil.gov/us/dc/council/code/sections/40-301.02 (accessed 2026-10-06)
  • D.C. Code § 40-301.02(b)(8)-(9) — https://code.dccouncil.gov/us/dc/council/code/sections/40-301.02 (accessed 2026-10-06)
  • D.C. Code § 40-301.03 — https://code.dccouncil.gov/us/dc/council/code/sections/40-301.03 (accessed 2026-10-06)
  • D.C. Code § 40-303.03 — https://code.dccouncil.gov/us/dc/council/code/sections/40-303.03 (accessed 2026-10-06)
  • D.C. Code § 40-303.06 — https://code.dccouncil.gov/us/dc/council/code/sections/40-303.06 (accessed 2026-10-06)
  • D.C. Code § 40-303.13 — https://code.dccouncil.gov/us/dc/council/code/sections/40-303.13 (accessed 2026-10-06)
  • D.C. Code § 47-2883.03 — https://code.dccouncil.gov/us/dc/council/code/sections/47-2883.03 (accessed 2026-10-06)
  • D.C. Code § 15-501 — https://code.dccouncil.gov/us/dc/council/code/sections/15-501 (accessed 2026-10-06)

Source links

Every statute quoted above, linked, with the date we checked it.

D.C. Code § 40-301.01 · accessed 2026-10-06
D.C. Code § 40-303.01 · accessed 2026-10-06
D.C. Code § 40-303.02 · accessed 2026-10-06
D.C. Code § 40-301.02 · accessed 2026-10-06
D.C. Code § 40-301.02(b)(7) · accessed 2026-10-06
D.C. Code § 40-301.02(b)(8)-(9) · accessed 2026-10-06
D.C. Code § 40-301.03 · accessed 2026-10-06
D.C. Code § 40-303.03 · accessed 2026-10-06
D.C. Code § 40-303.06 · accessed 2026-10-06
D.C. Code § 40-303.13 · accessed 2026-10-06
D.C. Code § 47-2883.03 · accessed 2026-10-06
D.C. Code § 15-501 · accessed 2026-10-06
This page is general legal information about statutory lien deadlines and notice requirements, not legal advice about your situation. Lien statutes are construed strictly and courts routinely enforce their deadlines to the day; missing one step can forfeit lien rights entirely even if the underlying debt is real. Verified against the official statute text on the date shown; confirm current law or consult a licensed attorney in the state before relying on it.

What does District of Columbia law mean for your facts?

You just read the general rule. Ask your own question and see which parts of current District of Columbia law apply to your situation, with citations you can check.

Opens in Ezel Pro.

  • Starts from the statutes this survey is built on
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace