Discharge and Release of Construction Lien - Michigan
DISCHARGE AND RELEASE OF CONSTRUCTION LIEN
(Michigan — Construction Lien Act, MCL 570.1101 et seq.)
IMPORTANT: Michigan calls these "construction liens" — not "mechanics' liens." The governing statute is the Construction Lien Act (MCL 570.1101-570.1305). Claims of lien are recorded with the Register of Deeds. Discharge by bond requires filing with the County Clerk and then recording a certificate with the Register of Deeds. The bond amount must be twice (2x) the lien amount.
FORM 1: FULL DISCHARGE OF CONSTRUCTION LIEN
(After Full Payment — Recording with Register of Deeds)
DISCHARGE OF CONSTRUCTION LIEN
STATE OF MICHIGAN
COUNTY OF [________________________________]
FOR RECORDING WITH THE REGISTER OF DEEDS, [________________________________] COUNTY
Construction Lien Information
| Field | Detail |
|---|---|
| Lien Claimant: | [________________________________] |
| Claimant's Address: | [________________________________] |
| Claimant's Role: | ☐ General Contractor ☐ Subcontractor ☐ Laborer ☐ Supplier ☐ Sub-subcontractor ☐ Design Professional ☐ Other: [________________] |
| Property Owner: | [________________________________] |
| Owner's Address: | [________________________________] |
| Designee (if applicable): | [________________________________] |
| Property Address: | [________________________________] |
| City/Township: | [________________________________] |
| County: | [________________________________] |
| Legal Description: | [________________________________] |
| Tax Parcel ID: | [________________________________] |
| Register of Deeds Office: | [________________________________] County |
| Liber: | [________________________________] |
| Page: | [________________________________] |
| Document Number: | [________________________________] |
| Date Claim of Lien Recorded: | [__/__/____] |
| Original Lien Amount: | $[________________________________] |
| Nature of Improvement: | [________________________________] |
Discharge Declaration
The undersigned Lien Claimant hereby declares and certifies:
-
Resolution Basis. The Claimant confirms the following documented basis for clearing the recorded Claim of Lien: ☐ full payment received and cleared ☐ settlement performed ☐ correction of an erroneous filing ☐ other counsel-approved basis: [________________________________].
-
Construction Lien Discharged. The Claim of Lien recorded at Liber [________________________________], Page [________________________________] (or Document No. [________________________________]) in the [________________________________] County Register of Deeds is hereby fully discharged, released, and satisfied.
-
Payment and Waiver Coordination. If Claimant received full payment for its contract, Claimant has provided the full unconditional waiver required by MCL 570.1115(2), using substantially the statutory form.
-
Scope. This instrument clears only the recorded Claim of Lien identified above. Any separate contract, bond, or other claim is affected only if expressly stated in a signed settlement reviewed by counsel: [________________________________].
-
Lis Pendens. ☐ A Notice of Lis Pendens was recorded in connection with this lien and requires separate attorney review for discharge. ☐ No Notice of Lis Pendens was recorded. The automatic lis-pendens discharge in MCL 570.1116 applies when the county clerk's bond certificate is recorded.
Claimant Signature
Signed this [____] day of [________________], 20[____].
LIEN CLAIMANT:
Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Michigan License No. (if applicable): [________________________________]
Acknowledgment
STATE OF MICHIGAN
COUNTY OF [________________________________]
On this [____] day of [________________], 20[____], before me, the undersigned Notary Public, personally appeared [________________________________], known to me (or proved to me through satisfactory evidence of identification) to be the person whose name is subscribed to the foregoing instrument, and acknowledged that he/she executed the same for the purposes therein stated.
Notary Public: ______________________________
Printed Name: [________________________________]
County of [________________________________], State of Michigan
My Commission Expires: [__/__/____]
Acting in the County of: [________________________________]
FORM 2: PARTIAL UNCONDITIONAL WAIVER OF CONSTRUCTION LIEN
(MCL 570.1115 — After Partial Payment; Use the Statutory Format)
PARTIAL UNCONDITIONAL WAIVER
STATE OF MICHIGAN
COUNTY OF [________________________________]
I/we have a contract with [________________________________] to provide [________________________________] for the improvement to the property described as [________________________________], and by signing this waiver waive my/our construction lien to the amount of $[________________________________], for labor/materials provided through [__/__/____].
This waiver, together with all previous waivers, if any, (circle one) does / does not cover all amounts due to me/us for contract improvement provided through the date shown above.
If the improvement is provided to property that is a residential structure and if the owner or lessee or the owner's or lessee's designee has received a notice of furnishing from me/one of us or if I/we are not required to provide one, and the owner, lessee, or designee has not received this waiver directly from me/one of us, the owner, lessee, or designee may not rely upon it without contacting me/one of us, either in writing, by telephone, or personally, to verify that it is authentic.
LIEN CLAIMANT:
Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Address: [________________________________]
Telephone: [________________________________]
Signed on: [__/__/____]
DO NOT SIGN BLANK OR INCOMPLETE FORMS. RETAIN A COPY.
FORM 3: DISCHARGE OF CONSTRUCTION LIEN BY BOND
(MCL 570.1116 — Bond Filed with County Clerk)
IMPORTANT: Michigan requires the bond to be filed with the County Clerk (not Register of Deeds). The bond must be in the penal sum of twice (2x) the claimed lien amount. After the County Clerk approves the bond and issues a certificate, the certificate is recorded with the Register of Deeds to discharge the lien.
PART A: BOND TO DISCHARGE CONSTRUCTION LIEN
BOND TO DISCHARGE CONSTRUCTION LIEN
MCL 570.1116
Filed with the County Clerk, [________________________________] County, Michigan
| Field | Detail |
|---|---|
| Principal (Person Filing Bond): | [________________________________] |
| Principal's Address: | [________________________________] |
| Obligee (Lien Claimant): | [________________________________] |
| Obligee's Address: | [________________________________] |
| Property Owner: | [________________________________] |
| Property Address: | [________________________________] |
| Legal Description: | [________________________________] |
| County: | [________________________________] |
| Liber/Page or Document No. of Claim of Lien: | [________________________________] |
| Date Claim of Lien Recorded: | [__/__/____] |
| Amount Claimed in Lien: | $[________________________________] |
Bond
KNOW ALL PERSONS BY THESE PRESENTS:
That [________________________________] ("Principal") and [________________________________] ("Surety"), a surety company authorized to transact surety business in the State of Michigan, are held and firmly bound unto [________________________________] ("Obligee"), the lien claimant named in the Claim of Lien described above, in the penal sum of:
$[________________________________]
(Must be TWICE the amount of the lien claim: $[________________________________] x 2 = $[________________________________])
for the payment of which sum, well and truly to be made, the Principal and Surety bind themselves, their heirs, executors, administrators, successors, and assigns, jointly and severally.
Condition
THE CONDITION OF THIS BOND IS: This bond is conditioned upon the payment of any sum for which the Obligee may obtain judgment on the claim for which the Claim of Lien was filed.
If the Principal or Surety shall pay any such sum as determined by judgment of a court of competent jurisdiction, then this obligation shall be void; otherwise it shall remain in full force and effect.
Execution
Signed and sealed this [____] day of [________________], 20[____].
PRINCIPAL:
Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
SURETY:
Signature: ______________________________
Printed Name: [________________________________]
Title: [________________________________]
Company: [________________________________]
Michigan Agent: [________________________________]
(Attach Power of Attorney for surety signatory)
PART B: REQUEST FOR CERTIFICATE FROM COUNTY CLERK
TO THE COUNTY CLERK, [________________________________] COUNTY, MICHIGAN:
Pursuant to MCL 570.1116, the undersigned has filed a bond with this office to discharge the Claim of Lien described above.
Notice to Lien Claimant: The Lien Claimant (Obligee) has been notified of the filing of this bond and has 10 days from notification to file an objection to the sufficiency of the surety.
☐ The 10-day objection period has expired and no objection was filed.
☐ An objection was filed, and the County Clerk has examined the surety and approved the bond.
REQUEST: The undersigned requests that the County Clerk issue a Certificate stating:
- A good and sufficient bond has been filed in accordance with the Construction Lien Act;
- The names of the obligor and obligee;
- The amount of the bond;
- The description of the property covered by the Claim of Lien being discharged.
PRINCIPAL:
Signature: ______________________________
Date: [__/__/____]
PART C: COUNTY CLERK'S CERTIFICATE
(Issued by County Clerk after bond approval — to be recorded at Register of Deeds)
COUNTY CLERK'S CERTIFICATE
MCL 570.1116
COUNTY OF [________________________________], MICHIGAN
I, [________________________________], County Clerk of [________________________________] County, Michigan, do hereby certify that:
-
A bond has been filed in this office in accordance with the Construction Lien Act, MCL 570.1116;
-
The names of the parties are:
- Obligor (Principal): [________________________________]
- Obligee (Lien Claimant): [________________________________]
-
The bond is in the penal sum of: $[________________________________]
-
The bond is conditioned upon payment of any sum for which the Obligee may obtain judgment on the claim for which the Claim of Lien was filed;
-
The property covered by the Claim of Lien being discharged is described as:
[________________________________]
[________________________________] -
The Claim of Lien is recorded in the Register of Deeds for [________________________________] County at Liber [________________________________], Page [________________________________] (or Document No. [________________________________]).
Upon recording this Certificate with the Register of Deeds, the Claim of Lien of the above-named Obligee shall be discharged. If a Notice of Lis Pendens has been recorded, the recording of this Certificate shall also operate as a discharge of the Lis Pendens.
Given under my hand and the seal of the County Clerk this [____] day of [________________], 20[____].
______________________________
County Clerk, [________________________________] County
[SEAL]
FORM 4: DEMAND FOR DISCHARGE OF CONSTRUCTION LIEN
(Letter Demanding Lien Claimant Release After Payment)
[LETTERHEAD OR SENDER INFORMATION]
Date: [__/__/____]
VIA CERTIFIED MAIL, RETURN RECEIPT REQUESTED
[________________________________]
[________________________________]
[________________________________]
RE: DEMAND FOR DISCHARGE OF CONSTRUCTION LIEN
Property: [________________________________]
Register of Deeds: [________________________________] County
Liber/Page: [________________________________]
Date Recorded: [__/__/____]
Lien Amount: $[________________________________]
Dear [________________________________]:
This firm represents [________________________________] ("Owner"), the owner of the above-referenced property. We request review and appropriate action concerning the recorded construction lien identified above.
GROUNDS FOR DEMAND
☐ Full Payment. The obligation giving rise to your construction lien has been paid in full. Payment of $[________________________________] was made on [__/__/____]. Your lien has been satisfied.
☐ Failure to Enforce. No timely foreclosure action appears in the reviewed court and recording records. MCL 570.1117(1) bars commencement later than one year after recording. Counsel has evaluated the county-clerk certificate and recording route recognized by MCL 570.1112(1), if available, rather than assuming this private letter alone cancels the instrument.
☐ Foreclosure Prerequisite. If applicable, the complaint, cross-claim, or counterclaim must show that the owner or lessee received a sworn statement requested or required under MCL 570.1110. MCL 570.1117(7).
☐ Other Validity Defect. The Claim of Lien lacks a statutory prerequisite or includes an unsupported amount because: [________________________________]. Obtain Michigan counsel's analysis of the available contract, tort, declaratory, quiet-title, or other remedy.
☐ Other Ground: [________________________________].
IMPORTANT STATUTORY LIMIT: MCL 570.1121 governs the judgment and sale procedure after foreclosure; it does not create a wrongful-lien civil penalty. MCL 570.1118(2) permits reasonable attorney fees to a prevailing lien claimant and permits fees to a prevailing defendant only if the foreclosure action was vexatious. Do not threaten a statutory penalty that the Construction Lien Act does not provide.
DEMAND
You are requested to review the enclosed payment and recording records, provide any correction, release, or statutory waiver that is appropriate, and cooperate in a counsel-approved record-clearing process by [__/__/____]. No fixed response period is asserted under the Construction Lien Act.
CONSEQUENCES OF NON-COMPLIANCE
Failure to comply will result in:
- Filing a cash or surety bond under MCL 570.1116 and recording the county clerk's certificate;
- Seeking available judicial relief after Michigan counsel identifies the proper claim and procedure;
- Pursuit of all other available legal and contractual remedies.
Very truly yours,
______________________________
[________________________________]
Attorney for [________________________________]
Michigan Bar No. (P[________________________________])
Address: [________________________________]
FORM 5: ATTORNEY-REVIEW INTAKE FOR JUDICIAL RELIEF
(Attorney intake only — not a court filing)
STATE OF MICHIGAN
IN THE CIRCUIT COURT FOR THE COUNTY OF [________________________________]
CASE NO.: [________________________________]
[________________________________],
Plaintiff / Property Owner,
v.
[________________________________],
Defendant / Lien Claimant.
FACTS FOR COUNSEL TO EVALUATE BEFORE FILING
Do not file this section as a complaint without Michigan counsel's revision. The Construction Lien Act expressly supplies foreclosure and bond-discharge procedures but does not create the generic wrongful-lien penalty claim formerly stated in this packet.
I. PARTIES AND JURISDICTION
-
Plaintiff is the owner of real property located at [________________________________], in the [☐ City ☐ Township] of [________________________________], County of [________________________________], State of Michigan.
-
Defendant is [________________________________], who recorded a Claim of Lien against Plaintiff's property.
-
Proposed jurisdictional and remedial basis identified by counsel: [________________________________]. MCL 570.1118 places a construction-lien foreclosure action in circuit court in a county where the property is located, but it does not itself create a freestanding owner cancellation complaint.
II. THE CONSTRUCTION LIEN
-
On [__/__/____], Defendant recorded a Claim of Lien with the Register of Deeds for [________________________________] County at Liber [________________________________], Page [________________________________] (or Document No. [________________________________]).
-
The Claim of Lien alleges an amount of $[________________________________] for [________________________________] [describe nature of work/materials].
III. GROUNDS FOR DISCHARGE
- The construction lien should be discharged because:
☐ a. Full Payment. The obligation has been paid in full. Payment of $[________________________________] was made on [__/__/____]. Defendant refuses to record a discharge.
☐ b. Failure to Foreclose Within One Year. Defendant failed to commence a foreclosure action within one (1) year after recording the Claim of Lien, as required by MCL 570.1117(1). The one-year period expired on [__/__/____].
☐ c. Other Validity Defect. The Claim of Lien allegedly lacks a statutory prerequisite because: [________________________________].
☐ d. Excessive Amount. The lien includes a greater amount than the sum due. The actual amount due is $[________________________________].
☐ e. Failure to Comply with Prerequisites. Defendant failed to comply with one or more prerequisites for a valid construction lien: [________________________________].
IV. CLAIMS AND RELIEF FOR COUNSEL TO EVALUATE
- By reason of the wrongfully maintained construction lien, Plaintiff has suffered:
☐ Actual damages: $[________________________________]
☐ Lost sale or refinancing opportunity: $[________________________________]
☐ Attorney fees and court costs: $[________________________________]
- Potential legal theories and requested relief, with supporting authority: [________________________________]. MCL 570.1121 itself is foreclosure-sale procedure, not a damages or penalty provision.
V. PROPOSED RELIEF FOR COUNSEL'S REVIEW
Potential relief for counsel's review, only if supported by an identified cause of action and current authority:
A. Appropriate declaratory, record-clearing, bond, or other relief concerning the Claim of Lien recorded at Liber [________________________________], Page [________________________________], in the [________________________________] County Register of Deeds;
B. Any order concerning the Register of Deeds that the identified statute, rule, or claim authorizes;
C. Actual damages in the amount of $[________________________________];
D. Attorney fees and court costs only under an identified contract, statute, rule, or other valid basis;
E. Any relief supported by the claims and authorities counsel identifies;
F. Such other and further relief as this Court deems just.
Respectfully submitted,
______________________________
[________________________________]
Attorney for Plaintiff
Michigan Bar No. (P[________________________________])
Address: [________________________________]
Telephone: [________________________________]
Email: [________________________________]
VERIFICATION
I, [________________________________], declare under penalty of perjury that the information supplied in this attorney-review intake is true to the best of my information, knowledge, and belief.
Signature: ______________________________
Date: [__/__/____]
RECORDING INSTRUCTIONS — MICHIGAN
Where to Record and File
| Document | Filed With | Notes |
|---|---|---|
| Claimant-executed release / discharge instrument | Register of Deeds, county where the Claim of Lien was recorded | Form and acceptance requirements must be confirmed with counsel and the county; MCL 570.1115 separately governs statutory waivers |
| Bond to Discharge Lien | County Clerk, county where property is located | NOT the Register of Deeds |
| County Clerk's Certificate | Register of Deeds, after County Clerk issues it | This actually discharges the lien |
| Foreclosure action | Circuit Court, county where property is located | MCL 570.1118; this packet does not supply a ready-to-file owner cancellation complaint |
Document Requirements
☐ County acceptance requirements confirmed for the specific instrument
☐ Signature, acknowledgment, return-address, preparer, margin, transfer-tax, and recording requirements confirmed
☐ Original Claim of Lien identified accurately by county and instrument / liber and page
☐ Property description and parcel information included if required for acceptance
☐ Recording fee (contact county Register of Deeds for current fee)
☐ For bonds: attach Power of Attorney for surety signatory
Michigan-Specific Recording Notes
☐ Michigan uses Liber and Page references (some counties have transitioned to Document Numbers)
☐ The Register of Deeds and County Clerk are separate offices
☐ Bonds go to County Clerk; discharges go to Register of Deeds
☐ The County Clerk's Certificate, once recorded at the Register of Deeds, discharges both the Claim of Lien and any recorded Notice of Lis Pendens
STATUTORY DEADLINES AND BOND REQUIREMENTS — MICHIGAN
| Item | Requirement | Citation |
|---|---|---|
| Recording Claim of Lien | 90 days after last furnishing labor/materials | MCL 570.1111(1) |
| Sworn Statement | Contractor: when payment is due or requested and on owner/lessee demand; subcontractor duties and enforcement gates vary | MCL 570.1110 |
| Foreclosure Action | Not later than 1 year after recording Claim of Lien | MCL 570.1117(1) |
| Bond Amount | Twice (2x) the amount of the lien claim | MCL 570.1116 |
| Surety Objection Period | 10 days after lien claimant receives notice of bond | MCL 570.1116 |
| Notice of Furnishing | Subcontractors/suppliers generally within 20 days after first furnishing; laborers have separate deadlines | MCL 570.1109 |
PRACTITIONER NOTES — MICHIGAN
Key Practice Points
-
"Construction Lien" Not "Mechanics' Lien." Michigan uses the term "construction lien" throughout the statute. Use correct terminology in all filings.
-
Double Bond Requirement. Michigan requires the bond to be twice (2x) the claimed amount — one of the higher bond requirements nationally. For a $50,000 lien, the bond must be $100,000.
-
Two-Office Filing for Bond Discharge. The bond discharge process involves two separate offices: (a) file the bond with the County Clerk, (b) record the Clerk's certificate with the Register of Deeds. Missing either step leaves the discharge incomplete.
-
10-Day Surety Objection Period. After the lien claimant is notified of the bond, the claimant has 10 days to file an objection to the sufficiency of the surety. If an objection is filed, the County Clerk must examine the surety before approving the bond.
-
No Generic MCL 570.1121 Penalty. Section 570.1121 governs foreclosure judgments, sales, distribution, and redemption. It does not create a greater-of-$1,000-or-10% wrongful-lien penalty. Attorney-fee treatment for a foreclosure action is in MCL 570.1118(2).
-
One-Year Foreclosure Deadline. A construction lien must be foreclosed within one year of recording. If no foreclosure action is commenced, the lien becomes void. This is distinct from many states that allow longer enforcement periods.
-
Residential Improvements. Do not apply a 60-day recording deadline or a generic 20-days-before-recording notice. Section 570.1111(1) uses 90 days after last furnishing, while § 570.1109 governs the earlier Notice of Furnishing by claimant role.
-
Sworn Statements. MCL 570.1110 requires detailed sworn statements in specified payment and demand circumstances. A contractor's failure before recording does not invalidate the lien, but blocks payment and enforcement until the statement is provided; a subcontractor's failure under subsection (2) likewise leaves the lien valid but blocks enforcement until compliance.
-
Liber/Page vs. Document Number. Michigan has historically used Liber (book) and Page references for recorded documents. Some counties have modernized to Document Numbers. Verify which system your county uses.
-
Lis Pendens Automatic Discharge. When a County Clerk's certificate is recorded at the Register of Deeds, any Notice of Lis Pendens recorded in connection with the lien is automatically discharged — no separate filing needed.
DISCLAIMER: This template is provided for informational purposes only and does not constitute legal advice. Michigan's Construction Lien Act has specific procedural requirements that must be strictly followed. Consult a Michigan-licensed attorney before using any of these forms.
Sources and References:
- MCL 570.1116 — Discharge by Bond
- MCL 570.1117 — Enforcement by Foreclosure
- Michigan Construction Lien Act — Full Text (PDF)
- MCL 570.1112 — Recorded instruments and certificate of no proceedings
- MCL 570.1115 — Statutory waivers
- MCL 570.1118 — Foreclosure forum and attorney fees
- MCL 570.1121 — Foreclosure judgment, sale, and redemption
About this template
- Last updated
- August 13, 2026
- Citations checked
- August 13, 2026
- Jurisdiction
- Michigan
- Category
- Real Estate
Legal authority
- MCL 570.1101 et seq. (Construction Lien Act)
- MCL 570.1110 (Sworn Statements)
- MCL 570.1115 (Statutory Construction-Lien Waivers)
- MCL 570.1116 (Discharge of Lien by Bond)
- MCL 570.1117(1) (One-Year Limit to Commence Foreclosure)
- MCL 570.1118 (Circuit-Court Foreclosure and Attorney Fees)
Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.
Not legal advice
This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.
Checked against the law it cites
A reviewer verified this template's legal citations against the official source on August 13, 2026.
Draft your Discharge and Release of Construction Lien in the editor
Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.