Mechanics Lien Filing Package — Oklahoma
Mechanics Lien Filing Package (OKLAHOMA)
Quick-Reference Summary
| Item | Oklahoma Specifics |
|---|---|
| Statutory framework | Title 42, Oklahoma Statutes, §§ 141 – 178 (Mechanics' and Materialmen's Liens) |
| Recording office | County Clerk of the county where the property is located |
| Pre-Lien Notice (42 O.S. § 142.6) | For a claimant other than an original contractor, send before filing and within 75 days after last supply when required; owner-occupied dwelling rule overrides the residential and under-$10,000 exceptions |
| Original contractor's lien statement deadline (§ 142) | 4 months after last labor/materials |
| Subcontractor's lien statement deadline (§ 143) | 90 days after last labor/materials |
| Notice to owner with copy of lien statement (§ 143.1) | Within one (1) business day after filing the lien statement |
| Service method | Certified mail, return receipt requested, or as otherwise provided by statute |
| Other exceptions | Non-owner-occupied residential project of 1–4 units; aggregate claim under $10,000; retainage and one-notice rules also apply |
| Foreclosure deadline (§ 172) | One (1) year after filing the lien statement |
| Verification | Lien statement must be sworn to and verified |
| Architects, engineers, surveyors | Lien rights when services result in actual construction on the land (per Stern v. Great Plains) |
Part A — Pre-Lien Notice
PRE-LIEN NOTICE (42 O.S. § 142.6)
Pursuant to Title 42, Oklahoma Statutes § 142.6
CRITICAL: Pursuant to 42 O.S. § 142.6, this notice must be sent prior to the filing of a lien statement and no later than seventy-five (75) days after the last date of supply of material, services, labor, or equipment. No lien affecting property occupied as a dwelling by an owner is valid unless this pre-lien notice was sent within seventy-five (75) days of the last furnishing.
TO (Original Contractor):
[________________________________]
[________________________________]
[______________________], OK [_______]
TO (Owner of property):
[________________________________]
[________________________________]
[______________________], OK [_______]
Date of mailing (certified mail, return receipt requested): [__/__/____]
1. Claimant
| Field | Entry |
|---|---|
| Name | [________________________________] |
| Address | [________________________________] |
| Phone | [________________________________] |
| [________________________________] | |
| Capacity | ☐ Subcontractor ☐ Materialman ☐ Supplier ☐ Equipment lessor ☐ Other: [_________] |
2. Description of Property
- Street address: [________________________________]
- County: [________________________________]
- Legal description (or sufficient legal description for identification):
[____________________________________________________________]
3. Description of Materials, Services, Labor, or Equipment Furnished
[____________________________________________________________]
4. Last Date of Supply / Furnishing
[__/__/____]
5. Amount Claimed
$[____________]
6. Person to Whom Claimant Furnished
- Name: [________________________________]
- Address: [________________________________]
Required content check: identify this as a pre-lien notice; include claimant contact information, date and description of supply, requester name and last-known address, property address/legal description/location, dollar amount furnished or to be furnished, and claimant/representative signature.
Signature of Claimant or Authorized Agent: ______________________________
Print name / title: [________________________________]
Date: [__/__/____]
DELIVERY PROOF: A rebuttable presumption arises from hand delivery with confirmation, an automated transaction under 12A O.S. § 15-115, or certified mail with return receipt requested. Certified-mail notice is effective when mailed.
Part B — Claim of Mechanics Lien
MECHANIC'S AND MATERIALMAN'S LIEN STATEMENT
Filed pursuant to 42 O.S. §§ 142 / 143
State of Oklahoma, County of [________________________________]
The undersigned, being first duly sworn, deposes and states as follows:
1. Claimant Information
- Name: [________________________________]
- Address: [________________________________]
- Phone: [________________________________]
- Capacity (check one):
☐ Original Contractor — filing under 42 O.S. § 142 (4-month deadline)
☐ Subcontractor — filing under 42 O.S. § 143 (90-day deadline)
☐ Materialman / Supplier — filing under 42 O.S. § 143
2. Owner of Property
- Name: [________________________________]
- Address: [________________________________]
3. Person With Whom Claimant Contracted (if not the owner)
- Name: [________________________________]
- Address: [________________________________]
4. Description of Property
- Street address: [________________________________]
- County: [________________________________]
- Legal description:
[____________________________________________________________]
[____________________________________________________________]
5. Statement of Claim
- Description of labor and/or materials furnished:
[____________________________________________________________]
- Date first furnished: [__/__/____]
- Date last furnished: [__/__/____]
- Total amount of contract: $[____________]
- Amounts paid: $[____________]
- Credits / offsets: $[____________]
- Amount due and unpaid (lien amount): $[____________]
6. Pre-Lien Notice Compliance (42 O.S. § 142.6)
☐ Pre-Lien Notice was sent to the owner and original contractor by certified mail, return receipt requested, on [__/__/____], which is within 75 days of the last date of supply. Proof of mailing attached.
☐ Not applicable — claimant is the original contractor with a direct contract with the owner.
7. Verification (42 O.S. §§ 142 / 143)
I, [________________________________], on oath state that I am the claimant or an authorized agent of the claimant; that I have read the foregoing lien statement; that the statements are true and correct to the best of my knowledge; and that the amount claimed is justly due and owing.
Signed: ______________________________
Print name / title: [________________________________]
Date: [__/__/____]
STATE OF OKLAHOMA )
) ss.
COUNTY OF [________________] )
Subscribed and sworn to before me by [________________________________] this [____] day of [____________], 20[____].
Notary Public — State of Oklahoma: ______________________________
My commission expires: [__/__/____]
Notary commission no.: [________________________________]
RECORDING: File the original verified statement with the County Clerk of the county where the property is located.
— Original contractor: within 4 months after last labor or materials (42 O.S. § 142).
— Subcontractor / materialman: within 90 days after last labor or materials (42 O.S. § 143).
Part C — Notice of Filing Lien Claim to Owner
NOTICE OF FILING LIEN STATEMENT TO OWNER (42 O.S. §§ 143.1, 144)
Service deadline: Within one (1) business day after filing the lien statement with the County Clerk (42 O.S. § 143.1).
Date: [__/__/____]
To (Owner of record):
[________________________________]
[________________________________]
[______________________], OK [_______]
RE: Mechanic's Lien Statement filed against your property
You are hereby notified that on [__/__/____], the undersigned filed a Mechanic's and Materialman's Lien Statement in the Office of the County Clerk of [______________] County, Oklahoma, as Instrument / Document No. [______________], against the real property commonly described as:
[____________________________________________________________]
Amount claimed: $[____________]
Claimant: [________________________________]
Claimant address: [________________________________]
Claimant phone: [________________________________]
A true and correct copy of the filed lien statement is enclosed.
METHOD OF SERVICE: Certified mail, return receipt requested (or as otherwise provided in 42 O.S. § 144).
Signature of Claimant or Authorized Agent: ______________________________
NOTE: 42 O.S. § 143.1 requires that, on the same day or within one business day after filing the lien statement, the claimant mail to the owner of the subject property a notice and a copy of the lien statement by certified mail, return receipt requested. Failure to do so may render the lien unenforceable.
Part D — Suit to Foreclose
PETITION TO FORECLOSE MECHANIC'S AND MATERIALMAN'S LIEN
Filed pursuant to 42 O.S. § 172
Filing deadline: Within one (1) year after the lien statement is filed with the County Clerk.
IN THE DISTRICT COURT OF [______________] COUNTY, STATE OF OKLAHOMA
| Party | Role |
|---|---|
| [CLAIMANT NAME], | Plaintiff |
| v. | |
| [OWNER NAME]; [CONTRACTING PARTY]; [MORTGAGEE / LIENHOLDER]; and JOHN DOES 1–10, | Defendants |
Case No.: CJ-[__-_______]
Judge: [______________]
PETITION TO FORECLOSE MECHANIC'S AND MATERIALMAN'S LIEN, FOR BREACH OF CONTRACT, AND FOR ATTORNEY FEES
COMES NOW Plaintiff [CLAIMANT NAME] and for its cause of action against Defendants alleges and states:
PARTIES, JURISDICTION, AND VENUE
-
Plaintiff is a [entity type] doing business in Oklahoma.
-
Defendant [OWNER NAME] is the record owner of the property at issue.
-
Defendant [CONTRACTING PARTY] is the party with whom Plaintiff contracted.
-
Defendant [MORTGAGEE] is a lienholder of record on the Property.
-
This Court has subject-matter jurisdiction under Okla. Const. art. VII, § 7(a), and venue is proper in [______________] County under 12 O.S. § 131 because this action seeks enforcement or sale of real property under a lien and the property is located in this county.
FACTUAL ALLEGATIONS
- The property (the "Property") is located at [________________________________], [______________] County, Oklahoma, and is more particularly described as:
[____________________________________________________________]
-
Beginning on [__/__/____], Plaintiff furnished labor and/or materials for the improvement of the Property at the request of [CONTRACTING PARTY].
-
Plaintiff last furnished labor and/or materials on [__/__/____].
-
The reasonable value of the labor and/or materials is $[____________]; Plaintiff has been paid $[____________]; and the unpaid balance is $[____________].
-
☐ Plaintiff is the original contractor and was not required to send a pre-lien notice under 42 O.S. § 142.6.
☐ Plaintiff timely sent the pre-lien notice required by 42 O.S. § 142.6 by certified mail, return receipt requested, on [__/__/____], which is within 75 days of last furnishing. -
Plaintiff timely filed a verified Mechanic's Lien Statement in the Office of the County Clerk of [______________] County on [__/__/____], as Instrument No. [______________], in compliance with 42 O.S. § 142 / § 143.
-
Plaintiff timely mailed a copy of the lien statement and notice of filing to the owner on [__/__/____], in compliance with 42 O.S. § 143.1.
FIRST CAUSE OF ACTION — Foreclosure of Mechanic's and Materialman's Lien (42 O.S. § 172)
-
Plaintiff incorporates the preceding paragraphs.
-
Plaintiff holds a valid mechanic's and materialman's lien on the Property securing the unpaid balance of $[____________].
-
Plaintiff is entitled to foreclose the lien, have the Property sold under decree of this Court, and have the proceeds applied to satisfaction of the lien.
SECOND CAUSE OF ACTION — Breach of Contract
-
Plaintiff incorporates the preceding paragraphs.
-
Defendant [CONTRACTING PARTY] breached the parties' contract by failing to pay. Plaintiff has been damaged in the amount of $[____________], plus interest at the statutory rate of 15 O.S. § 266 / contract rate, prejudgment interest, and costs.
THIRD CAUSE OF ACTION — Quantum Meruit (Alternative)
-
Plaintiff incorporates the preceding paragraphs.
-
The reasonable value of Plaintiff's work is $[____________]. Defendants accepted the benefit and refusal to pay would be inequitable.
PRAYER FOR RELIEF
WHEREFORE, Plaintiff prays for judgment:
a. Adjudging that Plaintiff has a valid mechanic's and materialman's lien upon the Property in the amount of $[____________], with interest from [__/__/____];
b. Foreclosing the lien and ordering sale of the Property under 12 O.S. § 686;
c. Awarding Plaintiff its costs and reasonable attorney fees pursuant to 42 O.S. § 176;
d. Granting such other and further relief as the Court deems just and equitable.
DATED this [____] day of [____________], 20[____].
[________________________________]
OBA No. [______________]
Attorney for Plaintiff
VERIFICATION
I, [________________________________], being first duly sworn, depose and state under oath that I am the [title] of Plaintiff, that I am authorized to make this verification, and that the factual allegations of the foregoing Petition are true and correct to the best of my knowledge, information, and belief.
Signed: ______________________________ Date: [__/__/____]
Subscribed and sworn before me this [____] day of [____________], 20[____].
Notary Public — State of Oklahoma: ______________________________
Part E — Pre-Filing Checklist
☐ Determine claimant's status: original contractor (4-month deadline; not a § 142.6 “claimant”) vs. subcontractor/materialman (90-day deadline; analyze § 142.6).
☐ Analyze owner occupancy, 1–4 unit non-owner-occupied residential exception, aggregate claim threshold (less than $10,000), and retainage/one-notice rules.
☐ If required, send § 142.6 Pre-Lien Notice before lien filing and within 75 days after last supply by a method supporting the statutory presumption; retain proof.
☐ Identify and verify owner of record, legal description, parcel number, and senior encumbrances via title search.
☐ Calendar lien statement filing deadline: 4 months (original contractor — § 142) or 90 days (subcontractor — § 143) after last labor/materials.
☐ Prepare verified Lien Statement including: claimant identity, owner identity, contracting party, property description, dates, amounts, and signed/sworn verification.
☐ Notarize the Lien Statement.
☐ File the original Lien Statement with the County Clerk where the property lies.
☐ Within one (1) business day after filing, mail a copy of the filed Lien Statement and notice to the owner by certified mail, return receipt requested (§ 143.1).
☐ Calendar one-year foreclosure deadline measured from filing of the Lien Statement (42 O.S. § 172).
☐ Confirm no statutory bond has been substituted to discharge the lien.
☐ Document the lienable scope; remove non-lienable items.
☐ Confirm claimant's contractor registration / licensing (where applicable to trade) is in good standing.
☐ Evaluate exposure for wrongful filing under Oklahoma slander-of-title or bad-faith standards before recording.
Sources and References
- 42 O.S. § 141 (Lien for labor, materials) — https://law.justia.com/codes/oklahoma/title-42/section-42-141/
- 42 O.S. § 142 (Original contractor's lien) — https://govt.westlaw.com/okjc/Document/N79D7AFF0C76E11DB8F04FB3E68C8F4C5
- 42 O.S. § 142.6 (Pre-lien notice) — https://govt.westlaw.com/okjc/Document/NB40997718E0A11F0A26CEF304F15790C
- 42 O.S. § 143 (Subcontractor's lien) — https://govt.westlaw.com/okjc/Document/N7BB5E5D0C76E11DB8F04FB3E68C8F4C5
- 42 O.S. § 143.1 (Notice to owner of filing) — https://law.justia.com/codes/oklahoma/title-42/section-42-143-1/
- 42 O.S. § 144 (Notice of lien claim) — https://law.justia.com/codes/oklahoma/title-42/section-42-144/
- 42 O.S. § 172 (Foreclosure / limitations) — https://law.justia.com/codes/oklahoma/title-42/section-42-172/
- 42 O.S. § 176 (Attorney fees) — https://law.justia.com/codes/oklahoma/title-42/section-42-176/
- Oklahoma Bar Journal, "To Lien or Not To Lien" (June 2024) — https://www.okbar.org/barjournal/june-2024/to-lien-or-not-to-lien/
- Oklahoma Senate codified statutes (Title 42) — https://oksenate.gov/sites/default/files/2022-05/os42.pdf
About this template
- Last updated
- August 1, 2026
- Jurisdiction
- Oklahoma
- Category
- Real Estate
Legal authority
- 42 O.S. § 141 (Mechanics' and materialmen's liens)
- 42 O.S. § 142 (Lien statement of original contractor; 4-month filing)
- 42 O.S. § 142.6 (Pre-lien notice; 75-day requirement)
- 42 O.S. § 143 (Lien statement of subcontractor; 90-day filing)
- 42 O.S. § 143.1 (Mandatory notice to owner with lien statement)
- 42 O.S. § 144 (Notice of lien claim to owner)
- 42 O.S. § 172 (Foreclosure of lien; one-year limitation)
- 12 O.S. § 686 (Foreclosure procedure)
Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.
Not legal advice
This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.
Checked against the law it cites
The statutes this template relies on are listed under Legal authority.