Tennessee: Mechanic's Lien Waiver Form and Advance-Waiver Rules

verified against the statute 2026-07-23 2 statute sources

The short answer

Tennessee makes any contract provision purporting to waive a Chapter 11 lien right void and unenforceable as against public policy. A contractor who solicits that provision can face a licensing-board process, license revocation, and attorney-fee and cost liability. The statute prescribes no conditional, unconditional, progress, or final waiver form; accepting a note does not waive the lien unless the lienor expressly agrees in writing, while a qualifying 100% payment bond supplied and recorded before work eliminates remote-contractor land liens.

Ask Ezel about your situation

This is the general rule in Tennessee. Ezel applies current Tennessee law to your specific facts and answers with citations to the statutes.

Governing law and project scopeTenn. Code Ann. § 66-11-124, within the private-improvement mechanics' and materialmen's lien chapter. Applies to any lien right under chapter 11; subsection (c) separately replaces remote-contractor land liens when a qualifying payment bond is provided before furnishing begins.
Advance or prospective waiverAny contract provision purporting to waive a lien right under chapter 11 is void and unenforceable as against public policy (§ 66-11-124(b)(1)).
Statutory form requirementNo statutory payment-stage waiver form or mandatory wording. Section 66-11-124 regulates contract clauses, express written agreement when accepting a note, enforcement consequences, and the payment-bond alternative.
Waiver types and payment stageNo statutory conditional/unconditional or progress/final forms. Accepting a note is not a waiver unless the lienor expressly agrees in writing; the statute does not supply a separate draw or final-waiver format (§ 66-11-124(a)).
Payment and effectivenessA note for all or part of the claim does not waive the lien absent express written agreement and does not affect the lien-notice period. No statutory actual-receipt, cleared-check, or amount-paid effectiveness rule for a separate payment-stage waiver (§ 66-11-124(a)).
Required contents, exceptions, and through dateNo statutory claimant, owner, project, property, amount, check, through-date, retainage, extras, change-order, or disputed-claim fields for a payment-stage waiver. A note-related waiver must at least be expressly agreed in writing (§ 66-11-124(a)).
Rights released and reservedThe anti-waiver rule protects any lien right under chapter 11. Section 66-11-124 does not state that a permitted written waiver releases contract, payment-bond, or other claims; subsection (c) preserves remote contractors through a payment bond while eliminating their land liens.
Signature, authority, notary, and formatNo statutory signer-title, agent-authority, notarization, acknowledgment, warning, type-size, attachment, or electronic-format rule for a payment-stage waiver. The only express format point is written agreement for a note to waive a lien (§ 66-11-124(a)).
Noncompliance, remedies, and transition trapsProhibited contract language is void. A solicited person reports it to the licensing board; refusal to delete can lead to hearing and immediate license revocation, notice to other states, and attorney fees/costs in a lien-enforcement damages action. Deletion plus a no-future-use statement ends the first complaint (§ 66-11-124(b)(2)).

Compare this rule across all 50 states + DC →

Requirements one by one

Contract lien waivers are void

Tenn. Code Ann. § 66-11-124(b)(1) states the rule without a work-start or
payment-stage qualifier:

Any contract provision that purports to waive any right of lien under this
chapter is void and unenforceable as against the public policy of this state.

The restriction is broader than a rule that merely forbids a pre-work clause.
It reaches any purported lien-waiver provision in the construction contract.

Soliciting the clause creates a licensing-board path

Under § 66-11-124(b)(2), the solicited person reports the prohibited provision
to the State Board for Licensing Contractors. If the contractor deletes it and
states that the language will not appear in future Tennessee construction
contracts, the board takes no further action on that first complaint. Refusal
can lead to a hearing and immediate license revocation, followed by notice to
the contractor's licensing authorities in other states.

The same subsection gives a solicited person reasonable attorney fees and costs
in an action for damages based on the waiver, in connection with enforcing the
lien.

Tennessee prescribes no payment-stage waiver form

Section 66-11-124 supplies no conditional, unconditional, progress, or final
form. Its payment-specific rule concerns a note: accepting a note for all or
part of the claim does not waive the lien unless the lienor expressly agrees in
writing. Accepting the note also does not change the time to serve or record the
lien notice.

A pre-work payment bond changes remote-contractor security

The separate subsection (c) mechanism is not a waiver. If, before anyone begins
furnishing, the owner or agent provides a payment bond equal to 100% of the
prime contract price in favor of remote contractors, with authorized surety and
recording in every affected county, remote contractors receive no land liens
under the chapter and instead look to the bond.

What trips people up

A note is not payment and does not stop the lien clock. Taking a promissory
note leaves the lien intact unless the lienor expressly agrees in writing to a
waiver, and it does not extend or alter the notice deadline.

The statute does not supply private-form safe harbors. It gives no approved
through-date, amount, exception, payment-condition, signature, or notary fields
for a separate draw waiver.

The board remedy begins with an opportunity to delete. Immediate revocation
does not follow merely from the first report; the contractor first receives
notice and can remove the clause and promise not to reuse it.

The 100% payment bond must predate furnishing. A later bond is not the
subsection (c) route that prevents remote-contractor liens from arising.

Common questions

Can a Tennessee subcontract contain a blanket lien waiver?
No. A contract provision purporting to waive a Chapter 11 lien right is void and
unenforceable.

Does Tennessee require conditional or unconditional waiver forms?
No. Section 66-11-124 prescribes no payment-stage waiver forms.

Does accepting a promissory note waive the lien?
Not by itself. The lienor must expressly agree in writing, and the note does not
change the lien-notice deadline.

Statutes and sources

  • Tenn. Code Ann. § 66-11-124(a)-(c), note, contract-waiver, and payment-bond
    rules as reenacted — http://www.capitol.tn.gov/Bills/105/Chapter/PC0189.pdf
    (accessed 2026-07-23)
  • Tenn. Code Ann. § 66-11-124(b)(2), licensing and fee remedies —
    https://publications.tnsosfiles.com/acts/111/pub/pc0749.pdf
    (accessed 2026-07-23)

Source links

Every statute quoted above, linked, with the date we checked it.

Tenn. Code Ann. § 66-11-124(a)-(c) · accessed 2026-07-23
Tenn. Code Ann. § 66-11-124(b)(2) · accessed 2026-07-23
This page is general legal information about pre-recording construction-lien waivers, not legal advice about a payment, draw, project, claim, or document. A waiver can permanently surrender lien, stop-notice, bond, payment, or other rights, and the result can depend on project type, claimant status, contract date, payment stage, actual receipt or clearance of funds, through date, exceptions, statutory wording, signature authority, and form presentation. A waiver is different from releasing or satisfying an already recorded lien. Verified against official sources on the date shown; use the current statutory form and have a qualified construction attorney review any disputed or high-value waiver before signing or relying on it.

Get the answer for your situation

You just read how Tennessee handles this in general. Ezel applies current Tennessee law to your facts and answers your specific question, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.