Mechanic's Lien Waiver Form and Advance-Waiver Rules in Indiana
At a glance
| Governing law and project scope | Ind. Code Title 32, art. 28, ch. 3, especially §§ 32-28-3-0.2, -1, -16, and -18. Section 16 covers Indiana building and structure improvement contracts but excludes Class 2 structures, their auxiliary improvements, and specified utility property. |
|---|---|
| Advance or prospective waiver | For covered projects, a contract term requiring a claimant to waive a real-estate lien or payment-bond claim before being paid is void; an agreement not to file a lien notice is also void (§ 32-28-3-16(b)-(c)). |
| Statutory form requirement | No statutory payment-stage waiver form or mandatory wording. Chapter 3 states the prepayment anti-waiver rule and special-project no-lien-clause rules but supplies no conditional, unconditional, progress, or final form. |
| Waiver types and payment stage | No statutory conditional/unconditional or progress/final forms. Section 32-28-3-16 uses payment as the dividing line but does not prescribe a post-payment waiver type or format. |
| Payment and effectiveness | A covered contract cannot require waiver before the claimant is paid. The statute states no actual-receipt, cleared-check, joint-check, written-acknowledgment, or partial-payment effectiveness test for a separate waiver (§ 32-28-3-16(b)). |
| Required contents, exceptions, and through date | No statutory claimant, owner, project, amount, check, through-date, retainage, extras, change-order, or disputed-claim fields for a payment-stage waiver. Special-project no-lien clauses instead require a writing, legal description, deed-style acknowledgment, and recording within five days (§ 32-28-3-1(f)). |
| Rights released and reserved | Before payment, § 32-28-3-16 protects both the real-estate lien and a payment-bond claim and voids an agreement not to file the lien notice. It does not prescribe release or reservation language for contract, delay, extras, retainage, or other claims. |
| Signature, authority, notary, and format | No statutory signer-title, agent-authority, notarization, warning, type-size, attachment, or electronic-format rule for a payment-stage waiver. Deed-style acknowledgment applies only to the separate special-project no-lien contract under § 32-28-3-1(f). |
| Noncompliance, remedies, and transition traps | A prohibited provision is void. The anti-waiver provisions apply to contracts and subcontracts entered after June 30, 1999; § 32-28-3-16 excludes specified Class 2/utility work, while § 32-28-3-1(e)-(f) permits qualifying no-lien clauses there and preserves liens for work supplied before recording. |
Requirements one by one
Covered claimants cannot be required to waive before payment
Ind. Code § 32-28-3-16(b) protects both the real-estate lien and a payment-bond claim:
A provision in a contract for the improvement of real estate in Indiana is void if the provision requires a person ... to waive a right to ... a lien against real estate; or ... a claim against a payment bond; before the person is paid for the labor or materials furnished.
Subsection (c) separately voids a contract provision under which one or more persons agree not to file the notice of intention that creates the lien.
Indiana prescribes no payment-stage waiver form
Chapter 3 supplies no conditional, unconditional, progress, or final waiver form. Section 32-28-3-16 draws a line at payment, but it does not define a cleared-check test, a through date, required reservations, a warning, a signature block, or notarization for a post-payment waiver.
Certain special projects follow a different no-lien-clause path
Section 32-28-3-16 does not apply to Class 2 structures, their auxiliary improvements, or specified utility property. Section 32-28-3-1(e)-(f) allows a no-lien provision for listed projects only if the owner-prime contract is in writing, identifies the real estate by legal description, is acknowledged like a deed, and is recorded within five days after execution. Even then, the clause does not affect a lien for labor, material, or machinery supplied before the contract was recorded.
A pay-if-paid term cannot defeat the lien on covered work
For contracts within § 32-28-3-18, an obligor's receipt of payment from an unrelated third person cannot be a condition precedent, limit, or defense to the provider's right to record or foreclose the lien. That provision carries the same principal Class 2 and utility exclusions.
What trips people up
The statute does not define what counts as being paid. Section 32-28-3-16(b) uses payment as the threshold but says nothing about whether a check must clear. A private document's payment condition should not be mistaken for statutory wording.
The project exception changes the analysis. A clause that is void on an ordinary covered building project may fall under the separate § 32-28-3-1(e)- (f) route on listed Class 2 or utility work. That route has recording and formality requirements of its own.
The anti-waiver enactment has a contract-date rule. Section 32-28-3-0.2(b) says the provisions now codified as §§ 16 to 18 apply only to contracts and subcontracts entered after June 30, 1999.
Common questions
Can an Indiana construction contract require a lien waiver before payment? Not on a project covered by § 32-28-3-16. The required prepayment waiver of either the real-estate lien or payment-bond claim is void.
Does Indiana require conditional or unconditional waiver forms? No. Chapter 3 prescribes no payment-stage waiver forms or mandatory waiver wording.
Can a contract simply say the claimant will never file a lien notice? Not on covered work. Section 32-28-3-16(c) makes that agreement void.
Statutes and sources
- Ind. Code § 32-28-3-16, covered-project advance-waiver and no-file-clause rules — https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf (accessed 2026-07-23)
- Ind. Code § 32-28-3-1(e)-(f), special-project no-lien clauses and formalities — https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf (accessed 2026-07-23)
- Ind. Code § 32-28-3-0.2(b), contract-date transition — https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf (accessed 2026-07-23)
- Ind. Code § 32-28-3-18, third-party-payment term cannot limit the lien — https://iga.in.gov/ic/2026/Title_32/Article_28/Chapter_3.pdf (accessed 2026-07-23)
Source links
Every statute quoted above, linked, with the date we checked it.
What does Indiana law mean for your facts?
You just read the general rule. Ask your own question and see which parts of current Indiana law apply to your situation, with citations you can check.
Opens in Ezel Pro.
- Starts from the statutes this survey is built on
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace