Templates Real Estate Tenant Improvement Work Letter
Tenant Improvement Work Letter
Ready to Edit
Tenant Improvement Work Letter - Free Editor

TENANT IMPROVEMENT WORK LETTER

1. DEFINITIONS

  • “Plans”: Final construction drawings approved by Landlord and Tenant.
  • “Substantial Completion”: Work sufficiently complete for occupancy subject only to punchlist items not materially interfering with use.
  • “Allowance”: $[AMOUNT]/SF (cap) for design/permits/constructing the Tenant Improvements (TI).
  • “Landlord Delay”: Delays caused by Landlord, its contractors, or failure to timely review/approve/deliver.
  • “Tenant Delay”: Delays caused by Tenant (late plans, changes, access issues, untimely approvals).
  • “Force Majeure”: As defined in the Lease (if applicable); excludes monetary obligations.

2. PLANS AND APPROVALS

  • Tenant delivers preliminary plans by [DATE]; Landlord responds within [X] business days; mutual approval required.
  • Changes require written approval; cost/time impacts allocated per Section 4.

3. CONSTRUCTION

  • ☐ Landlord Build / ☐ Tenant Build (select).
  • Contractor selection: [LANDLORD APPROVED LIST / TENANT SELECTS SUBJECT TO APPROVAL].
  • Compliance with laws, codes, permits, insurance, lien waivers.
  • Coordination with building rules; hours; staging and deliveries.

4. COSTS AND ALLOWANCE

  • Allowance applied to TI costs; overages paid by Tenant; unused allowance reverts to Landlord unless otherwise agreed.
  • Change orders must detail cost/time impact; overage funded by Tenant before commencement of change work.
  • Draw Mechanics (if Tenant Build): Disbursements upon submission of (a) invoices, (b) conditional/unconditional lien waivers, (c) architect certification of percentage completion, within [X] days of a complete draw request.

5. SCHEDULE AND DELAYS

  • Target Substantial Completion: [DATE].
  • Extensions for Tenant Delay and Force Majeure; schedule relief matches actual delay duration.
  • Landlord Delay: Tenant receives day-for-day relief plus, if Rent Commencement is tied to delivery, rent abatement equal to Base Rent for each day of Landlord Delay beyond a [GRACE] day grace period.
  • Tenant Delay: Extends Target Substantial Completion and Rent Commencement accordingly; no abatement.

6. PUNCHLIST / DELIVERY

  • Joint punchlist within [X] days of Substantial Completion; Landlord/Tenant complete their items within [Y] days.
  • Final lien waivers and permits required before occupancy (if applicable).

7. ALLOWANCE DRAWS (IF TENANT BUILD)

  • Draw process: invoices, lien waivers, architect certification; disbursed within [X] days.
  • Landlord may withhold only for: incomplete documentation, defective work, or over-budget items; partial release for undisputed amounts.

8. WARRANTIES

  • Standard contractor/subcontractor warranties assigned to Tenant (or Landlord) as applicable; defects corrected within warranty period.

9. MISCELLANEOUS

  • Insurance and indemnity align with Lease; governing law/venue per Lease; survival of obligations.
  • Self-Help/Fail-to-Fund (optional): If Landlord fails to fund undisputed Allowance draws after [NOTICE + X] days, Tenant may fund and offset against next Base Rent installments (subject to Lease limits) or seek specific performance.

[// GUIDANCE: Tie rent commencement to Substantial Completion/possession if negotiated; add ADA/local code references; include right to self-help if Landlord fails to fund allowance (if negotiated).]

AI Legal Assistant

Welcome to Tenant Improvement Work Letter

You're viewing a professional legal template that you can edit directly in your browser.

What's included:

  • Professional legal document formatting
  • Universal jurisdiction-specific content
  • Editable text with legal guidance
  • Free DOCX download

Upgrade to AI Editor for:

  • 🤖 Real-time AI legal assistance
  • 🔍 Intelligent document review
  • ⏰ Unlimited editing time
  • 📄 PDF exports
  • 💾 Auto-save & cloud sync