Stop-Notice - Nebraska

Nebraska Real Estate Updated August 22, 2026 Free Word and PDF

NEBRASKA CONSTRUCTION LIEN RIGHTS AND PAYMENT NOTICE

URL-PRESERVED “STOP NOTICE” CORRECTION

This is not a statutory lender stop notice. It may be used to prepare one of the following only after counsel selects the correct route:

☐ A notice of right to assert a construction lien under Neb. Rev. Stat. § 52-135

☐ A copy-delivery cover letter for an already recorded lien under § 52-135(3)

☐ A noncompulsory payment-dispute notice that expressly creates no statutory withholding duty

Do not demand a 125% reserve, a 150% private release bond, segregation of loan proceeds, automatic personal liability, a five-day cure, bondless injunction, or lender withholding. Those terms do not appear in the current Nebraska Construction Lien Act.

1. Applicability Gate

Required determination Verified answer Current official source / record Reviewer / date
Private or public project [________] [________] [________]
Contracting owner [________] [________] [________]
Claimant and contract-chain role [________] [________] [________]
Protected-party status for § 52-135 [________] [________] [________]
Real estate and improvement within the Act [________] [________] [________]
Existing notice of commencement and record location [________] [________] [________]
Existing surety-bond notice and record location [________] [________] [________]
Final furnishing date and evidence [________] [________] [________]
Lien amount and contract-chain calculation [________] [________] [________]
County register-of-deeds requirements [________] [________] [________]
Contract remedies and dispute procedure [________] [________] [________]

Selected route: [________________________________]

Why § 52-135 applies or does not apply: [________________________________]

2. Claim and Project Information

Claimant name: [________________________________]

Claimant notice address: [________________________________]

Person with whom claimant contracted: [________________________________]

That person's address: [________________________________]

Contracting owner: [________________________________]

Owner address: [________________________________]

Prime contractor: [________________________________]

Project name and street address: [________________________________]

Real-estate description sufficient for identification: [________________________________]

Services or materials furnished or to be furnished: [________________________________]

Contract date and identifier: [________________________________]

Amount unpaid, whether or not due: $[________________]

☐ Fixed contract amount

☐ Good-faith estimate, expressly designated as an estimate

Amount calculation and supporting documents: [________________________________]

3. Notice of Right to Assert a Lien — Protected-Party Route

Use this section only if counsel confirms that § 52-135 applies. The statutory notice is directed to the contracting owner, not automatically to a construction lender.

NOTICE OF RIGHT TO ASSERT A CONSTRUCTION LIEN

Date: [__/__/____]

To: [CONTRACTING OWNER]

Address: [________________________________]

From: [CLAIMANT]

Notice address: [________________________________]

Claimant contracted with [NAME AND ADDRESS] to furnish the following services or materials in connection with improvement of the real estate described below:

Services or materials: [________________________________]

Real estate: [________________________________]

Claimant states that claimant is entitled to record a construction lien under the Nebraska Construction Lien Act.

Amount unpaid: $[________________]

☐ This is the fixed unpaid amount.

☐ This is a good-faith estimate of the unpaid amount.

Warning. If you did not contract with the person giving this notice, any future payments you make in connection with this project may subject you to double liability.

Optional request for notice of termination of notice of commencement:

☐ Claimant requests written notice of the recording of any notice of termination at least three weeks before its effective date. Send notice to: [________________________________]

____________________________________

[CLAIMANT / AUTHORIZED SIGNER]

4. Noncompulsory Payment Request

This section may accompany the statutory notice or stand alone when counsel determines that § 52-135 does not apply. It is a settlement communication only and does not create a statutory freeze.

Claimant requests that the owner and contracting parties:

  1. confirm the disputed amount and identify every disputed line item;
  2. provide the prime-contract balance and relevant payment records voluntarily or as otherwise required by contract or law;
  3. preserve project, payment, change-order, delivery, and communication records;
  4. confer by [__/__/____] regarding payment, joint check, escrow by agreement, bond, or other negotiated resolution; and
  5. direct payment or lien communications to [________________________________].

Requested payment: $[________________]

Requested response date selected for settlement: [__/__/____]

No recipient admits liability or undertakes a statutory withholding, segregation, or payment duty merely by receiving this request.

5. Protected-Owner Payment Analysis

For a protected-party contracting owner, § 52-136 ties the lien amount and proper-payment analysis to the prime contract, notices, recorded liens, good faith, and amounts left unpaid. Complete this table before making any claim about double liability or available contract funds.

Item Amount Source
Prime contract price, as adjusted $[________] [________]
Payments made before notice / lien copy $[________] [________]
Payments made after notice / lien copy $[________] [________]
Prime contract amount remaining unpaid $[________] [________]
Other noticed or recorded claims $[________] [________]
Claimant's unpaid contract amount $[________] [________]
Counsel-approved lien amount $[________] [________]

Payment-treatment conclusion and operative § 52-136 subsection: [________________________________]

6. Lien Recording and Enforcement Calendar

Event Date Deadline / action Proof
Contract entered [__/__/____] Confirm Act coverage [________]
Final furnishing [__/__/____] Start § 52-137 calendar [________]
Last day to record lien [__/__/____] No later than 120 days after final furnishing [________]
Lien recorded [__/__/____] Record location: [________] [________]
Copy sent to contracting owner [__/__/____] Within 10 days after recording [________]
Ordinary enforceability end [__/__/____] Two years after recording, subject to § 52-140 [________]
Demand to institute proceeding received [__/__/____] Analyze 30-day action / affidavit route immediately [________]
Foreclosure proceeding filed [__/__/____] Court / case: [________] [________]

Do not use service of this payment notice as a substitute for recording a compliant lien.

7. Recorded-Lien Preparation Checklist

Section 52-147 requires the signed recorded lien to state the following. Prepare the recorder-ready document separately.

☐ Real estate subject to lien, sufficiently identified

☐ Name of person whose real-estate interest is claimed

☐ Claimant name and address

☐ Name and address of person with whom claimant contracted

☐ General description of services or materials and contract price

☐ Unpaid amount, whether or not due, or labeled good-faith estimate

☐ Last furnishing date or estimate if not yet occurred

☐ Claimant signature

☐ County recording standards, fees, tax-lot data, and return address checked

8. Bond, Substitute Collateral, and Release

Do not privately demand a percentage bond from the owner or lender as though service of this notice created that right.

After liens have attached, § 52-142 permits a person with an interest in the real estate to use the district-court-clerk deposit procedure for money or an authorized surety bond in an amount sufficient to pay the total lien amounts being released plus fifteen percent. The clerk's certificate is then recorded. Record the actual route here:

Item Verified entry
Attached lien record locations [________]
Total claimed in liens to be released $[________]
Additional 15% $[________]
Cash / certified check / bank obligation / surety bond [________]
District court clerk and county [________]
Clerk certificate record location [________]

For payment or resolution, prepare the separate recordable release or partial-release instrument required by § 52-154. Do not label a private letter as a statutory lien release.

9. Delivery Record

Recipient Capacity Address Method Sent Received / tracking
[________] Contracting owner [________] [________] [__/__/____] [________]
[________] Prime contractor [________] [________] [__/__/____] [________]
[________] Contract-chain party [________] [________] [__/__/____] [________]
[________] Lender, courtesy only if appropriate [________] [________] [__/__/____] [________]

Delivery method and effectiveness under current law verified by counsel: [________________________________]

10. Final Review

☐ The document is not represented as a statutory lender stop notice.

☐ Protected-party status and § 52-135 applicability are resolved.

☐ The statutory warning is reproduced exactly and in type no smaller than the other required information.

☐ Claim amount is supported and any estimate is labeled.

☐ Recording and ten-day owner-copy deadlines are calendared separately.

☐ No invented reserve, segregation, lender duty, private bond, default, fee, indemnity, or injunction term remains.

☐ Any substitute-collateral route uses the district court clerk and attached-lien procedure.

☐ Current official Act text and recent amendment leads were checked.

Reviewing Nebraska attorney: [________________________________]

Review date: [__/__/____]

Insert Image

Insert Table

Watch Ezel in action (sample case)Choose a plan

All changes saved
Save
Export
Export as DOCX
Export as PDF
Generating PDF...
stop_notice_ne.pdf
Ready to export as PDF or Word
AI is editing...
Chat
Review

Draft it in the editor

The AI drafts each section from your answers and you review every word. Drafting from scratch takes hours; finish yours for $99 one time.

  • Built on this template
    Uses the Nebraska version and the statutes it cites.
  • Formatted like the template
    Captions, numbering and layout stay intact.
  • AI editing
    Rewrite any section from your own notes.
  • Export as PDF and Word
    Yours to review, sign, or file.
Secure checkout via Stripe
Need to customize this document?

About this template

Last updated
August 22, 2026
Citations checked
August 22, 2026
Jurisdiction
Nebraska
Category
Real Estate

Legal authority

  • Neb. Rev. Stat. § 52-125 (Nebraska Construction Lien Act)
  • Neb. Rev. Stat. § 52-135 (notice of right to assert lien)
  • Neb. Rev. Stat. § 52-136 (amount of lien and protected-owner payment treatment)
  • Neb. Rev. Stat. § 52-137 (recording deadline and attachment)
  • Neb. Rev. Stat. § 52-140 (duration and demand to institute proceedings)
  • Neb. Rev. Stat. § 52-142 (substitution of collateral after lien attachment)
  • Neb. Rev. Stat. § 52-147 (recorded-lien contents)
  • Neb. Rev. Stat. § 52-154 (discharge and partial release)

Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.

Not legal advice

This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.

Checked against the law it cites

A reviewer verified this template's legal citations against the official source on August 22, 2026.

Neb. Rev. Stat. § 52-125 (checked August 22, 2026): "Sections 52-125 to 52-159 shall be known and may be cited as the Nebraska Construction Lien Act."

Neb. Rev. Stat. § 52-135(1) (checked August 22, 2026): "At any time after a claimant has entered into the contract under which he or she may claim a lien under the Nebraska Construction Lien Act, he or she may give notice of the right to assert a lien to the contracting owner."

Neb. Rev. Stat. § 52-135(3) (checked August 22, 2026): "The claimant shall send a copy of a recorded lien to the contracting owner within ten days after recording."

Neb. Rev. Stat. § 52-136(5)(b) (checked August 22, 2026): "is made in good faith and leaves unpaid a part of the prime contract price sufficient to satisfy the unpaid claims of all claimants"

Draft your Stop-Notice in the editor

Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.