Was a structural-steel fabricator a construction contractor when the prime contractor separately hired the installer and the fabricator lacked installation responsibility?

Short answer No. Appeals treated it as the retailer and material supplier because the record showed no contractual installation duty, supervision, testing, or installation equipment.
State
CA
Ruling
Annotation 190.1020
Tax type
Sales and Use Tax
Issued
1996-02-09
Issued by
California State Board of Equalization
Requested by
Structural-steel fabricator petitioner

Apply this to your situation

This page answers the general question as of 1996. Ask about yours and see what current California tax law says, with citations.

Currency note: this ruling is from 1996
Subsequent statutory amendments, regulation changes, court decisions, or later rulings may have changed the analysis. Treat this page as historical context, not current tax advice. Verify current law before relying on any specific rule, rate, or position mentioned here.
Disclaimer: This February 9, 1996 Legal Division and Appeals Board-hearing summary concerned one structural-steel fabricator's April 1988-March 1991 audit. No Appeals conference or Decision and Recommendation was prepared after the petitioner challenged the assigned attorney and waived appearance if no reassignment occurred. Exhibits A-C, the audit workpapers and purchase orders, the petitioner's later documents, and the October 10, 1995 reaudit report are described but not reproduced in the official PDF. The summary recommended following the reaudit, but this source does not record the Board's final vote. Purchase orders, installation contracts, supervision, testing, equipment, correction duties, duplicate transactions, documentation, later authority, and current law control.
About this page: The plain-English summary, reader guidance, and Q&A below were written by Ezel based on the official state tax ruling. The original ruling (linked on this page as a PDF) is the authoritative source for any reliance.
View original ruling (PDF)

Plain-English summary

A structural-steel fabricator included an installer quote in its bid, but the prime contractor issued one purchase order to the fabricator for steel and a separate purchase order directly to the installing subcontractor. The fabricator's purchase orders did not require installation, and the record showed no installation supervision, testing, equipment, or correction responsibility.

Appeals therefore treated the petitioner as a manufacturer and retailer of tangible personal property, not a construction contractor consuming materials. Unlike the taxpayer in Western Concrete Structures, it did not have ultimate contractual responsibility and control over final installation.

The reaudit removed duplicates and adjusted transactions where installation was proved, but the remaining material-only sales stayed taxable at retail selling price. Appeals recommended redetermination under the reaudit; the source does not report the Board's final action.

Common questions

Did including the installer's quote make the fabricator the contractor?

No.

What evidence was missing?

A contractual installation duty, supervision, testing, installation equipment, or correction responsibility.

Was every audit transaction sustained?

No. The reaudit removed duplicates and adjusted supported installed transactions.

Does this source record the Board's final decision?

No.

Citations and references

  • California Code of Regulations, title 18, section 1521(b)(2)(A) — contractor consumption requires furnished-and-installed materials
  • Western Concrete Structures, Inc. v. State Board of Equalization (1977) 66 Cal.App.3d 543, especially page 547 footnote 3 — ultimate installation responsibility and control distinguished; the identified Exhibit C page is not reproduced in the official PDF
  • Sales and Use Tax Annotations 190.0240 and 190.0960 — job-site delivery without installation treated as retail sale
  • February 4, 1994 representative letter — requested reassignment of the Appeals attorney or waived an Appeals-conference appearance; identified as Exhibit A but not reproduced in the official PDF
  • March 2, 1994 Appeals Section letter — declined reassignment; identified as Exhibit B but not reproduced in the official PDF
  • Audit workpapers and prime-contractor purchase orders — showed material purchases without installation responsibility; described but not reproduced in the official PDF
  • Petitioner's later documents — addressed installed materials, duplicate transactions, contract extras, and retail selling price; described but not reproduced in the official PDF
  • October 10, 1995 reaudit report — reduced understated retail sales to $2,764,186 and supplied the recommended redetermination basis; not reproduced in the official PDF

Source

Original ruling text

State of California

Board of Equalization
Legal Division
MIC: 82

Memorandum

To:

Mr. Gary J. Jugum

From:

Warren L. Astleford

Subject:

Sacramento Board Hearings – 2/21/96

Attached are the summaries for my Board hearings on 2/21/96.

190.1020

Date:

February 9, 1996

L. O--- & S---, INC. – ITEM #XX (wla)

-2-

February 9, 1996
190.1020

Petitioner’s claim for redetermination should be denied since petitioner is not a construction contractor within the meaning of Regulation 1521. Instead, petitioner was the manufacturer and retailer of tangible personal property that it provided to a sub-contractor for installation at a particular jobsite.

A construction contractor is a consumer of materials which are furnished and installed in the performance of a construction contract. (Reg. 1521(b)(2)(A).) The meaning of the term “installed” as it relates to construction contracts was explored in Western Concrete Structures, Inc. v. State Bd. of Equalization (1977) 66 Cal.App.3d 543. In Western, the plaintiff contracted with a general contractor to provide shop drawings and the fabrication of post-tensioning tendons. Plaintiff did not unload the tendons nor install or stress the tendons at the jobsite. Plaintiff did, however, inspect and approve the placement of the tendons, provided the equipment necessary to stress the tendons, was contractually responsible for correcting any problems caused by its design, and directly provided all supervision and testing in the installation of its product (since it was the only one with the expertise to do so). Under these facts, the court concluded that plaintiff was a construction contractor within the meaning of Regulation 1521 since it had the ultimate responsibility and control over the final installation of the products it moved to the jobsite.

In this case, petitioner acted only as the supplier of materials under purchased orders issued by the prime contractor. Petitioner would: 1) obtain a quote from a third party contractor who would install the property sold by petitioner; 2) petitioner would communicate that amount

L. O--- & S---, INC. – ITEM #XX (wla)

-3-

February 9, 1996
190.1020

to the general contractor, 3) the prime contractor would then issue a purchase order to petitioner for the bid amount less the installation amount; and 4) the prime contractor would directly contract with the subcontractor at the bid price communicated by the petitioner to the prime contractor. The audit work papers contain various purchase orders from prime contractors only for the purchase of supplies – not installation. There is no documentation specifying that the petitioner was contractually obligated to install the property it sold or that petitioner either supervised the installation of its products or provided the equipment necessary for installation. Petitioner further failed to provide such documentation upon reaudit that it was responsible for installation of the property it sold to the prime contractor. Petitioner fails to meet any of the elements set forth in Western Concrete Structures necessary for a finding that it was responsible for the installation of the property it supplied to its prime contractors during the audit period. For these reasons, the Department requests that petitioner claim be denied.

STATE OF CALIFORNIA

190.1020

BOARD OF EQUALIZATION

In the Matter of the Petition
for Redetermination Under the
Sales and Use Tax Law of:
L. O--- & S--- INC.
dba L. O--- & S--Petitioner

)
)
)
)
)
)
)
)

APPEALS SECTION
SUMMARY FOR BOARD HEARING

S- -- XX XXXXXX-010

[city]

Petitioner's representative, --- --- --- ---, Inc., requested in a February 4, 1994 letter (Exhibit A) that the Appeals attorney assigned to this matter be replaced because petitioner's representative believed that the Appeals attorney was strongly disposed to rule in favor of the Board's audit staff. Otherwise, petitioner would waive appearance at an Appeals conference. The Appeals Section, in a March 2, 1994 letter (Exhibit B) declined to reassign this matter. Thus, an Appeals conference was not held, nor was a Decision and Recommendation prepared. Business: Structural steel fabricator with some construction contracts.

Tax determined for the period 4-1-88 to 3-31-91
Reaudit adjustment

$176,403.58

  • 4,797.95

Proposed redetermination
Credit concurred in

$171,605.63
300.00

Protested

$171,905.63

Proposed tax redetermination
Estimated interest to February 29, 1996

$171,605.63
112,679.33

Total tax and estimated interest
Payments

$284,284.96

  • 60,000.00

Balance

$224,284.96

Estimated additional monthly
interest to accrue March 1,1996

$1,116.06

L. O--- & S--- Inc.
S- -- XX XXXXXX-010

Page 2 of 3

February 9, 1996
190.1020

The protested tax is measured by $2,764,186 representing an understatement of retail sales established on an actual basis. No penalty was added to the determination. Statement of Unresolved Issue Whether the evidence establishes that petitioner was contractually responsible for the installation of steel furnished and fabricated by petitioner under lump sum construction contracts. Petitioner's Contention There are several transactions included in the audit classified as retail sales which are construction contracts. Appeals Section Summary Background Petitioner entered into contracts which did not state that petitioner was responsible for installation of the steel that petitioner fabricated. Petitioner would issue a bid to a prime contractor including a quoted price from a third party who would be the installing contractor of the steel. The name of the proposed installer and the installer's price quote was communicated to the prime contractor as part of the bid. The prime contractor would then issue a purchase order to petitioner for the bid amount less the installation portion. The prime contractor would issue a purchase order directly to the installing sub-contractor for the amount quoted by petitioner. Petitioner was not responsible for any supervision of the installation. The reason for handling the installation in this manner is that the prime contractor is a union business and petitioner is not. The installing sub-contractors were also union businesses. Petitioner argues that even though it did not do the physical installation, it was responsible for the installation. Therefore, pursuant to Western Concrete Structures, Inc. v. State Board of Equalization (1977) 66 Cal.App.3d 543, (WCS) it is a construction contractor pursuant to Sales and Use Tax Regulation 1521. Thus, the proper tax liability is the cost of materials installed on lump-sum contracts and not the retail selling price of tangible personal property. Subsequently, petitioner presented additional documents arguing that certain materials were furnished and installed by petitioner as a construction contractor, not as a retailer. In addition, petitioner argues that 5 transactions were included in the audit twice, extras added to the contract and installed were considered retail sales, and the amount shown as the retail selling price on certain retail sales was overstated.

L. O--- & S--- Inc.
S- -- XX XXXXXX-010

Page 3 of 3

February 9, 1996
190.1020

The Sales and Use Tax Department prepared a reaudit where they deleted the 5 transactions that were duplicated, made adjustments on contracts and extras where petitioner proved that the materials were installed, and allowed an adjustment to one retail sale. No adjustments were made on the remaining transactions due to lack of documentary evidence supporting petitioner’s position. The reaudit reduced the understated retail sales by $77,559 to
$2,764,186.
Decision and Recommendation
The Appeals Section recommends that the tax be redetermined in accordance with the reaudit report dated October 10, 1995. Appeals Section's Analysis A construction contractor is a consumer of materials which are furnished and installed in the performance of a construction contract (Sales and Use Tax Regulation 1521(b)(2)(A)). However, if a fabricator delivers property to a job-site and does not install the property, the fabricator is a retailer (Sales and Use Tax Annotations 190.0240 and 190.0960). In Western Concrete Structures, Inc., supra, the Court found that there was evidence that WCS was contractually responsible for, and directly provided, all supervision and testing of the installation work performed and that WCS was required to make any necessary corrections in the materials whenever there was a force failure. (Attached as Exhibit C is a copy of page 547 of the Court of Appeal opinion in Western Concrete Structures, Inc., which in footnote 3 details the work performed by WCS.) The available evidence in this matter does not show that petitioner was responsible for the installation as in Western Concrete Structures, Inc., thus, petitioner is a retailer of tangible personal property and no adjustment is warranted. Summary prepared by the Appeals Review Section ARS:me:--1-10-95; rev. 11-21-95

What does the law say today, for your facts?

This ruling is from 1996. Ezel checks current California tax law against your situation and cites the authority it relies on.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace