Mortar strength testing and controlling contractor duties in steel erection

Summary A contractor asked how to meet a steel-erection mortar strength test requirement when no suitable ASTM method existed, and whether it could delegate its other duties. OSHA said it would defer enforcement of the mortar test rule until a suitable test or substitute existed. It also said a controlling contractor may contract out tasks but remains responsible for compliance; the deferral’s current status is uncertain.
Document
Federal opinion letter
Agency
Occupational Safety and Health Administration (OSHA)
Document number
2002-12-27-0
Date issued
December 27, 2002
Status
Unknown
The letter states a temporary enforcement deferral until an appropriate mortar test method or substitute is defined; OSHA does not state on this page whether that condition remains in effect.
Status last verified October 9, 2026

Apply this to your situation

This page explains the general guidance. Ask about your specific situation and see what current federal labor law says, with citations.

The current status of this document is unclear
The letter states a temporary enforcement deferral until an appropriate mortar test method or substitute is defined; OSHA does not state on this page whether that condition remains in effect. It may no longer reflect the agency's current position. Treat this page as historical context, not current guidance, and verify current law before relying on anything here.
About this page: The full text below is the official document from Occupational Safety and Health Administration (OSHA). Ezel adds the plain-English summary and tracks the document's status. The official source linked on this page is authoritative for any reliance.

December 27, 2002

Sean Purcell

Safety Officer

RPCarbone Company

[Recipient address omitted]

Re: What are an employer's obligations under Part 1926 Subpart R with respect to testing mortar? What OSHA responsibilities does a controlling contractor have under Subpart R when it subcontracts duties placed by Subpart R on the controlling contractor? §1926.752(a)(1); mortar testing requirements; contracting-out duties of controlling contractor

Dear Mr. Purcell:

This is in response to your letter of March 19, 2002, requesting clarification of the mortar testing requirements in §1926.752(a)(1) and of controlling contractor responsibilities under the new steel erection standard. We apologize for the delay in responding. We have paraphrased your questions below.

Question (1): Section 1926.752(a)(1) requires that "the mortar in masonry piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection." However, there is no "appropriate ASTM standard test method" for mortar strength. ASTM C780 - Method for Preconstruction and Construction Evaluation of Mortars for Masonry assesses the consistency of field-mixed mortar, but does not assess the compressive strength of the mortar. What, then, are employers required to do under this provision?

Answer

Since there currently is no ASTM standard test method to test the compressive strength of field-cured mortar, OSHA will not enforce the requirements of §1926.752(a)(1) until such time as we are able to define an appropriate substitute or until an appropriate ASTM test method is developed.

Question (2): Subpart R places several specific responsibilities on the controlling contractor. May a general contractor contract with the steel erector to perform those duties? If so, is the controlling contractor responsible if the steel erector fails to perform them?

Answer

There are several requirements in the new standard that require specific actions by the controlling contractor. While the controlling contractor may contract with another entity to perform them, the controlling contractor remains responsible for compliance with those duties. For example, in Qs&As 13 and 14 of the compliance directive, we stated:

Question 13: Can the controlling contractor contract with subcontractors to perform the work required by §1926.752(a)? If so, is the controlling contractor still responsible for these duties after subcontracting them out?

Answer: Under §1926.752(a), the controlling contractor "shall ensure that the steel erector is provided" with written notification that the concrete has cured to the specified degree. While the controlling contractor may contract with subcontractors to do the requisite tests and provide the written notification, the controlling contractor remains responsible for ensuring that the subcontractor does that work. If the subcontractor fails to do the test and provide the notification, the controlling contractor may be cited for a violation under §1926.752(a).

Question 14: Section 1926.752(a)(1) requires the controlling contractor to ensure that the steel erector is provided with written notifications that the concrete and masonry meet certain specified strength requirements. To what extent is the controlling contractor responsible for the accuracy of the strength assessments in the written notifications?

Answer: As explained in Q&A #12, the controlling contractor can choose to either: (1) conduct the tests itself, if it has the expertise to do so; or (2) select an entity that has the expertise to do the test. If the controlling contractor does the tests itself, it is responsible for the accuracy of the tests.

If the controlling contractor selects someone else to do the tests, it is responsible for exercising reasonable care in the selection of the testing entity. As long as it has a reasonable basis for believing that the testing entity is competent and capable of doing the work, and the controlling contractor has no actual knowledge that the tests results are wrong, erroneous test results will not constitute a violation of §1926.752(a).

Note that, for some of the controlling contractor responsibilities, there may be practical difficulties in contracting with the steel erector to perform them. For example, one of the duties is to provide written notification to the steel erector that anchor bolt modifications/repairs have been approved by the project engineer of record (see §§1926.752(a),1926.755(b)). A primary reason for this provision was to the address the fact that the steel erector often does not know that an anchor bolt was modified or repaired. Without that knowledge, it would not know to check with the project engineer to find out if the modification/repair was adequate. The duty for ensuring that this notification is made was placed on the controlling contractor because it is usually in the best position to obtain that information (see 66 FR 5206).

If you need additional information, please contact us by fax at: U.S. Department of Labor, OSHA, Directorate of Construction, Office of Construction Standards and Guidance, fax # 202-693-1689. You can also contact us by mail at the above office, Room N3468, 200 Constitution Avenue, N.W., Washington, D.C. 20210, although there will be a delay in our receiving correspondence by mail.

Sincerely,

Russell B. Swanson, Director

Directorate of Construction

What does federal law require in your situation?

Ezel checks current federal labor law against your facts and answers with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace