Process hazard analysis deadlines with one or two covered processes

Summary An employer asked how process hazard analysis percentage deadlines applied at sites with just one or two covered processes. OSHA said a single covered process generally had to be analyzed in full by the first deadline and described how the phased schedule applied to two processes.
Document
Federal opinion letter
Agency
Occupational Safety and Health Administration (OSHA)
Document number
1993-06-03-0
Date issued
June 3, 1993
Status
Archived by the agency
OSHA labels this an archive document and warns that it may no longer represent current policy.
Status last verified October 9, 2026

Apply this to your situation

This page explains the general guidance. Ask about your specific situation and see what current federal labor law says, with citations.

The current status of this document is unclear
OSHA labels this an archive document and warns that it may no longer represent current policy. It may no longer reflect the agency's current position. Treat this page as historical context, not current guidance, and verify current law before relying on anything here.
About this page: The full text below is the official document from Occupational Safety and Health Administration (OSHA). Ezel adds the plain-English summary and tracks the document's status. The official source linked on this page is authoritative for any reliance.

NOTICE: This is an OSHA Archive Document, and may no longer represent OSHA Policy. It is presented here as historical content, for research and review purposes only.

June 3, 1993

Ms. Shelly Howard
Tyson Foods, Inc.
[Recipient address omitted]
Dear Ms. Howard:

This is in response to the February 12 letter from Tyson Foods, Inc., signed by Ms. Shannon Weather, to Mr. James F. Foster, Director Office of Information and Consumer Affairs of the Occupational Safety and Health Administration (OSHA). Your letter was forwarded to the Directorate of Compliance Programs for response. In the April 27 telephone call between you and Mr. Ronald Davies of my staff, you disclosed that Ms. Weather no longer is employed by Tyson Foods, Inc., and you asked that this response be addressed to you. Please accept our apology for the delay in responding.

In the February 12 letter, clarification was requested on the 1910.119(e) deadlines for completion of process hazard analysis (PHA's). Specifically, does the percentage requirement pertain even if one or two processes are present at a worksite? Also, should 100% of the PHA be completed by May 26, 1994, if one process is present?

Normally, if only one process (covered by the PSM standard) is present, the PHA for the covered process must be completed in its entirety as soon as possible but no later than May 26, 1994. If there are only two covered processes then a PHA on the higher priority process must be completed in its entirety as soon as possible but not later than May 26, 1994, and a PHA on the second process must be completed in its entirety as soon as possible but no later than May 26, 1995.

Thank you for your interest in occupational safety and health. If we may be of further assistance please contact us.

Sincerely,
Roger A. Clark, Director
Directorate of Compliance Programs

What does federal law require in your situation?

Ezel checks current federal labor law against your facts and answers with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace