June 4, 1979
Mr. Victor J. Greco
Regional Supervisor
Maryland Occupational
Safety and Health
[Recipient address omitted]
Dear Mr. Greco:
This is in response to your recent inquiry requesting an interpretation of our trenching requirements.
29 CFR 1926.653(c) defines "Bank" as a mass of soil rising above a digging level. This area was addressed to take into consideration trenches passing close to a side of a hill or a vertical face that would have a direct bearing on the sides of the trench being excavated. The digging level could be considered as grade.
29 CFR 1926.651(i)(1) and (2) requires that excavated or other material shall be effectively shored and retained. If a compliance officer observed an employee working below grade (digging level) in a trench 6 feet in depth, 10 feet in length and 4 feet in width in unstable or soft material with a soil bank rising 6 feet above grade, he would cite 29 CFR 1926.652(b) for the trench violation, 29 CFR 1926.651(i)(1) or (2) for an excavated material violation and 29 CFR 1926.652(a) for a bank violation.
I hope this information will be helpful to you. If I may be of any further assistance, please feel free to contact me.
Sincerely,
Grover C. Wrenn Director,
Federal Compliance
and State Programs
What does federal law require in your situation?
Ezel checks current federal labor law against your facts and answers with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace