Solid-fuel salamanders during concrete curing

Summary A construction-employer group sought a variance for solid-fuel heaters used during concrete curing. OSHA said the ban targeted open, spark-producing units in buildings or on scaffolds, not properly built and equipped covered units in structures under construction. It closed the variance request but cited other applicable heater, exposure, and concrete-work precautions.
Document
Federal opinion letter
Agency
Occupational Safety and Health Administration (OSHA)
Document number
1977-03-25
Date issued
March 25, 1977
Status
Active
Status last verified October 10, 2026

Apply this to your situation

This page explains the general guidance. Ask about your specific situation and see what current federal labor law says, with citations.

About this page: The full text below is the official document from Occupational Safety and Health Administration (OSHA). Ezel adds the plain-English summary and tracks the document's status. The official source linked on this page is authoritative for any reliance.

March 25, 1977

Mr. James F. McGlame, Jr.
President
Massachusetts Council of Construction
Employers, Inc.
[Recipient address omitted]
Dear Mr. McGlame:

This is in reference to your class application for variance from Section 1926.154(d) Solid Fuel Salamanders, of the Occupational Safety and Health Standards, for which and interim order was issued.

Section 1926.154(d) prohibits the use of solid fuel salamanders in buildings and on scaffolds. This standard was adopted to prevent the fire and carbon monoxide hazards associated with the burning of spark-producing fuels such as wood and paper in open salamanders. The ban was not intended to apply to properly constructed and equipped solid fuel salamanders which are fueled by coke of coal and are used in structures under construction. The use of open solid fuel salamanders (heating units with combustion exhausting into the surrounding enclosed atmosphere) will continue to be prohibited on scaffolds or in buildings defined as roofed and walled structures. For these reasons, a variance from Section 1926.154(d) to permit the use of solid fuel salamanders for curing of concrete in buildings under construction is not necessary.

Section 1926.700(a), however, requires that all equipment and materials used in concrete construction and masonry work shall meet the applicable requirements for design, construction, inspection, testing, maintenance and operations as prescribed in ANSI A10.9-1970, Safety Requirements for Concrete Construction and Masonry Work.

Paragraph 5.6.4 of ANSI A10.9-1970 states in part: "When salamanders of similar heating devices are used to protect concrete, the following precautions shall be taken:

(1) All salamanders shall be covered and equipped with exhaust stacks.

(2) Heating units shall not be set on or placed near wood or combustible materials.

(3) Salamanders should be attended at all times, and suitable fire extinguishers maintained readily available in the area."

In addition, it should be noted that other applicable requirements of 29 CFR 1926, particularly Section 55(a) and Section 154 shall be observed.

No further action will be taken on your request for a variance. The interim order granted on December 27, 1973 is now moot.

All companies included in the request for a variance shall be informed of this decision and shall be required to inform their employees in the same manner in which they were informed of the request for a variance.

Sincerely,
James J. Concannon
Director Office of Variance Determination

What does federal law require in your situation?

Ezel checks current federal labor law against your facts and answers with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace