November 11, 1975
Mr. Charles A. Della
Assistant Commissioner
Department of Licensing and Regulation
[Recipient address omitted]
Dear Mr. Della:
In response to your letter of October 21, 1975 concerning 29 CFR 1926.800(c)(2)(v) and 29 CFR 1926.803(i)(1) we concur with the interpretations indicated in your letter.
- [29 CFR 1926.800(k)(2)]: Requires the supply of fresh air to be not less than 200 cubic feet per minute for each employee in a tunnel work area where operations are conducted at atmospheric pressure. This standard does not apply to compressed air work.
- 29 CFR 1926.803(i)(1): The sentence "Ventilating air shall be not less than 30 cubic feet minute." Means not less than 30 cubic feet minute man during compressed air work.
Sincerely yours,
DAVID H. RHONE
Assistant Regional Director
Occupational Safety and Health Administration
[Corrected 05/28/2004]
What does federal law require in your situation?
Ezel checks current federal labor law against your facts and answers with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace