Summary A company asked whether a powered window-cleaning platform used every 120 days needed inspection and testing every 30 days while locked in storage. OSHA said the 30-day inspection and test did not apply during non-use, but the platform had to be inspected, tested, and documented before the next cleaning cycle. It also explained the inspection interval for a platform in use.
Document
Federal opinion letter
Agency
Occupational Safety and Health Administration (OSHA)
Document number
1975-08-25
Date issued
August 25, 1975
Status
Active
Status last verified October 10, 2026

Apply this to your situation

This page explains the general guidance. Ask about your specific situation and see what current federal labor law says, with citations.

About this page: The full text below is the official document from Occupational Safety and Health Administration (OSHA). Ezel adds the plain-English summary and tracks the document's status. The official source linked on this page is authoritative for any reliance.

August 25, 1975

Mr. K. M. Stead
Regional Manager
The Equitable Life Assurance
Society of the United States
[Recipient address omitted]

Dear Mr. Stead:

This is in response to your letter dated July 28, 1975, concerning certain inspections required by Section 1910.66(e)(3) Powered Platforms for Exterior Building Maintenance, of the Occupational Safety and Health Standards.

You have questioned the requirement for a 30 day inspection and test contained in the above standard as it pertains to a powered platform used by the Gem Window Cleaning Company of New York.

The requirements of the standard are, in part, that each installation undergo a maintenance inspection and test every 30 days except where the cleaning cycle is less than 30 days such inspection and test shall be made prior to each cleaning cycle. The powered platform referred to in our June 6, 1975 letter is used only on a 120 day cleaning cycle. It is placed in storage and locked up between these cycles. In this instance the required inspection and test must be conducted and documented prior to the start of the next cleaning cycle.

For the purpose of clarification, a powered platform in use shall undergo a maintenance inspection and test every 30 days except where the cleaning cycle is less than 30 days, such inspection and test shall be made prior to each cleaning cycle. With respect to non-use (in storage, undergoing repairs, etc.) a 30 day maintenance inspection and test would not be required.

If I can be of further service, please contact me.

Sincerely,
Bert M. Concklin
Deputy Assistant Secretary

What does federal law require in your situation?

Ezel checks current federal labor law against your facts and answers with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace