J S Sand & Gravel, Inc. (Commission decision, October 7, 2004)

J S Sand & Gravel, Inc. (FMSHRC YORK 2004-50-M, YORK 2004-51-M, YORK 2004-52-M, YORK 2004-53-M): Three reopening requests denied, one remanded

Decision type
Commission decision
Dockets
YORK 2004-50-M, YORK 2004-51-M, YORK 2004-52-M, YORK 2004-53-M
Decided
October 7, 2004
Outcome
Mixed result
Precedential status
Citable Commission precedent
Checked against source
2026-08-09

Apply this precedent to your situation

This is citable Commission precedent from 2004, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2004
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

J S Sand & Gravel asked the Commission to reopen four penalty assessments that had become final after the company did not timely contest them. The Commission denied reopening for three assessments because the requests came more than one year after the orders became final and the company gave no explanation for its failures to respond. For the fourth assessment, the Commission remanded the matter to the Chief Administrative Law Judge to determine whether good cause supported relief. A concurring and dissenting opinion would have denied relief for that fourth assessment as well.

Decision snapshot

  • Cited authority: 29 C.F.R. §§ 2700.1(b) and 2700.12; 30 U.S.C. §§ 801 and 815(a)
  • Outcome: Reopening was denied for three assessments, while the fourth was remanded for a good-cause determination.
  • Key point: A late request to reopen a final penalty order needs a timely and supported explanation for the failure to contest.

Full text (FMSHRC public release)

J S SAND & GRAVEL, INC. -- October 7, 2004

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 New Jersey Avenue, NW,

Suite 9500

Washington, DC 20001

October 7, 2004

SECRETARY OF LABOR, : Docket No. YORK 2004-50-M
MINE SAFETY AND HEALTH : A.C. No. 30-03325-05501
ADMINISTRATION (MSHA) :
: Docket No. YORK 2004-51-M
: A.C. No. 30-03325-05502
:
v. : Docket No. YORK 2004-52-M
: A.C. No. 30-03325-05503
:
: Docket No. YORK 2004-53-M
J S SAND & GRAVEL, INC. : A.C. No. 30-03325-08141

BEFORE: Duffy, Chairman; Jordan, Suboleski, and Young, Commissioners

ORDER

BY: Duffy, Chairman; Suboleski, and Young, Commissioners

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. 801 et seq. (2000) ("Mine Act").1 On June 29, 2004, the Commission received from J S Sand & Gravel, Inc. ("JSSG") a letter from its president which included a request that the Commission reopen four penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. 815(a). On July 8, 2004, the Secretary of Labor filed a Response to Request to Reopen Penalty Assessments.

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. 815(a). In its petition, JSSG gives no reason for its failure to contest any of the four penalty assessments.

A. Docket Nos. YORK 2004-50-M, YORK 2004-51-M, and YORK 2004-52-M

Based on the Secretary's submission, MSHA issued proposed assessment A.C. No. 30-03325-05501 (YORK 2004-50-M) to JSSG on May 11, 2001, JSSG received the proposed assessment on May 17, 2001, and it became a final order on June 22, 2001. S. Resp. at 1 & Attach. A. Similarly, MSHA issued proposed assessment A.C. No. 30-03325-05502 (YORK 2004-51-M) to JSSG on August 30, 2002, JSSG received it on September 6, 2002, and it became a final order on October 11, 2002. Id. at 2 & Attach. B. In addition, MSHA issued proposed assessment A.C. No. 30-03325-05503 (YORK 2004-52-M) to JSSG on January 16, 2003, JSSG received it on January 24, 2003, and it became a final order on February 27, 2003. Id. at 2 & Attach. C. JSSG provides no reason in its request to reopen why it did not timely contest any of the three assessments.

The Secretary opposes reopening all three proposed assessments because JSSG's requests were filed approximately three years, 20 months, and 16 months, respectively, after the assessments became final. S. Resp. at 1-2. The Secretary attached to her response copies of the proposed assessments, signed return receipt verification cards indicating JSSG had received the proposed assessments, and MSHA's delinquent payment notice for each assessment. Id., Attach. A to C. JSSG did not reply to the Secretary's response.

We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) ("JWR"). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure. See 29 C.F.R. 2700.1(b) ("the Commission and its judges shall be guided so far as practicable by the Federal Rules of Civil Procedure"); JWR, 15 FMSHRC at 787. For instance, relief from a final Commission judgment or order is available to a party under Rule 60(b)(1) in circumstances such as mistake, inadvertence, or excusable neglect. We have observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond to a penalty petition, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

However, under Rule 60(b) any motion for relief must be made within a reasonable time, and in the case of mistake, inadvertence, or excusable neglect not more than one year after the order was entered. Fed. R. Civ. P. 60(b). Here, JSSG has requested reopening of the three proposed assessments more than one year after each assessment became a final Commission order, and has provided no explanation of why it never responded to the correspondence it received from MSHA. Consequently, we deny JSSG's motion for relief from the final orders in Docket Nos. YORK 2004- 50-M, YORK 2004-51-M, and YORK 2004-52-M.

B. Docket No. YORK 2004-53-M

JSSG also requests the Commission to reopen another proposed assessment, A.C. No. 30- 03325-08141 (YORK 2004-53-M). According to JSSG, that assessment issued on September 11, 2003. The Secretary responds that because JSSG identifies no grounds for requesting reopening of the assessment, the Commission should direct JSSG to provide a detailed explanation of why it believes circumstances warrant reopening. S. Resp. at 3.

JSSG has provided no explanation for its failure to timely contest the proposed assessment. On the basis of the present record, we are thus unable to evaluate the merits of JSSG's request to reopen. We hereby remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for JSSG's failure to timely contest the penalty proposal and whether relief from the final order should be granted. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission's Procedural Rules, 29 C.F.R. Part 2700.

Accordingly, we deny JSSG's request to reopen the penalty assessments in Docket Nos. YORK 2004-50-M, YORK 2004-51-M, and YORK 2004-52-M and the proceedings are hereby dismissed, and we remand Docket No. YORK 2004-53-M for further proceedings as appropriate.

______
Michael F. Duffy, Chairman

______
Stanley C. Suboleski, Commissioner

______
Michael G. Young, Commissioner

Commissioner Jordan, concurring in part and dissenting in part:

I agree with the majority's decision to deny JSSG's request to reopen the penalty assessments in Docket Nos. YORK 2004-50-M, YORK 2004-51-M, and YORK 2004-52-M. However, I would also deny the operator's request for relief from the final order in YORK 2004-53-M. Pursuant to Rule 60(b) of the Federal Rules of Civil Procedure, we have previously afforded a party relief from a final order on the basis of inadvertence or mistake. Slip op. at 2. However, JSSG has failed to provide any explanation to justify its failure to timely contest the proposed penalty assessment. See Tanglewood Energy, Inc., 17 FMSHRC 1105, 1107 (July 1995) (denying request to reopen final Commission order where operator failed to set forth grounds justifying relief). I also note that this matter involves four proposed penalty assessments issued between May 22, 2001 and September 11, 2003 which the operator failed to timely contest. Consequently, I respectfully dissent.

______
Mary Lu Jordan, Commissioner

Distribution:

Jeff DeFranco, President

J S Sand & Gravel, Inc.

139 C Peconic Avenue

Medford, NY 11763

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., 22nd Floor West

Arlington, VA 22209-2247

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

FOOTNOTE:

1 Pursuant to Commission Procedural Rule 12, on our own motion, we hereby consolidate docket numbers YORK 2004-50-M, YORK 2004-51-M, YORK 2004-52-M, and YORK 2004-53-M, all captioned J S Sand & Gravel, Inc., and all involving similar procedural issues. 29 C.F.R. 2700.12.

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Try Ezel Pro free for 7 days. Cancel anytime before the trial ends and you pay nothing.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace