FMSHRC ALJ decision Docket WEVA 92-729-R Decided March 26, 1992 Modified Judge Avram Weisberger Transcribed from scan

Eagle Nest, Inc.

Eagle Nest, Inc. (FMSHRC WEVA 92-729-R): Trolley-wire citation amended to non-S&S

Apply this to your situation

This order from 1992 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1992
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Transcribed from a scanned original: FMSHRC released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (fmshrc.gov)

Plain-English summary

Eagle Nest contested a citation alleging that trolley wires at its longwall mine were too close to pillar workings. Judge Avram Weisberger found that the wires were less than 150 feet from the gob area and that the operator violated 30 C.F.R. § 75.1002. He found, however, that the evidence did not establish a reasonable likelihood that methane would reach the trolley wires and cause an injury during continued mining. The citation was amended from significant and substantial to non-S&S, and the notice of contest was dismissed.

Decision snapshot

  • Cited standard: 30 C.F.R. § 75.1002
  • Outcome: The violation was affirmed but amended to non-S&S, and the notice of contest was dismissed.
  • Key point: An S&S finding requires evidence that the hazard contributed to by the violation would reasonably likely result in an injury during continued normal mining.

Full text (FMSHRC public release)

EAGLE NEST, INC., : CONTEST PROCEEDING
Contestant :
v. : Docket No. WEVA 92-729-R
: Citation No. 3754287; 3/2/92
SECRETARY OF LABOR, :
MINE SAFETY AND HEALTH : East Nest Mine
ADMINISTRATION (MSHA), :
Respondent :
:

                         DECISION

Appearances: David J. Hardy, Esq., Jackson and Kelly,
Charleston, West Virginia, for Contestant;
Pamela Silverman, Esq., U.S. Department of Labor,
Office of the Solicitor, Arlington, Virginia,
for Respondent.

Before: Judge Weisberger

 This case is before me based upon a Notice of Contest

filed by the Operator on March 5, 1992, challenging the issuance
of Citation No. 3754287 which alleges a violation of 30 C.F.R.
75.1002.(Footnote 1) On the same date, the Operator filed a
Motion for Expedited Proceedings. In telephone conference calls
on March 5 and 6, 1992, counsel for the Operator presented
argument in favor of the Motion, and counsel for the Secretary
presented argument in opposition to the Motion. The Motion was
granted, and the case was scheduled for hearing on March 12, 1992
in Charleston, West Virginia and was heard on that date. At the
hearing, Ronald Lorrison, Thomas Hager, and Steve Alexander
testified for the Operator. Ernest H. Thompson and Ernest
Sheppard testified for the Secretary. The parties waived their
right to submit written post hearing briefs, and in lieu thereof
presented oral argument. The Secretary, in addition, filed a
written argument on March 17, 1992, and the Operator filed a
response to this argument on March 18, 1992.


1The Secretary filed an Answer on March 12, 1992.

               FINDING OF FACT AND DISCUSSION


          I.    Violation of 30 C.F.R. § 75.1002

 On February 19, 1992, longwall mining had commenced in the

E-Panel at the Operator's Eagle Nest Mine. In general, as
longwall mining proceeds, a gob area is built up behind (inby) the
longwall face. In the E-Panel immediately inby the gob
(mined-out areas), the Operator located a set up entry wherein
various equipment to develop a future longwall panel was stored.
Immediately inby this entry, a bleeder entry vented gases from the
gob to the return entries, and then out of the mine. An intake
entry, containing trolley wires and tracks, was located immediately
inby the bleeder entry, and was separated from the bleeder entry by
a double row of cement blocks, each row consisting of blocks 8
inches x 8 inches x 16 inches. On February 24, 1992, as part of the
normal longwall mining process, the first roof fall in the gob area
occurred.

 On February 27, 1992, the entry containing the trolley

tracks and wires was inspected by MSHA Inspector Ernest Thompson.
The trolley wires were 108 feet from the inby end of the set-up
entry, but were approximately 350 feet from longwall face.

 Thompson issued a Citation alleging a violation of 30 C.F.R.

§ 75.1002 which, as pertinent, provides that trolley wire
"...shall be kept 150 feet from pilar workings". (emphasis
added). The initial issue for resolution is whether the term
"pilar workings", encompasses the gob or mined out area or,
whether it means the longwall face.

 The term "pilar workings", as set forth in Section 75.1002,

supra, is not defined in Volume 30 of the Code of Federal
Regulations. Section 75.1002, supra, sets forth the statutory
provision found at Section 310(c) of the Federal Mine Safety and
Health Act of 1977 (P.L. 95-164, "the 1977 Act", and, its
predecessor, Section 310(c) of the Federal Coal Mine Health and
Safety Act of 1969, (P.L. 91-173, "the 1969 Act"). Neither the
1969 Act, nor the 1977 Act contains any definition of the term
"pilar workings". Neither is that term defined in A Dictionary
of Mining, Mineral, and Related Terms (U.S. Department of the
Interior, 1968). Hence, in analyzing the scope to be accorded
the term "pilar workings", emphasis is placed on the
Congressional intent behind the enactment of Section 310(c),
supra.

 The only indication of any Congressional intent with regard

to Section 310(c) supra, consists of the following language
contained in the Section-by-Section analysis of the Senate
version of the 1969 Act "This Section(Footnote 2) requires that
...trolley wires...be kept at least 150 feet from pilar
workings...because the ventilating current may contain explosive
mixtures of gas. Also, pilar falls may damage and cause short
circuits in the cables and transformers." (S. Rep. No. 91-411,
91st, Cong., 1st Sess. 77, reprinted in Legislative History
Federal Coal Mine Health and Safety Act, at 77) Since the gob
area of a longwall panel can liberate gas, and can cause a
"sudden outrush of air" (Tr. 147) when the gob roof falls, even
after the first fall, it would appear that Congress, in enacting
Section 75.1002 supra, intended to minimize the hazard of gob
gases being forced over trolley wires, a source of ignition (See,
Consolidation Coal Company, 4 FMSHRC 2153, 2161 (1982), petition
for discretionary review denied (January 14, 1983), wherein Judge
Broderick, in analyzing whether the measurement of the distance
to certain non-permissible equipment should be taken from the
outby corner of the pilar being mined, or from the actual place
of the cut, set forth as follows with regard to Section 75.1102
supra: "The hazard which the standard is designed to prevent is
an ignition or explosion which could result from methane being
forced back over electrical equipment which may arc."

 Thomas Hager, the Operator's mine foreman, and Steve

Alexander, underground superintendent at Eagle Nest, both of whom
have more than 20 years experience each in the mining industry,
testified, in essence, that the term "pilar workings" means the
area where coal is being extracted i.e., the longwall face.
Also, in support of its position herein, the Operator relies on
the Secretary's Program Policy Manual, Volume V, Part 75,
wherein, under the heading 75.1002-1, location of other electric
equipment; requirements for permissibility, the following
language is set forth: "In longwall mining, the 150-foot
distance shall be measured in a straight line from the wire,
cable or electric equipment in question to the outby edge of the
longwall roof-support system." It was not controverted that this
language contemplates that the measurement be taken from the
longwall face.

 The Program Policy Manual, supra, does not explicitly define

the term "pilar workings". Further, to the extent that the
Program Policy Manual supra, is inconsistent with the
expressed Congressional intent behind the enactment of Section
310(c), supra, I accord more weight to the latter with regard to
the scope to be accorded the term "pilar workings". Also, I have
considered the definitions of the term "pilar workings", as
provided by Hager and Alexander. Although they each have
extensive mining experience, they did not explicitly testify as to
the common usage of that term in the industry.


2In the Senate version of the 1969 Act, the statutory
provision at issue was set forth as Section 211(c).

Instead, it appears that their definitions of "pilar workings"
were based on what the term meant to them. In contrast, I place
more weight on the testimony of Ernest Sheppard an MSHA
Ventilation Specialist who indicated that, in his experience
mining prior to MSHA, and during the time he has worked for MSHA,
he has not known the term "pilar workings" to exclude the gob
area. (Tr.270)

 Hence, for all the above reasons I conclude that the

Operator violated Section 75.1002 supra, inasmuch as the trolley
wires were located less than 150 feet from the set-up entry which
is immediately inby the gob area which is part of the "pilar
workings."

            II.   Significant and Substantial


 The Citation herein alleges that the violation is

significant and substantial. In Southern Ohio Coal Company, 13
FMSHRC 912, (1991), the Commission reiterated the elements
required to establish a significant and substantial violation as
follows:

      We also affirm the judge's conclusion that the
 violation was of a significant and substantial nature.
 A violation is properly designated as significant and
 substantial "if, based on the particular facts
 surrounding that violation, there exists a reasonable
 likelihood that the hazard contributed to will result
 in an injury or illness of a reasonably serious
 nature." Cement Division, National Gypsum Co.,
 3 FMSHRC 822, 825 (April 1981). In Mathies Coal Co., 6
 FMSHRC 1, 3-4 (January 1984), the Commission explained:

           In order to establish that a violation
      of a mandatory standard is significant and
      substantial under National Gypsum the
      Secretary must prove: (1) the underlying
      violation of a mandatory safety standard;
      (2) a discrete safety hazard -- that is, a
      measure of danger to safety -- contributed to
      by the violation; (3) a reasonable likelihood
      that the hazard contributed to will result in
      an injury; and (4) a reasonable likelihood that
      the injury in question will be of a reasonably
      serious nature.

      See also Austin Power Co. v. Secretary, 861 F.2d
 99, 103-04 (5th Cir. 1988), aff'g, 9 FMSHRC 2015, 2021
 (December 1987) (approving Mathies criteria). The
 third element of the Mathies formula "requires that the
 Secretary establish a reasonable likelihood that the
 hazard contributed to will result in an event in which

 there is an injury" (U.S. Steel Mining Co., 6 FMSHRC 1834,

1836 (August 1984)), and also that the likelihood of injury be
evaluated in terms of continued normal mining operations (U.S.
Steel Mining Co., Inc. 6 FMSHRC 1573, 1574 (July 1984); see also
Halfway, Inc., 8 FMSHRC 8, 12 (January 1986)." (Southern Ohio,
supra at 916-917).

 With regard to the first element, I find that a violation

Section 75.1002 supra has been established. Also, as discussed
above, infra, the presence of trolley wires 108 feet from the gob
contributed to the hazard of an explosion, inasmuch as the
trolley wires, an ignition source, could have come in contact
with gob gas. However, the record fails to establish the third
element set forth in Mathies, supra, i.e. a reasonable likelihood
that the hazard contributed to would result in an injury, as it
has not been established that there was a "reasonable likelihood"
that the hazard contributed to would result in an event in which
there is injury", U.S. Steel Mining Co., 6 FMSHRC 1834, 1836
(August 1984).

 Hager, on cross examination, agreed with Thompson that the

trolley wires are an ignition source. Readings taken by Thompson
with an MX270 Methane Tester on February 27, 1992, did not reveal
the presence of methane. Samples taken at two evaluation points
on February 27, indicated the presence of 1/100th of one percent
and 1/10th of one percent of methane, and, at the latter
location, 8,706 cubic feet of methane in 24 hours. The amount of
methane produced was not within the explosive range, and was
considered by Thompson to be "not high", (Tr. 173), but the
positive readings indicated to him that the gob area was
liberating methane. However, the area that the evaluation points
were located in was approximately three crosscuts removed from
the track entry in question, and separated by stoppings from that
entry. Also, any methane present at the evaluation points would
go directly into the return and be vented out of the mine.

 Of more significance is the fact that any hazard of a gas

explosion occasioned by the location of the trolley wires, is
minimized by the presence of a double row of cement block
stoppings, 8 inches x 8 inches x 16 inches, between the bleeder
entry and the trolley track entry. Although Thompson performed a
smoke test which showed air going from the bleeder to the track
through four stoppings on March 3 and 4, and observed a hole 6
inches by 6 inches between the rib and one of the stoppings,
there is insufficient evidence to base a conclusion that these
conditions had existed on February 27, the date of the original
citation. Indeed, Thompson indicated that he did not check the
stoppings on that date. Also, according to Hager, smoke readings
that he took at one of these stoppings on February 20, 26, 27,
29, and 3 dates subsequent to March 4, indicated the air to be
travelling into the bleeder entry. Moreover, although the

planned longwall roof fall that had occurred on February 24,
1992, did blow out some stoppings, there is no evidence that the
roof fall affected any of the stoppings between the bleeder and
track entries.

 Thompson indicated that he had observed an area of bad roof

and indicated that if it should fall, it could crush ventilation
controls. However, an examination of the mine map, Joint Exhibit
No. 1, indicates, as explained by Alexander, that should the roof
fall in the area indicated by Thompson and ruin stoppings, then
air would flow to the return entries, and not to the track entry.

 Although Thompson indicated that even with various

precautions something can happen to release gas at the gas well
that is present in the solid pilar to be mined, the specific
safety precautions to be taken, Operator's Exhibit No. 3, appear
to mitigate against the degree of this hazard.

 Further, the presence of a low level of incombustible

elements, the energized power center, and the presence of coal
dust and saturated oil on the mine floor do not increase the
likelihood of an explosion, in the absence of a reasonable
likelihood of gas from the gob reaching the area in which the
trolley track was located.

 Thompson observed that 11 rail bonds, used to prevent the

trolley tracks from arcing, were missing, and that the balance
were struck on rather than welded. This condition extended over
five crosscuts. However, it is significant to note, as indicated
by Hager, that this area was 200 to 800 feet from the area in
question.

 Accordingly, for all the above reasons, I conclude that the

violation herein was not significant and substantial.

ORDER

 It is ORDERED that Citation No. 3754287 be amended to

indicate that the violation alleged therein is not significant
and substantial. It is further ordered that the Notice of
Contest be DISMISSED.(Footnote 3)

                            Avram Weisberger
                            Administrative Law Judge

Distribution:

David J. Hardy, Esq., Jackson & Kelly, P.O. Box 553, Charleston,
WV 25322 (Certified Mail)

Pamela Silverman, Esq., Office of the Solicitor, U. S. Department
of Labor, 4015 Wilson Boulevard, Room 516, Arlington, VA 22203
(Certified Mail)

nb


3Counsel have each presented argument as to the level, if any, of
the Operator's negligence. I decline to reach any decision on
this issue. I find that a finding on the issue of negligence is
only necessary in deciding the amount of a civil penalty pursuant
to Section 110(i) of the act. Hence, a decision on the issue of
negligence at this stage of the proceedings would not be in
harmony with the statutory scheme for enforcement of violations
set forth in the Act, which provides for the Secretary to
initially propose a penalty (See, Section 105(c) and 110 of the
Act).