Secretary of Labor (MSHA) v. Consolidation Coal Company (ALJ decision, August 22, 1983)

Secretary of Labor (MSHA) v. Consolidation Coal Company (FMSHRC WEVA 83-32): Inquiry ordered on penalty-petition withdrawal

Decision type
ALJ decision
Docket
WEVA 83-32
Decided
August 22, 1983
Presiding judge
Outcome
Procedural
Precedential status
Interlocutory order, not final
Checked against source
2026-10-21
Cited standards

Apply this to your situation

This order from 1983 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1983
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Interim ALJ order, not Commission precedent
This order required the Secretary to clarify whether a roof control violation existed when the citation was issued. It did not decide the citation or become a final decision under the 40-day rule in 30 U.S.C. § 823(d)(1). It is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Transcribed from a scanned original: FMSHRC released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (fmshrc.gov)

Plain-English summary

MSHA cited Consolidation Coal Company for failing to install center roof bolts within the time required by its approved roof control plan. The Secretary asked to withdraw the penalty petition but also reported that the operator had paid a $20 assessment. Judge Paul Merlin observed that, according to the Secretary's account, the condition had been corrected before the citation issued. He directed the Secretary to determine whether a violation still existed at that time and, if none did, to free the operator from liability. He required a response within 30 days and did not resolve the citation in this order.

Decision snapshot

  • Cited standard: 30 C.F.R. § 75.200, compliance with an approved roof control plan.
  • Outcome: Secretary ordered to clarify the citation's basis and payment within 30 days; no final ruling on liability.
  • Key point: The judge asked whether the citation should have issued when the Secretary sought to withdraw the penalty petition but left the operator's payment in place.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR
WASHINGTON, D.C. 20006

August 22, 1983

SECRETARY OF LABOR, : CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH :
ADMINISTRATION (MSHA), : Docket No. WEVA 83-32
Petitioner : A.C. No. 46-01436-03509
v. :
: Shoemaker Mine
CONSOLIDATION COAL COMPANY, :
Respondent :

ORDER TO SOLICITOR TO SUBMIT INFORMATION The Solicitor has filed a motion to withdraw his Petition for the Assessment of Civil Penalty in this case.
The subject citation was issued on May 7, 1982, for a violation of 30 C.F.R. § 75.200 because center bolting was not completed within 24 hours as required by the approved roof control plan. According to the Solicitor the inspector determined that center bolts had not been installed at the cited location for a period of 34 hours.
However, the Solicitor further states that "The con- dition had been abated even before issuance of the citation." The Solicitor then states that the operator has paid the penalty assessment of $20.
If as the Solicitor states, the condition was corrected before the citation was issued then no violation existed at the critical time. Republic Steel Corp., 5 FMSHRC 1158 (June 1983). Under such circumstances the citation should not have been issued and no penalty should have been assessed. It is inconsistent for the Solicitor to seek to withdraw his penalty petition and at the same time allow the operator to pay a $20 penalty.
Accordingly, the Solicitor should review this matter and determine whether or not a violation actually existed at the time the citation was issued and if it did not, then to free the operator of liability. In light of the foregoing, it is Ordered that the Solicitor advise me with respect to the foregoing within 30 days of the date of this order.

Paul Merlin
~~Chief~~ Administrative Law Judge
Distribution:
Howard K. Agran, Esq., Office of the Solicitor, U. S. Department of Labor, Rm. 14480-Gateway Building, 3535 Market Street, Philadelphia, PA 19104 (Certified Mail) Robert M. Vukas, Esq., Consolidation Coal Company, 1800 Washington Road, Pittsburgh, PA 15241 (Certified Mail)

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace