Westmoreland Coal Company v. Secretary of Labor (MSHA) (ALJ decision, June 15, 1983)
Westmoreland Coal Company v. MSHA (FMSHRC WEVA 83-140-R): Order contest dismissed as late
Apply this to your situation
This order from 1983 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.
Plain-English summary
Westmoreland Coal challenged Order No. 2140708 concerning its Hampton No. 3 Mine. The company received the order on February 18, 1983, but mailed its contest on March 31, 41 days later. Mine Act § 105(d) required a contest within 30 days of receiving the order. Chief Judge Paul Merlin granted the Secretary's motion and dismissed the contest as untimely. The order does not decide the merits of the mine order or assess a penalty.
Decision snapshot
- Governing provisions: Mine Act § 105(d), 30 U.S.C. § 815(d); 29 C.F.R. § 2700.20, contest deadline.
- Outcome: Notice of contest dismissed as untimely; no penalty assessed.
- Key point: The contest was mailed 41 days after receipt, beyond the 30-day deadline.
Full text (FMSHRC public release)
CCASE:
WESTMORELAND COAL V. SOL (MSHA)
DDATE:
19830615
TTEXT:
~1144
Federal Mine Safety and Health Review Commission Office of Administrative Law Judges
WESTMORELAND COAL COMPANY,
NOTICE OF CONTEST
CONTESTANT
Docket No. WEVA 83-140-R v.
Order No. 2140708
SECRETARY OF LABOR,
2/18/83
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA),
Hampton No. 3 Mine
RESPONDENT
ORDER OF DISMISSAL
On April 4, 1983, Westmoreland Coal Company filed a Notice of Contest of the above-captioned order. On April 13, 1983, the Solicitor filed a motion to dismiss the notice of contest for untimely filing.
The Solicitor's motion explained that the order was received by the operator on February 18, 1983. The Solicitor cited section 105(d) of the Act which provides that a notice of contest to an order be filed within 30 days of its receipt. Based thereon the Solicitor argued that since the order was not contested until March 31, 1983 (FOOTNOTE 1), it was not filed within the requisite 30-day period.
The Solicitor's motion to dismiss must be granted. Section 105(d) of the Act is clear in directing that an operator contest issuance of an order within 30 days from the order's receipt. 29 C.F.R. 2700.20. Island Creek Coal Company, 1 FMSHRC 989 (August 3, 1979) affirming PIKE 79-18 (January 30, 1979) reported at 1 MSHC 2143-2144. In this case, the operator waited 41 days before mailing the notice of contest.
In light of the foregoing, this case is DISMISSED.
Paul Merlin
Chief Administrative Law Judge
FOOTNOTE START HERE-
1 The notice of contest was mailed to the Commission and the Solicitor by certified mail on March 31, 1983 and received by the Commission on April 4, 1983.
What applies to your situation today?
This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.