Kenneth A. Wiggins v. Eastern Associated Coal Corporation (Commission decision, October 6, 1983)

Kenneth A. Wiggins v. Eastern Associated Coal Corporation (FMSHRC WEVA 82-300-D): Review petition dismissed as premature

Decision type
Commission decision
Docket
WEVA 82-300-D
Decided
October 6, 1983
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-10-21

Apply this precedent to your situation

This is citable Commission precedent from 1983, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1983
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
The Commission dismissed a petition for review because the judge had not yet issued an order finally disposing of the case. This procedural order left the discrimination case before the judge and did not decide its merits or relief. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Kenneth Wiggins brought a mine safety discrimination case against Eastern Associated Coal Corporation. An administrative law judge found that Eastern had unlawfully discharged him but left the remedy for a later order. Eastern petitioned the Commission to review that merits ruling. The Commission dismissed the petition as premature because the judge had not yet granted relief and therefore had not finally disposed of the case. The parties could seek review after a final order from the judge; the Commission also denied interlocutory review to the extent Eastern had requested it.

Decision snapshot

  • Governing authorities: 30 U.S.C. §§ 815(c) and 823(d)(1); 29 C.F.R. § 2700.65(a).
  • Outcome: Petition for review dismissed as premature; case remained before the judge.
  • Key point: A merits ruling that leaves relief unresolved does not start the statutory period for Commission review.

Full text (FMSHRC public release)

CCASE:
KENNETH WIGGINS V. EASTERN ASSOC. COAL
DDATE:
19831006
TTEXT:

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION WASHINGTON, DC
October 6, 1983

KENNETH A. WIGGINS

v. Docket No. WEVA 82-300-D

EASTERN ASSOCIATED COAL CORP.

ORDER

This discrimination case arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. 801 et seq. (1976 & Supp. V 1981). On September 6, 1983, the administrative law judge issued a "Decision on the Merits" in which he held that Eastern Associated Coal Corp. had discharged Kenneth A. Wiggins in violation of section 105(c) of the Mine Act. 30 U.S.C. 815(c). The judge did not, however, award the miner relief. Instead, "Pending a Final Order" in this case, the judge allowed the miner 15 days from the date of his decision on the merits to submit a proposed order granting relief. The judge further allowed the operator 15 days from receipt of the miner's proposed order in which to reply. On October 3, 1983, Eastern Associated filed a petition for review of the judge's September 6, 1983 decision on the merits. 1/

Section 113(d)(1) of the Mine Act (30 U.S.C. 823(d)(1)) and Commission Rule 65(a) (29 C.F.R. 2700.65(a)) require that the decision of the judge contain an order that finally disposes of the proceedings. Because the judge has not as yet issued an order granting the miner appropriate relief he has not finally disposed of the case. Thus, the issuance of his decision on the merits did not initiate the running of the statutory review period. Jurisdiction in the case remains with the judge. Campbell v. The Anaconda Co., 3 FMSHRC 2763 (December 1981); McCoy v. Crescent Coal Co., 3 FMSHRC 2475 (November 1981).
____
1/ The petition was styled, "Respondent's Petition for Interlocutory Review or in the Alternative for Discretionary Review." We read the petition as one for discretionary review. To the extent that it is intended as a petition for interlocutory review, it is denied.
~1669
Accordingly, the petition for review is dismissed as premature. The parties may file petitions for discretionary review in accordance with section 113 of the Mine Act and Commission Rule 70 (29 C.F.R. 2700.70) once the judge has issued an order finally disposing of thi proceeding.
~1670
Distribution

Larry W. Blalock, Esq.
Jackson, Kelly, Holt & O'Farrell
P.0. Box 553
Charleston, West Virginia 25322

William B. Talty
Talty and Carroll
112 Central Avenue
P.0. Box 104
Tazewell, Virginia 24651

Administrative Law Judge Charles C. Moore
Federal Mine Safety & Health Review Commission 5203 Leesburg Pike, lOth Floor Falls Church, Virginia 22041

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace