FMSHRC Commission decision Docket WEVA 2013-422, WEVA 2012-918, WEVA 2012-919 Decided January 14, 2013 Remanded

Secretary of Labor v. Argus Energy WV, LLC

Secretary of Labor v. Argus Energy WV, LLC (FMSHRC WEVA 2013-422, WEVA 2012-918, WEVA 2012-919): Three final assessments reopened

Apply this precedent to your situation

This is citable Commission precedent from 2013, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2013
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the Commission's own document.
Read the official release (fmshrc.gov)

Plain-English summary

Argus Energy asked the Commission to reopen three MSHA penalty assessments that had become final after they were not timely contested. The corrected published order does not state why the deadlines were missed. The Secretary did not oppose any of the requests. The Commission reopened all three matters in the interests of justice, remanded them for penalty proceedings, and directed the Secretary to file penalty petitions within 45 days.

Decision snapshot

  • Governing provisions: 30 U.S.C. § 815(a); 29 C.F.R. § 2700.28
  • Outcome: Three final assessments were reopened and remanded for penalty proceedings.
  • Key point: The Commission granted unopposed reopening, although the corrected order does not describe the operator's reason for missing the contest deadlines.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVENUE, NW, SUITE 520N

WASHINGTON, D.C. 20004-1710

January 14, 2013

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

ARGUS ENERGY WV, LLC

:

:

:

:

:

:

:

Docket No. WEVA 2013-422

A.C. No. 46-08994-273633

Docket No. WEVA 2012-918
A.C. No. 46-08704-279357

Docket No. WEVA 2012-919
A.C. No. 46-08994-279358

BEFORE: Jordan, Chairman; Young and Nakamura, Commissioners

CORRECTED ORDER

BY THE COMMISSION:

These matters arise under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On March 8 and 30, 2012, the Commission received from
Argus Energy WV, LLC (“Argus”) three motions seeking to reopen three penalty assessments
that had become final orders of the Commission pursuant to section 105(a) of the Mine Act,
30 U.S.C. § 815(a).

The Secretary does not oppose the requests to reopen.

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed
penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed
penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment
is deemed a final order of the Commission. 30 U.S.C. § 815(a).

We have held, however, that in appropriate circumstances, we possess jurisdiction to
reopen uncontested assessments that have become final Commission orders under section 105(a).
Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to
reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the
Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief
from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect.
See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable
by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed
that default is a harsh remedy and that, if the defaulting party can make a showing of good cause
for a failure to timely respond, the case may be reopened and appropriate proceedings on the
merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Having reviewed Argus’ requests and the Secretary’s responses, in the interests of justice,
we hereby reopen these matters and remand them to the Chief Administrative Law Judge for
further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R.
Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment
of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.

/s/ Mary Lu Jordan

Mary Lu Jordan, Commissioner

/s/ Michael G. Young

Michael G. Young, Commissioner

/s/ Patrick K. Nakamura

Patrick K. Nakamura, Commissioner

Distribution:

R. Jill Bruner, Esq.

Argus Energy WV, LLC

2408 Sir Barton Way, Suite 375

Lexington, KY 40509

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

1331 Pennsylvania Avenue, N. W., Suite 520N

Washington, D.C. 20004-1710