FMSHRC ALJ decision Docket WEVA 2012-498-R, WEVA 2012-499-R, WEVA 2012-500-R, WEVA 2012-501-R, WEVA 2012-502-R, WEVA 2012-503-R, WEVA 2012-540, WEVA 2012-541 Decided November 9, 2012 Mixed result Judge Margaret A. Miller

David Stanley Consultants, LLC

David Stanley Consultants, LLC (FMSHRC WEVA 2012-498-R): Four citations vacated and two training citations left for further proceedings

Apply this to your situation

This order from 2012 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current MSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 2012
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the Commission's own document.
Read the official release (fmshrc.gov)

Plain-English summary

After the Upper Big Branch explosion, MSHA cited David Stanley Consultants, a staffing contractor whose employees worked underground at the mine, for training and examination violations. Judge Margaret A. Miller held that the company was an independent contractor subject to the Mine Act because it provided services at the mine. She found that it had no day-to-day control over miners after they entered the mine, so she vacated four citations involving task training, examinations, and correction of hazards. Two citations involving experienced-miner and supervisory first-aid training remained because the company administered or coordinated mine-safety training, with gravity, negligence, and penalty issues left for later proceedings.

Decision snapshot

  • Cited standards: 30 C.F.R. §§ 48.6, 48.7, 75.360, 75.363(a), and 75.1713-3
  • Outcome: Four citations were vacated, while two non-task-specific training citations remained for further proceedings.
  • Key point: An independent contractor's Mine Act liability depends on supervision or control over the specific activity, not merely on employing the workers involved.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
th
721 19 Street, Suite 443
Denver, CO 80202-2500
303-844-3577/ FAX 303-844-5268

                                  November 9, 2012

DAVID STANLEY CONSULTANTS, LLC, : CONTEST PROCEEDINGS
Contestant, :
: Docket No. WEVA 2012-498-R
: Citation No. 4900439, 12/06/2011
:
: Docket No. WEVA 2012-499-R
: Citation No. 4900440, 12/06/2011
:
: Docket No. WEVA 2012-500-R
v. : Citation No. 4900589, 12/06/2011
:
: Docket No. WEVA 2012-501-R
: Citation No. 4900604, 12/06/2011
:
: Docket No. WEVA 2012-502-R
: Citation No. 4900615, 12/06/2011
:
: Docket No. WEVA 2012-503-R
SECRETARY OF LABOR : Citation No. 8431839, 12/06/2011
MINE SAFETY AND HEALTH :
ADMINISTRATION, (MSHA), : Upper Big Branch Mine – South
Respondent, : Mine ID 46-08436 YBV
:
SECRETARY OF LABOR, : CIVIL PENALTY PROCEEDINGS
MINE SAFETY AND HEALTH :
ADMINISTRATION, (MSHA), : Docket No. WEVA 2012-540
Petitioner, : A.C. No. 46-08436-274683-01 YBV
:
v. : Docket No. WEVA 2012-541
: A.C. No. 46-08436-274683-02 YBV
DAVID STANLEY CONSULTANTS, LLC, :
Respondent. : Upper Big Branch Mine – South

 ORDER GRANTING IN PART AND DENYING IN PART DAVID STANLEY
      CONSULTANTS’ MOTION FOR SUMMARY DECISION &
ORDER GRANTING IN PART AND DENYING IN PART THE SECRETARY’S
          MOTION FOR PARTIAL SUMMARY DECISION

   These cases are before me upon notices of contest filed by David Stanley Consultants

(“DSC”) and petitions for assessment of civil penalty filed by the Secretary of Labor, acting
through the Mine Safety and Health Administration (“MSHA”), pursuant to section 105(d) of the

Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (the “Mine Act” or the
“Act”). The cases involve five 104(a) citations and one 104(d)(1) citation issued to DSC on
December 6, 2011.

                                   I. BACKGROUND

    On April 5, 2010 an explosion occurred at Performance Coal Company’s

(“Performance”) Upper Big Branch Mine-South (“UBB” or the “mine”). Eleven DSC
employees worked at the mine prior to and at the time of the explosion. Following an extensive
investigation, MSHA issued the six citations that are the subject of the above captioned dockets1
to DSC. Three citations were issued for various training violations, while three other citations
were issued for failure to correct hazardous conditions observed and recorded by one of the DSC
employees during the course of examinations he conducted. The parties determined that the
primary issue in these cases is one of jurisdiction and that the matter could be decided on cross
motions for summary decision. Specifically, the parties dispute whether DSC is an “independent
contractor” subject to liability under the Mine Act.

   On July 6, 2012 DSC submitted its Motion for Summary Decision (“DSC Mot.”), while

the Secretary submitted her Motion for Partial Summary Decision (“Sec’y Mot.”).
Subsequently, on July 27, 2012, DSC filed its Opposition to the Secretary’s Motion (“DSC
Opp.”), while the Secretary submitted her Reply to DSC’s Motion (“Sec’y Rep.”).

  1
     Citation No. 4900615 alleges a violation of Section 75.363(a) of the Secretary’s

regulations, and contends that a DSC employee working at the mine “failed to immediately
correct or post with conspicuous ‘Danger’ signs hazardous conditions observed and recorded
during the examinations[.]” Citation No. 8431839 alleges a violation of Section 75.360 of the
Secretary’s regulations, and contends that a DSC employee working at the mine “failed to
conduct adequate preshift examinations[.]” Citation No. 4900604 alleges a violation of Section
75.363(a) of the Secretary’s regulations, and contends that a DSC employee working at the mine
“failed to immediately correct hazardous conditions or post the area with conspicuous
‘DANGER’ signs for hazards observed and recorded during the examinations[.]” Citation No.
4900589 alleges a violation of Section 75.1713-3 of the Secretary’s regulations, and contends
that DSC “failed to develop, implement, and train select supervisory employees, to assure they
have received the required first-aid training, for all sections, on all shifts.” Citation No. 4900440
alleges a violation of Section 48.7 of the Secretary’s regulations, and contends that DSC, “which
provides contract employees to the Upper Big Branch Mine[,] failed to ensure their employees
received task training for the jobs they were performing.” Citation No. 4900439 alleges a
violation of Section 48.6 of the Secretary’s regulations, and contends that a DSC, “which
provides contract employees to the Upper Big Branch Mine, failed to ensure their employees
received experienced miner training.”

                          II. STIPULATIONS

The parties submitted the following joint stipulations:

  1. This proceeding is subject to the jurisdiction of the Federal Mine Safety
    and Health Review Commission and its designated Administrative Law
    Judges pursuant to Sections 105 and 113 of the Federal Mine Safety and
    Health Act of 1977 (“the Act”).
  2. The Upper Big Branch Mine-South (“UBB”) was operated by
    Performance Coal Company (“Performance”), a former subsidiary of
    Massey Energy Company.
  3. Performance was an “operator” as defined in Section 3(d) of the Act at the
    coal mine at which the order at issue in this proceeding was issued.
  4. The products of the mine at which Citations 4900615, 8431839, 4900439,
    4900440, 4900589 and 4900604 were issued entered commerce, or the
    operation or products thereof affected commerce, within the meaning and
    scope of Section 4 of the Act.
  5. DSC does business in several states and maintains its headquarters in
    Fairmont, West Virginia.
  6. DSC is in the business of providing temporary labor to the mining
    industry. Such laborers are DSC employees, in that they are hired by and
    paid by DSC, but mining activities performed by such employees is
    performed at the client mine to which, at the request of the client mine, the
    laborers have been assigned for a certain period of time (which can range
    from days to months, depending on the client mine’s need).
  7. DSC provides company training to its employees before placing them at
    mine sites. In general, this training includes expectations of employees
    (e.g., showing up on time, working safely, following instructions, accident
    reporting, etc.), general roof control and ventilation plan theory and the
    rights of miners to know the contents of the plans, accident prevention,
    and hazard recognition.
  8. DSC had an agreement with Performance to provide such temporary labor
    to UBB, before and on April 5, 2010.
  9. All of the temporary laborers employed by DSC and assigned to UBB
    were hourly employees. The DSC employees working at UBB before and
    on April 5, 2010 were David E. Farley, Blake J. Accord, John W. Morris,
    Owen Thomas Davis, William Campbell, Adam B. Farley, Justin L.
    Hatcher, Timothy G. Sigmon, James A. Smith, Joshua S. Napper and
    Jason M. Stanley.
  10. Most of the workers supplied to UBB by DSC were inexperienced miners.
    (i.e., most had fewer than 12 months mining experience).
  11. William Campbell worked as a David Stanley employee at UBB from
    December 7, 2009 until April 9, 2010. At the direction of Performance,
    Mr. Campbell worked for a time as a fire boss and examined belts at UBB.
  12. James Gump was the Director of Operations and Safety for DSC before
    and on April 5, 2010.

    1. DSC did not maintain an independent office or work area at UBB.
    2. DSC is responsible for reprimanding, and would reprimand, its employees,
      including those who were supplied to UBB, if, for example, DSC learned
      that they had acted in violation of DSC company policies, such as failing
      to report to work on time or being insubordinate.
    3. DSC has in the past submitted 7000-1 accident report forms regarding
      accidents involving its employees.
    4. The daily instruction of DSC employees working at UBB was provided by
      Performance supervisors.
    5. The penalties which have been assessed for Citations 4900615, 8431839,
      4900439, 4900440, 4900589 and 4900604 and pursuant to 30 U.S.C. 820
      will not affect the ability of DSC to remain in business.
    6. The individual or individuals whose signatures appear in Block 22 of
      Citations 4900615, 8431839, 4900439, 4900440, 4900589 and 4900604
      were acting in their official capacity and as an authorized representative
      for the Secretary of Labor when the citations were issued.
    7. True copies of Citations 4900615, 8431839, 4900439, 4900440, 4900589
      and 4900604, with any and all modifications and abatements, were served
      on DSC or its agent as required by the Act.
    8. The Citations contained in Exhibit A attached hereto are an authentic copy
      of Citations 4900615, 8431839, 4900439, 4900440, 4900589 and
      4900604, including any and all modifications or abatements.
    9. Citations 4900615, 8431839, 4900439, 4900440, 4900589 and 4900604,
      along with any and all modifications and abatements, may be admitted
      into evidence, without objection, although Respondent may dispute
      specific allegations contained within the citations.
             III. SUMMARY OF THE PARTIES’ ARGUMENTS
      

i. DSC’s Motion for Summary Decision

    DSC argues that there are no genuine issues of material fact and that it is entitled to

summary decision as a matter of law. DSC Mot. 2. Specifically, DSC argues that, “because [it]
did not operate the subject mine, . . . [the citations] were unlawfully issued to DSC and must
therefore be vacated. DSC Mot. 1-2.

    DSC avers that its primary business is “to provide temporary labor to the mining

industry[,]” and, as a provider of temporary labor, “DSC has no authority to supervise the work
done by the laborers, nor any involvement in making any of the work-related decisions at or
concerning a client mine-operator’s mine site.” DSC Mot. 2, 4. While DSC does offer services
in addition to temporary labor, such services or resources would only be provided “by
contractual agreement for that additional service or resource.” DSC Mot. 5.

   Prior to, and on April 5, 2010, DSC had an agreement with Performance for DSC to

provide temporary employees to Performance at the UBB mine. DSC Mot. 5. DSC did not

provide any other services or resources under the agreement, nor did DSC “have any presence,
actual or constructive, at UBB, or have the authority to or exercise any control over any portion
or the mine site or the work assignments of miners working at the mine, or training of those
miners, directly or indirectly.” DSC Mot. 5. “DSC was never hired by Performance to provide
training of any type to DSC employees assigned to work at UBB, or to any other miners working
at UBB.” DSC Mot. 6. Moreover, William Campbell, like the other miners assigned to UBB,
was a DSC employee assigned to work at UBB as an hourly miner and “DSC had no authority to
direct Mr. Campbell’s tasks or control or examine the workplace conditions in which he worked
at UBB.” DSC Mot. 5-6.

   DSC argues that it was not an “operator” as defined by the Mine Act. DSC Mot. 6. The

Mine Act’s definition of “operator” contemplates production-operators and independent
contractors “performing services or construction at such mine.” DSC Mot. 6-7. Performance was
the production-operator at UBB, as it was the “only entity with ‘substantial involvement . . . in
the mine’s engineering, financial, production, personnel, and health and safety matters.’” DSC
Mot. 7 (quoting Berwind Nat’l Resources Corp., 21 FMSHRC 1284, 1293 (Dec. 1999)). DSC
“had no involvement with UBB’s operations, other than to provide UBB with temporary mine
laborers whose work Performance controlled and supervised.” Further, DSC is not an
independent contractor as contemplated by the Act. DSC Mot. 7. DSC argues that it “does not
become an independent contractor ‘operator’ merely by virtue of a business relationship with a
mine.” DSC Mot. 8. DSC argues that the Secretary’s own policy, set forth in her Program
Policy Letter No. P-11-V-05, is that “temporary employment agencies are not Mine Act
independent contractors, and thus are not operators under the Mine Act.”2 DSC Mot. 8.

    DSC suggests that “the Commission routinely looks to OSHRC decisions for guidance in

analogous situations under the OSH Act.” DSC Mot. 10 n. 5. OSHRC has long recognized that a
temporary employment agency cannot be liable for violations committed by its employees at
OSHA regulated sites if the employment agency did not create or control the hazardous
conditions alleged.” DSC Mot. 10 (citing Manpower Temp. Services, Inc., 5 BNA OSCH 1803
(No. 76-9809, 1977)(ALJ) 1977 WL 6891 (Jan. 1977), aff’d Manpower Temp. Services, Inc., 5
BNA OSHC 1803 (No. 76-980, 1977), 1977 WL 7973 (June 1977)). Here, DSC “ha[d] no
authority to inspect, manage, enter, or oversee” the mine site where the subject citations were
issued. DSC Mot. 12. Further, “like the employee in Manpower that was assigned to a
supervisory position, the fact that Mr. Campbell in particular had his fire boss certification and
was, for a period of time, assigned by Performance to conduct examinations at UBB . . . does not
make him a supervisor or agent of DSC for purposes of imputing liability to DSC.” DSC Mot.
13
Finally, DSC argues that, even if it is found to be an independent contractor under the
Mine Act, it cannot be liable for conditions over which it has no control. DSC Mot. 15 (citing
Sec’y of Labor v. National Cement Co. of California, 573 F.3d 788, 795 (D.C. Cir. 2009),
Musser Engineering, Inc., 32 FMSHRC 1257, 1276 (Oct. 2010), Berwind Nat’l Resources Corp.,
21 FMSHRC 1284, 1293 (Dec. 1999), and Ames Construction, Inc. v. FMSHRC, No. 11-1303,

   2
      The 2011 PPL, which was in place at the time DSC was cited and the proposed

penalties were assessed, was simply a reissue of the 2009 PPL, i.e., PPL P09-V-02, which was in
place at the time of the explosion.

slip op. at 5 (D.C. Cir. April 17, 2012)). Specifically, DSC alleges that it “lacked control over
any aspect of UBB, including the work assignments, workplace conditions, and training of the
DSC employees assigned to work at the mine[.]” DSC Mot. 17.

ii. Secretary’s Reply to DSC’s Motion

    The Secretary responds by arguing that DSC is more than a “temporary employment

agency contractor” and its relationship with Performance included an agreement “for DSC to
build seals, which is traditional contractor work.” Sec’y Rep. 2, 4. DSC’s own website markets
the company as “very diverse” and capable of “all types of infrastructure work[.]” Sec’y Rep. 2.

   The Secretary argues that the OSHRC case law relied upon by DSC is not controlling,

while the Commission case law, which “DSC’s motion glosses over,” is clear on “how the court
should examine whether an entity is an independent contractor and an operator under the Mine
Act.” Sec’y Rep. 2-3.

    The Secretary disputes a number of the “undisputed facts” included in DSC’s Motion.

Namely, the Secretary “cannot agree that temporary manpower is the principle resource provided
by DSC.” Sec’y Rep. 3. Moreover, despite DSC’s contrary contention, DSC did exercise
control at the mine as evidenced by the DSC employees working at the mine, the presence of
DSC’s Director of Operations and Safety underground a half dozen times, and the presence of a
DSC agent fire boss and examiner who conducted and controlled examinations. Sec’y Rep. 3, 5.
Further, while DSC contends that the training it provided its employees was not intended to
satisfy the Part 48 requirements, and that it was not hired by Performance to conduct training of
any type, the Secretary argues that DSC did exercise control over training, and it is the
inadequacy of that training that forms the basis of the training violations issued here. Sec’y Rep.
4-5

iii. Secretary’s Motion for Partial Summary Decision

     The Secretary argues that there are no genuine issues of material fact and that she is

entitled to partial summary decision as a matter of law. She further states that the subject
citations were properly issued to DSC, who, as an independent contractor and operator under the
Act, is liable for the actions of its employees. Sec’y Mot. 1-3, 13-14.

     The Secretary argues that, on September 26, 2006 DSC entered into an agreement with

Performance to build seals at UBB. Sec’y Mot. 12. That agreement refers to DSC as an
independent contractor. Sec’y Mot. 12. That same agreement was amended on June 9, 2008 and
certain provisions were replaced, including provisions “pertaining to the Price Schedule,
payment, governing law, jury trial waiver and arbitration, and enforcement of judgment.” Sec’y
Mot. 12. “All other terms and conditions of the . . . [2006 agreement] remained unchanged and
in full force and effect. Sec’y Mot. 13. The Secretary asserts that eleven DSC employees
worked at UBB before and on the date of the deadly explosion, and that DSC’s Director of
Operations and Safety at the relevant times, James Gump, “traveled underground at UBB a half
dozen times.” Sec’y Mot. 13.

    The Secretary states that, consistent with Commission case law, the issue of whether an

independent contractor is a statutory operator under the Mine Act turns on (1) “whether the
independent contractor has a sufficiently proximate relationship to the extraction process and . . .
[(2)] the extent of the independent contractor’s presence at the mine.” Sec’y Mot. 14-15 (citing
Otis Elevator Co., 11 FMSHRC 1896 (Oct. 1989); Otis Elevator Co., 11 FMSHRC 1918 (Oct.
1989)). Moreover, she argues, the Act’s definition of operator “‘does not extend only to certain
‘independent contractor[s] performing services . . . at [a] mine; by its terms it extends to ‘any
independent contractor performing services . . . at [a] mine.” Sec’y Mot. 15 (citing Otis Elevator
Co. v. Sec’y of Labor, 921 F.2d 1285,1290 (D.C. Cir. 1990) (omissions and additions in
Secretary’s Motion).

    The Secretary argues that the line of Commission and Courts of Appeal cases on this

subject “suggest[] that section 3(d) covers any independent contractor performing more than de
minimis services at a mine, although no Court has specified what would constitute de minimis
services.” Sec’y Mot. 16. While the determination of whether one is independent contractor is
“not confined by the terms of [the parties’] contract[,] . . . the contracts are evidence of the
parties’ actual relationships.” Sec’y Mot. 16 (citing Bulk Transp. Servs., Inc., 13 FMSHRC 1354
(Sept. 1991)).

    The Secretary argues that DSC was “extensively involved” in the extraction process in

the form of “[f]irebossing, conducting examinations, correcting hazards, and training,” which
“are all essential to ensuring the safety of workers during the mining process, including the
extraction of coal.” Sec’y Mot. 17. Given that DSC was the employer of the eleven cited
individuals, it had the “authority and influence to play a substantial role in controlling” their
activities. Sec’y Mot. 18.

    The Secretary argues that the agreement and amendment between DSC and Performance,

while not dispositive, is evidence of DSC’s status as an independent contractor. Sec’y Mot. 18.
She points to the inclusion of language in the original agreement identifying DSC as a contractor,
as well as language indicating that DSC is responsible for the acts of its employees. Sec’y Mot.
18-19. Moreover, she cites specific language regarding the DSC’s responsibility to file all
necessary reports and documents required by law, as well as to provide all safety training to
DSC’s employees as required by law. Sec’y Mot. 19. Finally, she references language in the
agreement regarding DSC being “solely liable” for all “assessments, penalties, or other fines” for
violations of law by DSC or its employees. Sec’y Mot. 19.

    The Secretary also notes that DSC had an MSHA contractor ID and had been operating

as an independent contractor at mines under Mine Act jurisdiction since at least 2001. Sec’y
Mot. 19-21 n. 4. The Secretary argues that the work that DSC employees were conducting at
UBB “falls within the plain meaning of ‘services’ under the Mine Act.” Sec’y Mot. 20. The
dictionary defines “services” as “the performance of any duties or work for another; helpful or
professional activity: medical services.” Sec’y Mot. 20 (citing Dictionary.com). She argues that
the examinations and other tasks performed by DSC employees at UBB all constitute services.
Moreover, the 2006 agreement between DSC and Performance “explicitly describes DSC’s work
product as ‘services’ to be provided to Performance in fulfillment of the contract.” Sec’y Mot.
21.

    The Secretary, citing Joy Technologies, Inc., v. Sec’y of Labor, 99 F.3d 991, 997 (10th

Cir. 1996), argues that “independent contractor,” as contemplated in the Mine Act, is somewhat
different than “independent contractor” as understood by common law. Sec’y Mot. 22. Given
the ambiguity of the term, the court should defer to the Secretary’s interpretation that the
circumstances of this case “provide reasonable grounds for the Secretary’s judgment that DSC
was an independent contractor and, because it was providing services to UBB, an operator under
the Mine Act.” Sec’y Mot. 24.3 The Secretary argues that “DSC cannot contract to avoid duties
imposed upon it by the Mine Act” by claiming that “Performance, by exercising some degree of
concurrent control over DSC’s employees, was in some sense operating as a subcontractor to
DSC.” Sec’y Mot. 24

    The Secretary acknowledges that an independent contractor who exercises no control will

not be responsible for a violation. Sec’y Mot. 25-26 (citing Musser Engineering, 32 FMSHC
1257 (Oct. 2010), Joy Technologies, Inc., 17 FMSHRC 1303 (1995), aff’d, 99F.3d 991 (10th Cir.
1996), and Sec’y of Labor v. National Cement Co. of California, 573 F.3d 788 (D.C. Cir. 2009)).
However, unlike Musser where the Commission found that the independent contractor did not
exercise control, DSC did exercise control in the form of performing the contractual duties
underground at the mine. Sec’y. Mot. 26-27. Moreover, the DSC’s presence was further
demonstrated by DSC Director of Operations and Safety, James Gump’s being at the mine
approximately six times. Sec’y Mot. 27.

     The Secretary argues that it is well-settled that operators are liable for the actions of their

employees. Sec’y Mot. 27. Accordingly, DSC is liable for the violations of the eleven
employees it had assigned to UBB. Sec’y Mot. 27. This is true of both the lack of training
violations, as well as the actions of William Campbell, who was an agent of DSC. Sec’y Mot.

  1. The Secretary argues that Campbell, by virtue of his function as a mine examiner who
    conducted numerous examinations that were crucial to the mine’s operation and were performed
    while alone and functioning as a supervisor of his own activities, was an agent of DSC. Sec’y
    Mot. 28-30. In addition, the Secretary points to language in the 2006 Agreement that, among
    other things, addresses the conduct and control DSC exerted, DSC’s sole responsibility for the
    acts of its employees, and the fact that neither DSC, its agents, employees, etc. could be treated
    as agents of or employees of Performance. Sec’y Mot. 30-31. Nevertheless, the Secretary argues
    that she may cite the production operator, the independent contractor, of both for violations of
    the Mine Act committed by the independent contractor. Sec’y Mot. 32-33 (citing Speed Mining,
    Inc., v. FMSHRC, 528 F.3d 310, 314 (4th Cir. 2008)).
    Finally, the Secretary argues that her program policy letter, PPL P09-V-02, addressing
    

    temporary employment agency contracting in the context of Part 50 applies only to those
    reporting obligations under that part of her regulations. Sec’y Mot. 34. To apply the PPL
    outside of the context of Part 50 would be inconsistent with the purpose of the PPL. Sec’y Mot.
    34-35

    3
     The Secretary asks for Chevron deference on this issue, but states that “[e]ven if the
    

    court were not to afford Chevron deference to the Secretary, it should nonetheless apply Auer
    deference [.]” Sec’y Mot. 24

iv. DSC’s Opposition to the Secretary of Labor’s Motion

     DSC agrees that it entered into an Independent Contractor Agreement with Performance

in September of 2006 for DSC to construct mine seals at UBB. DSC Opp. 4. DSC further
agrees that, during the period of seal construction, it was an independent contractor and an
operator according to the Act. DSC Opp. 5. However, DSC argues that it last performed
services related to the building of seals at UBB in April of 2007, three years prior to the April
2010 explosion, and that said services were, and are, totally unrelated to the April 2010
explosion at UBB. DSC Opp. 2, 5, 7. While the 2006 Independent Contractor Agreement was
amended in 2008, the amendment was, “for all practical purposes, a new agreement – no longer
to build seals, but one to supply temporary labor.” DSC Opp. 5. Accordingly, the 2006 contract
is irrelevant to the current situation. DSC Opp. 6-8.

     Further, as pointed out by the Secretary, “the independent-contractor operator analysis is

not ‘confined’ by the terms of a contract.” DSC Opp. 8 (citing Sec’y Mot. 16-17). Rather, “the
key to determining whether the independent-contractor operator status attaches is the ‘actual
relationship[]’between the purported contractor and the production-operator[.]” DSC Opp. 8
(citing Bulk Transp. Servs., Inc., 13 FMSHRC 1354, 1358 n. 2 (Sept. 1991)(emphasis added)).
Accordingly, “the Commission must consider the relationship between DSC and Performance as
it existed at the time of the accident[.]” DSC Opp. 8. At the time of the explosion, and in the
years leading up to such, DSC’s only connection to UBB “was that certain DSC employees
worked at UBB.” DSC Opp. 2.

    DSC argues that the temporary labor provided to Performance does not qualify as a

“services” as is contemplated by the term “independent contractor” in the Act’s definition of
“operator.” DSC Opp. 9. There is no precedent for holding DSC liable as an independent
contractor, as “DSC merely provided manpower to perform services that were assigned, directed,
and controlled exclusively by Performance.” DSC Opp. 9. Further, unlike the present situation,
the cases relied upon by the Secretary “each involves work performed under the direction and
supervision of the contractor.” DSC Opp. 9.

    DSC further argues that the Secretary’s dismissal of her PPL denies the underlying

rationale of the PPL, which is that “work performed by miners from temporary employment
agencies is not ‘true contract work’ because the temporary employment agency does not
‘maintain[] supervisory control over its employees.’” DSC Opp. 11-12 (citing DSC Mot. Exs. 2
and 3). DSC also disputes the Secretary’s argument that her interpretation of “independent
contractor” is entitled to deference. DSC Opp. 15. DSC notes that the Secretary does not
address any ambiguities to which she may be entitled to deference in her interpretation. DSC
Opp. 15. Moreover, any deference to her stated position would be in contradiction to her
position in the PPL. DSC Opp. 15.

    DSC disputes the Secretary’s argument that William Campbell’s activities as a fire boss

make him an agent of DSC. DSC Opp. 16. Specifically, DSC argues that, consistent with basic
agency law, Performance alone had the legal obligation to examine the mine, and Performance
alone assigned Campbell to conduct such examinations. DSC Opp. 16, 17. Thus, Performance
alone is the only principal liable for Campbell’s actions as an examiner. DSC Opp. 17. Finally,

DSC argues that, even if it were found to be an independent contractor, it would “still not be
liable as an operator because the work performed by the miners assigned to Performance was
outside its ‘control and supervision.’” DSC Opp. 18

                                   IV. DISCUSSION

   Commission Procedural Rule 67 sets forth the grounds for granting summary decision as

follows:

           A motion for summary decision shall be granted only if the entire
           record, including the pleadings, depositions, answers to
           interrogatories, admissions, and affidavits, shows:
           (1) That there is no genuine issue as to any material fact; and
           (2) That the moving party is entitled to summary decision as a
           matter of law.

29 C.F.R. § 2700.67. The parties have agreed and I find that there are no genuine issues as to any
material fact and that this jurisdictional question can properly be decided based on the record
before me.

   Liability under the Mine Act is imposed upon “operators” of mines. See 30 U.S.C. § 814.

Section 3(d) of the Act defines “operator” as “any owner, lessee, or other person who operates,
controls, or supervises a coal or other mine or any independent contractor performing services or
construction at such mine.” (Emphasis added). In the case at hand, the Secretary seeks to
impose liability upon DSC under the “independent contractor” clause of Section 3(d).4

     While the Act does not define “independent contractor,” the Secretary’s regulations

define an “independent contractor” as an entity “that contracts to perform services or
construction at a mine.” 30 C.F.R. § 45.2(c). In Joy Technologies Inc., 17 FMSHRC 1303 (Aug.
1995) aff’d, 99 F.3d 991 (10th Cir. 1996), the Commission held that, in determining whether an
entity is an “independent contractor”, the “‘focus is on the actual relationship between the
parties, and is not confined to the terms of [the parties’] contracts. . . . [T]he determination of
whether a party is a properly designated to be within the scope of section 3(d) of Act is not based
on the existence of a contract, nor the terms of such a contract.’” (quoting Bulk Transportation
Services, Inc., 13 FMSHRC 1354 (Sept. 1991). Nevertheless, the contract between the parties
may be “evidence of the parties’ actual relationships.” Bulk Transp. Servs., Inc., 13 FMSHRC
1354, 1358 n. 2 (Sept. 1991).

   4
      The Secretary argues that deference should be afforded to her interpretation of

“independent contractor.” I agree with DSC that the Secretary’s deference argument is not
entirely clear. Nevertheless, I find that no ambiguity exists in the Act, the Secretary’s
regulations, or Commission case law and that this matter can properly be decided without
affording deference to any interpretation the Secretary has put forth.

    In 1989 the Commission addressed the issue of “operator” liability pursuant to the

“independent contractor” clause of Section 3(d) in two Otis Elevator Company decisions, Otis
Elevator Co., 11 FMSHRC 1896 (Oct. 1989) (hereinafter “Otis I”) and Otis Elevator Co., 11
FMSHRC 1918 (Oct. 1989) (hereinafter “Otis II”). In Otis I the Commission explained that
“Section 3(d) [of the 1977] Mine Act expanded the definition of ‘operator’ under . . .[the 1969
Coal Act] to include ‘any independent contractor performing services or construction at such
mine.’” 11 FMSHRC at 1900. “[T]he goal of Congress, in expanding the definition of
‘operator’ . . . to include ‘independent contractors,’ was to broaden the enforcement power of the
Secretary so as to reach not only owners and lessees but a wide range of independent contractors
as well.” Id. at 1900-1901. However, the Commission noted that, in analyzing an independent
contractor’s contacts with the mine, “not all independent contractors are operators under the
Mine Act, and that ‘there may be a point, at least, at which an independent contractor’s contact
with a mine is so infrequent or de minimis that it would be difficult to conclude that services
were being performed.’” Id. (quoting National Industrial Sand Ass’n, 601 F.2d 289, 701 (3rd Cir.
1979)).

    First, I find that DSC is an independent contractor performing services at the mine. In its

Otis decisions the Commission outlined a two pronged test for determining whether an entity is
an “operator” pursuant to the “independent contractor” clause of Section 3(d) of the Mine Act.
First, one must examine the subject entity’s “proximity to the extraction process” and second,
whether that entity’s work is “sufficiently related” to that process. Otis I, 11 FMSHRC 1896,
1902 (Oct. 1989). In Otis I the Commission determined that the independent contractor, an
elevator service contractor, satisfied this prong of the test because its employees “were working
in the center of mining activities while servicing equipment essential to the mining process, were
exposed to mining hazards, and had a direct effect on the safety of others because of their
exclusive control over the safety of the mine elevators[.]” Id.

    The second prong of the Otis test requires an examination of “the extent of [the entity’s]

presence at the mine.” Otis I, 11 FMSHRC 1896, 1902 (Oct. 1989). In Lang Bros., Inc., 14
FMSHRC 413, 420 (Sept. 1991), the Commission stated that “[a]n independent contractor's
presence at a mine may appropriately be measured by the significance of its presence, as well as
by the duration or frequency of its presence.”

    The undisputed material facts establish that “DSC had an agreement with Performance to

provide . . . temporary labor to UBB, before and on April 5, 2010.” Jt. Stip. 8. That agreement
is memorialized in the June 2008 document entitled “Amendment No. 1 to Independent
Contractor Agreement.” Sec’y Mot. Ex. C (hereinafter the “2008 Amendment”). The language
of the 2008 Amendment states that “WHEREAS, Owner and Contactor entered into that certain
Independent Contractor Agreement dated September 26, 2006 . . . ; and WHEREAS Owner and
Contactor agree to amend the agreement as set forth below.” The September 26, 2006 agreement
referenced in the Amendment, Sec’y Mot. Ex. B (hereinafter the “2006 Agreement”), called for
DSC to build mine seals at UBB. DSC argues that the 2006 Agreement is irrelevant because
after completing the seals in 2007 DSC’s only involvement at the mine was the provision of
temporary labor. DSC Opp. 4-9. Instead of drafting a new contract, the parties simply amended,
albeit inartfully, the original contract. As the Commission stated in Bulk Transportation
Services, 13 FMSHRC 1354 (Sept. 1991), while the “focus [of this analysis] is on the actual

relationships between the parties, and is not confined by the terms of their contracts,” the
contract between the parties may be “evidence of the parties’ actual relationships.” I find that
the 2006 Agreement and 2008 Amendment provide some evidence of an ongoing contractual
relationship between the parties.

    While DSC asserts, and Secretary does not explicitly dispute, that DSC had not provided

seal building services since April of 2007, certain provisions of that agreement remained intact
up until April, 2010. Further, I note that, in spite of the alleged ceasing of any services under the
2006 Agreement, the parties clearly had an ongoing contractual relationship for the provision of
services.5 While seal building, as opposed to the provision of temporary labor, may be more
easily classified as a traditional contractor service, it does not take away from the fact that that
ongoing independent contractor relationship was initiated on September 26, 2006 and continued,
albeit modified, at least until April 5, 2010 and that relationship included the provision of
services by DSC.

     Tellingly, and as pointed out by the Secretary, while DSC may have stopped building

seals in April of 2007, there is no indication that the 2006 Agreement was at any point
terminated. The fact that DSC and Performance chose to amend the 2008 Agreement is clear
evidence of the acknowledgement that an independent contractor relationship continued to exist
between the parties. However, I agree with DSC that the nature of the relationship changed after
the completion of the seals in April, 2007. The scope of work included in the original contract
provided that DSC would supply labor and supervision necessary to build the mine seals at UBB
and that UBB would provide all tools and safety equipment for the workers. The agreement
between the parties was changed after the seals were installed and thereafter, DSC provided
temporary labor to UBB. This finding is supported by the affidavit filed by James Gump, the
Director of Operations and Safety for David Stanley Consultants, LLC. Gump asserts in his
supplemental declaration that the intent of the parties in entering into the amended contract was
to set forth a rate of pay for the various employees and to change the relationship of the parties to
that of DSC providing only temporary workers to the mine. DSC Opp. Ex. 1. There is no
“scope of work” included in the amendment but it does include a list, dated September 4, 2008
setting forth the agreed upon billing rate for each classification of employee. Sec’y Mot. Ex. C.
The amendment is simply unclear and, while I find that there was a contractual relationship
between DSC and Performance, I cannot find that various portions of the original contract
remained in effect after September, 2008. The terms of the amended agreement, specifically the
duties ascribed to DSC are not clear.

    In both his statement to MSHA and in his affidavit, Gump explains that DSC recruited

employees for many mines, including the various Massey mines. DSC Mot. Ex. 1; Sec’y Mot.
Ex. D. Gump does not explain the terms of the agreement, and he specifically does not address
whether DSC expected to indemnify Performance for penalties assessed as a result of the actions
of its employee, which was something that was addressed in the original 2006 Agreement with
Performance. However, Gump’s statements do indicate that the miners remained employees of
DSC and were not employees of UBB. Although somewhat contrary to his statement to MSHA,
Gump explained in his affidavit that DSC hires only individuals who have had new miner

   5
       See infra discussion of “services” below.

training. DSC Mot. Ex. 1. Applicants for employment must show all documents and
certifications as to their experience and positions. Gump further explained that while DSC
conducted an initial training, about one hour in duration, it covered items such as information on
“mining and miner responsibilities” as well as attendance at work, and an overview of mine
plans. DSC also covers hazard recognition and reporting accidents. The training took place at
the Massey Marfork training facility. DSC does not conduct training for any particular mine,
unless otherwise contracted to do so, and, according to Gump, did not conduct training for
miners sent to UBB. However, in his statement, Gump acknowledges that DSC employs at least
two trainers, and it does provide refresher training to miners who are being assigned to work at
UBB. The refresher training is a requirement of UBB. Sec’y Mot. Ex. D.pg 30. However,
Massey conducted most training for miners sent to its mines. DSC Mot. Ex. 1, p. 3; Sec’y Mot.
Ex. D, p. 13-14, 17-18.

    DSC primarily provides new hire miners to UBB at the request of Massey. The mine

provides all safety equipment for each worker, including a SCSR. Once the miner is placed with
UBB, they attend annual refresher training according to the mine’s schedule. Sec’y Mot. Ex. D,
p. 18. Additionally, once the individual is assigned to a mine, “all decisions regarding where and
when that individual must show up for work and what work tasks that individual must perform at
the mine, are made by the client mine operator.” DSC Mot. Ex. 1 ¶ 4. However, according to
Gump, DSC has a mine ID and does report any accidents in which employees sent by DSC are
involved. Sec’y Mot. Ex. D, p. 34. In reporting accidents, DSC uses both the mine ID and
DSC’s contractor ID in filling out the report. DSC gives each employee a handbook with DSC
policies and a safety handbook. Moreover, DSC disciplines the employees when necessary,
including for failure to timely show up for work and insubordination. DSC provides
verifications for miners to show that they are experienced using their time cards and is
responsible for providing the paychecks to the employees placed in a mine.

    A company whose only function is to hire the miner, send them to the mine, and process

the payroll may result in a different finding. However, DSC does more than simply hire, assign,
and pay workers. As described above, DSC disciplines employees even after placed in the mine,
trains certain miners, and reports accidents that include its employees. In addition, the trainers at
DSC use the Massey training facilities, attend certain trainings and visit the mine location on
occasion. Therefore, I find that the employees of DSC are intimately connected to the extraction
process. While DSC’s involvement in the actual work of its miners may be limited, it is
nevertheless sufficiently connected to the extraction process.

    In addition to the training and discipline of miners who are assigned to work

underground, the DSC employees are proximately involved in the extraction process for other
reasons. One such employee, William Campbell, was a fire boss and examined belts at UBB. Jt.
Stip. 11. That same miner was subject to reprimand, employment rules, and accident reporting by
DSC. Mr. Campbell, among other things, was tasked with the responsibility of examining the
belts. Moreover, while examining the belts, he was constantly exposed to mining hazards.
Accordingly, his activities as a DSC employee, even if they were at the direction of Performance,
were sufficiently proximate to the extraction process.

    As to the second prong of the Otis test, I find that DSC and its DSC’s employees had an

extensive presence at the mine. There is no dispute that the eleven individuals were “employed
by DSC” and were working at UBB. Jt. Stip. 11. Mr. Campbell had been working at the mine
for approximately four months at the time of the explosion. Jt. Stip. 11. The ten other DSC
employees were working at UBB “before and on April 5, 2010.” Jt. Stip. 9. In Joy Technologies
Inc., 17 FMSHRC 1303, 1308 (Aug. 1995) the Commission found that substantial evidence
supported the ALJ’s finding that an independent contractor spending six days at the mine over a
two and a half month period, along with an expectation that such contact would continue,
satisfied the second prong of the Otis test. See also Lang Bros., Inc., 14 FMSHRC 413 (Sept.
1991) (sufficient presence found when contractor was present seven to ten days on a non-
continuing basis) and Otis I, 11 FMSHRC 1896 (Oct. 1989) (sufficient presence found when
contractor was present six hours per month). I find that the extended presence of Mr. Campbell,
combined with the presence of the ten other DSC employees, amount to a sufficient and
significant presence at the mine. In addition, the use of the Massey training facility by DSC,
along with Gump’s visits to the mine demonstrate a continued presence at the mine.
Accordingly, I find that the Secretary has satisfied the second prong of the Otis test and that DSC
is an independent contractor.

    The Mine Act creates liability for operators who are independent contractors performing

services at the mine. DSC argues that it does not provide services and, therefore, is not an
independent contractor. I disagree. The Commission noted that, in analyzing an independent
contractor’s contacts with the mine, “not all independent contractors are operators under the
Mine Act, and that ‘there may be a point, at least, at which an independent contractor’s contact
with a mine is so infrequent or de minimis that it would be difficult to conclude that services
were being performed.’” Id. (quoting National Industrial Sand Ass’n, 601 F.2d 289, 701 (3rd Cir.
1979)). Neither the Act nor the Secretary’s regulations define “performing services.” “In the
absence of a statutory or regulatory definition of a term, the Commission applies the ordinary
meaning of that term.” Twentymile Coal Co., 30 FMSHRC 736, 750 (Aug. 2008). The
dictionary defines the singular form of “services” as “the work performed by one that serves.”
Webster's New Collegiate Dictionary 1051 (1979). The term “services” is broad. DSC supplied
employees, provided information to those employees, hired and placed those employees with the
mine, and could discipline those employees if needed. The actions of DSC in providing
employees and all that entails demonstrate that it did provide a service to UBB.

     Next, section 3(d) covers any independent contractor performing more than de minimis

services at a mine. As a result, I must determine whether the DSC contact was so infrequent or
de minimis that it would be difficult to conclude that services were being performed. Northern
Illinois Steel Supply Co. v. Secretary of Labor, 294 F.3d 844, 848-49 (7th Cir. 2002), Musser
Engineering, Inc., 32 FMSHRC 1257, 1276 (Oct. 2010). In Musser, the Commission
determined that the services provided by Musser were extensive in time and substantial in
content. Musser’s activities included “engineering support, mapping, and surveying services”
that were performed to meet the operational needs of the mine. Musser had no office at the
mine, but did provide employees who performed activities both at the mine and at the Musser
office. The activities provided by those employees were found to be adequate to determine that
Musser provided services to the mine. The Circuit Court of Appeals did find that services were
de minimis in Northern Illinois, Id. but characterized the contractor as a vendor who provided

supplies once or twice a week. DSC’s contact is far greater. Accordingly, the services provided
by DSC in this case were not de minimis.

    I note that much of DSC’s argument in this case is premised upon its claimed status as a

temporary employment agency and what it perceives as the law’s insulating treatment of such
entities with regard to the employment agency’s liability for the actions of its employees at their
respective placements. However, the supporting case law submitted by DSC in its motion, DSC
Mot. 10-15, is not controlling. It is well settled that the jurisdictional reach of the Mine Act is
broad. Based on the controlling Commission case law discussed above, to restrict the reach of
Mine Act jurisdiction in this instance would not serve to effectuate the goal of Congress when it
expanded the definition of “operator” to include a “wide range of independent contractors.” Otis
I, 11 FMSHRC at 1900-1901. 6

    With regard to DSC’s argument that the Secretary’s PPL formally sets forth a policy “that

temporary employment agencies are not Mine Act independent contractors, and thus are not
operators under the Mine Act[,]” the PPL states under the “purpose” heading that it is issued to
“clarify that miners obtained through a temporary employment agency contractor are “miners for
purposes of reporting under 30 C.F.R. Part 50.” It goes on to explain that when a temporary
employment agency provides miners, it is the mine operator who is responsible for reporting any
accident, injuries, illnesses, production and hours worked by these employees. It then discusses
the definition of “miner”. The PPL acknowledges that mines often hire employees through
employment agencies and the miners hired through an agency work alongside those hired
directly by the mine. The PPL explains that “when a temporary employment agency or other
contractor supplies miners to the operator, the mine operator supervises these miners.” Because
the mine supervises the miners, the mine must complete MSHA required reporting for those
miners. I cannot agree that the PPL has the meaning and intent that DSC asserts. Instead, it is a
clarification that the company who supervises a miner must report any accidents or injuries.
Accordingly, I reject DSC’s argument that the PPL sets forth a policy that temporary
employment agencies are not Mine Act independent contractors. In any event, UBB and DSC
chose not to follow the policy set forth in the PPL and it was DSC, not UBB, who reported
accidents at the mine in which DSC employees were involved.

     Having found that DSC is an independent contractor providing services, I must analyze

the issue of potential liability for the citations that were issued. In order to impute liability to a
contractor who performs services, that independent contractor must “exercise supervision or
control” over the area or persons who were cited. The Commission has recognized that, while
strict liability under the Act “‘means liability without fault[;] [i]t does not mean liability for
things that occur outside one's control or supervision.” Ames Const., Inc., 33 FMSHRC 1607,
1611 (quoting Sec'y of Labor v. National Cement Co. of Cal., Inc., 573 F.3d 788, 795 (D.C. Cir.
2009) (citation omitted)), aff’d, 676 F.3d 1109 (D.C. Cir. 2012), see also Joy Technologies Inc.,

   6
     On appeal, the D.C. Circuit explained how broad the “wide range of independent

contractors” is when it stated that “Section 3(d) does not extend only to certain “independent
contractor[s] performing services ... at [a] mine”; by its terms, it extends to “ any independent
contractor performing services ... at [a] mine.” 30 U.S.C. § 802(d) (emphasis added).” Otis
Elevator Co. v. FMSHRC, 921 F.2d 1285 (D.C. Cir. 1990) (aff’g Otis I and II)

17 FMSHRC 1303, 1309 (Aug. 1995) (Noting the limitations in holding an independent
contractor liable for matters over which it and its employees have no control) and Musser
Engineering, 32 FMSHRC 1257 (Oct. 2010). Recently in Musser, the Commission addressed
the issue of supervision and control and in doing so looked first to the specific violation and then
to whether Musser was in a position to prevent errors. Consequently, the Commission
determined that Musser’s role in preparing a map was insufficient to bring it within the
parameters of the specific standard involved in that case.

    In the instant matter, I find that, DSC did not exercise supervision over the day to day

instruction of the miners, did not assign work tasks, did not supervise the daily work and did not
maintain an independent office or work area at UBB. Jt. Stips. 13 and 16. The eleven DSC
employees were working underground at the mine and, once they entered the mine, they were
subject to the sole supervision and control of the mine operator, UBB. Jt. Stip. 16; DSC Mot.
Ex. 1, p. 1-2, 4-6. DSC had no authority to direct the work force or be in a position to
understand what tasks they were assigned daily. While the cited individuals, who were
performing their contractually obligated labor duties at the mine, were DSC employees, DSC had
no control over those miners or the tasks they were assigned to once they entered the mine.
Sec’y Mot. Ex. D, p. 32. Accordingly, DSC cannot be held liable for the actions of Mr.
Campbell and his alleged failure to conduct adequate examinations and correct hazards observed
during those examinations as alleged in Citation Nos. 4900615, 8431839, and 4900604.7 DSC
would have no way in which to observe Campbell’s actions or determine if he was adequately
performing his assigned tasks. Moreover, given that DSC had no knowledge of or control over
what tasks its miners were assigned by UBB personnel, it cannot be held liable for Citation No.
4900440 and its alleged failure to task train those miners. DSC had no means to alter the work
tasks or assignments, had no way of preventing any action, and had no manner in which to
correct or direct the work of the persons assigned at UBB. Like Musser, DSC was in no position
to prevent errors on the part of the workers. Nor was DSC in a position to know when task
training was needed or required.

     However, while I find that DSC had no control over the actions of the miners once they

entered the mine, there is evidence to establish that DSC had some control and supervision over
other non-task specific training that was cited in Citation Nos. 4900589 and 4900439. DSC
stipulated and Gump testified regarding the administration of training, including mining specific
safety training, as well as hazard recognition training, to the miners it assigned to UBB. Jt. Stip.
7; Sec’y Mot. Ex. D, p. 18, 20. Certainly, the administration of mine safety training, including
hazard recognition training, is evidence enough that DSC retained at least some control in the
context of the types of training discussed in Citation Nos. 4900589 and 4900439; supervisory
first-aid and experienced miner training. DSC claims that it had no authority to train its own
employees. DSC Mot. 5. However, this claim is in direct conflict with DSC management’s own
acknowledgement, Sec’y Mot. Ex. D p. 19-20, and the parties’ stipulation, Jt. Stip. 7, that DSC
did in fact provide training. Further, as mentioned above, DSC provides annual refresher
training to prospective employees at UBB, and, as explained by Gump in his sworn statement, he

   7
      The Secretary has argued that Campbell, as a face boss, was an agent of DSC, but I do

not find that argument persuasive for purposes of determining the supervision and control of
DSC.

used the Massey training facilities, has observed the training conducted by Massey, and must
understand the training that each employee has had prior to placement. Sec’y Mot. Ex. D p. 18-
22, 30. DSC, in its position as the employer of the miners, had some responsibility to assure that
they are adequately trained. I find that, given DSC’s closeness to Massey, both physically in the
training facility, and in working to place miners, DSC exercises control and supervision as to
training. While its control does not extend to task training, it does extend to the other training
areas cited by the Secretary.

    Accordingly, I find that DSC may properly be cited for the training violations alleged in

Citation Nos. 4900589 and 4900439. However, given its lack of control or supervision over the
miners once they enter the mine, DSC may not be cited for the alleged examination and task
specific training violations over which it had no control or supervision.

                                      V. ORDER

    DSC’s Motion for Summary Decision is GRANTED IN PART and DENIED IN

PART. The Secretary’s Motion for Partial Summary Decision is GRANTED IN PART and
DENIED IN PART. Citation Nos. 4900615, 8431839, 4900604, and 4900440 are VACATED.
The citations that remain have not addressed the issues related to the gravity, negligence and
other penalty criteria. Therefore, the parties are ORDERED to contact the court within fifteen
days to schedule a conference call to discuss how the case will proceed from this point.

                                                 /s/ Margaret A. Miller
                                                 Margaret A. Miller
                                                 Administrative Law Judge

Distribution:

Pollyanna E.F. Hampton, Office of the Solicitor, U.S. Dept. of Labor, 1100 Wilson Blvd., 22nd
Floor, Arlington, VA 22209-2247

Daniel W. Wolff, Crowell & Moring, LLP, 1001 Pennsylvania Avenue NW, Washington, DC
20004-2595

Get today's answer for your situation

You just read what one judge decided for one employer in 2012, and it binds only those parties. Ezel checks the current MSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.