Endurance Mining (Commission decision, February 4, 2009)
Endurance Mining (FMSHRC WEVA 2009-267): Good cause for late contest sent to the Chief ALJ
Apply this precedent to your situation
This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Endurance Mining asked the Commission to reopen a penalty assessment that had become a final order after the contest deadline passed. The Secretary did not oppose reopening. The Commission applied its Rule 60(b) framework but did not grant relief outright. It remanded for the Chief ALJ to decide whether Endurance had good cause for the late contest and whether the final order should be reopened.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The matter was remanded for a good-cause determination on reopening.
- Key point: Even without opposition from the Secretary, the operator still had to establish good cause for missing the contest deadline.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
February 4, 2009
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
ENDURANCE MINING
:
:
:
:
:
:
:
Docket No. WEVA 2009-267
A.C. No. 46-08549-157507
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On November 12, 2008, the Commission received from Endurance Mining (“Endurance”) a request to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
The Secretary states that she does not oppose the reopening of the proposed penalty assessment.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Endurance’s request and the Secretary’s response, in the interests of justice, we hereby remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Endurance’s failure to timely contest the penalty proposal and whether relief from the final order should be granted. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
Michael F. Duffy, Chairman
Mary Lu Jordan, Commissioner
Michael G. Young, Commissioner
Robert F. Cohen, Jr., Commissioner
Distribution:
Max L. Corley, III, Esq.
Dinsmore & Shohl, LLP
P. O. Box 11887
900 Lee Street, Suite 600
Charleston, WV 25339
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance
MSHA
U.S. Department of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209-2247
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace