Brody Mining, LLC (Commission decision, February 2, 2009)

Brody Mining, LLC (FMSHRC WEVA 2008-1861): Contest mix-up and delay required fact-finding

Decision type
Commission decision
Docket
WEVA 2008-1861
Decided
February 2, 2009
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2009
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Brody Mining intended to pay 11 penalties and contest four others from a 15-citation assessment. Its safety director and counsel each believed the other would complete the contest, leaving the four penalties to become final. The Secretary opposed reopening and questioned why Brody waited more than six months to seek relief after MSHA issued a final-order notice, which was returned undelivered. The Commission remanded for the Chief ALJ to determine whether good cause supported reopening and specifically directed the Judge to examine Brody's delay.

Decision snapshot

  • Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
  • Outcome: The matter was remanded for findings on good cause and the delay in seeking relief.
  • Key point: An internal misunderstanding about who would file a contest did not resolve the separate question of why the operator waited months to seek reopening.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

February 2, 2009

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

BRODY MINING, LLC

:

:

:

:

:

:

:

Docket No. WEVA 2008-1861
A.C. No. 46-09086-135505

BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On September 23, 2008, the Commission received from Brody Mining, LLC (“Brody”) a request by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a). 

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

On January 8, 2008, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000135505 to Brody proposing civil penalties for violations alleged in 15 citations. Brody states that on approximately January 24, 2008, its safety director mailed the proposed assessment and a check to MSHA to pay 11 of the 15 penalties. Of the 15 citations in the Proposed Assessment that was returned to MSHA, Citation Nos. 7280178, 7280180, 9967987, and 9967988 were checked for contest and blackened out. The operator submits that on the same date, the safety director also faxed copies of the Proposed Assessment and check to MSHA’s Civil Penalty Compliance Office and copied counsel on the fax. Counsel states that he mistakenly believed that the safety director was contesting the four citations, while the safety director believed that counsel would separately contest the citations. Brody states that MSHA has since marked Citation Nos. 7280178, 7280180, 9967987, and 9967988 as delinquent and the remaining citations in the case, to which payment was applied, as closed.

In response, the Secretary states that she opposes the request to reopen. The Secretary explains that on April 3, 2008, MSHA sent the operator a notice indicating that the assessment had become a final order on February 14, 2008. She submits that the notice, which was sent to the address listed on the operator’s legal identity form, was returned to MSHA as “undelivered.”

The Secretary contends that the operator fails to explain why, after MSHA had informed it that it had not contested the Proposed Assessment, it took over half a year to request reopening.

We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessment forms that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Having reviewed Brody’s request and the Secretary’s response, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Brody’s failure to timely contest the penalty proposal and whether relief from the final order should be granted. We ask the Judge, in considering the matter, to ascertain the reasons for the delay of the operator in seeking relief from the final order. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.


Michael F. Duffy, Chairman


Mary Lu Jordan, Commissioner


Michael G. Young, Commissioner


Robert F. Cohen, Jr., Commissioner

Distribution:

William K. Doran, Esq.

Ogletree, Deakins, Nash, Smoak & Stewart, P.C.

2400 N Street NW, 5th Floor

Washington, DC 20037

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Myra James, Chief

Office of Civil Penalty Compliance

MSHA

U.S. Department of Labor,

1100 Wilson Blvd., 25th Floor,

Arlington, VA 22209-2247

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace