BGS Construction, Inc.
BGS Construction, Inc. (FMSHRC WEVA 2002-41): Motion to dismiss denied after delayed penalty notice
Apply this to your situation
This order from 2002 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.
Plain-English summary
BGS Construction faced two citations involving the death of a miner at the Blacksville No. 2 mine. The Secretary mailed the proposed penalty notice about 14 months after the investigation ended, and BGS argued that the delay required dismissal. Judge T. Todd Hodgdon held that the Secretary gave an adequate staffing and workload explanation and that BGS had not shown actual prejudice from the delay. The judge denied the motion to dismiss and set prehearing steps for the case to proceed.
Decision snapshot
- Governing provisions: 30 U.S.C. §§ 815, 815(a), and 815(d); 29 C.F.R. §§ 2700.10(c), 2700.56, 2700.57, and 2700.58
- Outcome: The motion to dismiss was denied, and the case was set for further prehearing proceedings.
- Key point: A delayed penalty notice does not require dismissal when the Secretary explains the delay and the operator shows no actual prejudice.
Full text (FMSHRC public release)
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
OFFICE OF ADMINISTRATIVE LAW JUDGES
2 Skyline, Suite 1000
5203 Leesburg Pike
Falls Church, Virginia 22041
May 3, 2002
SECRETARY OF LABOR, : CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH :
ADMINISTRATION (MSHA), : Docket No. WEVA 2002-41
Petitioner : A.C. No. 46-01968-03505 ZAG
v. :
:
BGS CONSTRUCTION, INC., : Blacksville No. 2
Respondent, :
ORDER DENYING MOTION TO DISMISS
AND
PREHEARING ORDER
This case is before under section 105 of the Federal Mine Safety and Health Act of 1977,
30 U.S.C. § 815. The Respondent has moved to dismiss the case claiming that the Secretary did
not notify it of the proposed civil penalty within a reasonable time as required by section 105(a)
of the Act, 30 U.S.C. § 815(a). The Secretary opposes the motion. For the reasons set forth
below, the motion is denied.
The two citations at issue in this case, alleging violations involving the death of a miner,
were issued on September 15, 2000. The Mine Safety and Health Administration’s (MSHA)
investigation report was issued on November 9, 2000. The notice of the proposed assessment for
the citations was mailed to the company on January 17, 2002. Thus, 14 months and eight days
elapsed between the completion of the investigation and notification of the operator of the
proposed penalty.
Section 105(a) provides that: “If, after an inspection or investigation, the Secretary issues
a citation or order under section 104, he shall, within a reasonable time after the termination of
such inspection or investigation, notify the operator by certified mail of the civil penalty
proposed to be assessed under section 110(a) for the violation cited . . . .” With regard to
whether a civil penalty has been proposed within a “reasonable time,” the Commission has
furnished the following guidance:
Section 105(a) does not establish a limitations period
within which the Secretary must issue penalty proposals. See
Rhone-Poulenc of Wyoming Co., 15 FMSHRC 2089, 2092-93
(October 1993), aff’d 57 F.3d 982 (10th Cir. 1995); Salt Lake
County Rd. Dept., 3 FMSHRC 1714 (July 1981); and Medicine
Bow Coal Co., 4 FMSHRC 882 (May 1982). In commenting on
787
Page 2
the Secretary’s statutory responsibility to act “within a reasonable
time,” the key Senate Committee that drafted the bill enacted as the
Mine Act observed that “there may be circumstances, although
rare, when prompt proposal of a penalty may not be possible, and
the Committee does not expect that the failure to propose a penalty
with promptness shall vitiate any proposed penalty proceeding.” S.
Rep. No. 181, 95th Cong., 1st Sess. 34 (1977), reprinted in senate
Subcommittee on Labor, Committee on Human Resources, 95th
Cong., 2d Sess., Legislative History of the Federal Mine Safety and
Health Act of 1977, at 622 (1978). Accordingly, in cases of delay
in the Secretary’s notification of proposed penalties, we examine
the same factors that we consider in the closely related context of
the Secretary’s delay in filing his penalty proposal with the
Commission: the reason for the delay and whether the delay
prejudiced the operator.
Steel Branch Mining, 18 FMSHRC 6, 14 (January 1996).
The Secretary asserts that the reason for the delay in this case was that:
[T]he Office of Assessments had a large case load and was
understaffed during the relevant time period. During that period,
four persons were responsible for processing over 2,500 citations
and orders that were considered for special assessment. Two of
those individuals were not in the office for extended periods of
time.
(Sec. Resp. at 3.)
In Steel Branch, the Commission took official notice that the Secretary had an unusually
high case load in 1992 and accepted that as an adequate reason for the delay, even though the
“Secretary ha[d] not offered any explanation for his delay.” Id. Consequently, keeping in mind
Congress’ expectation that failure to propose a penalty with promptness will not vitiate any
proposed penalty proceeding, I find that the Secretary has provided an adequate explanation for
the delay.
Turning next to the issue of prejudice to the operator, the company asserts that its “Safety
Director, who was at the site and likely to testify on issues in the case, left the company in
December 2001 and all BGS work at the Blacksville plant has ceased. Further, trial of this case
would require witnesses to testify as to events almost two years old.” (Resp. Mot. at 6.) These
suppositions do not demonstrate actual prejudice. Although the Safety Director may have left the
company, there is no indication that he would not be available for deposition or trial. In addition,
788
Page 3
the fact that events are almost two years old is not an unusual occurrence in these cases and has
the same effect on both sides. Furthermore, since the company has been aware of the factual
allegations in this case since September 15, 2000, there is no reason that the Safety Director’s
testimony as well as the testimony of any other employees could not have been recorded to
refresh recollections before trial.
Accordingly, an adequate explanation having been provided for the delay by the Secretary
and the Respondent having failed to demonstrate actual prejudice, the Motion to Dismiss is
DENIED.
Prehearing Order
In accordance with the provisions of section 105(d) of the Act, 30 U.S.C. § 815(d), the
above proceeding will be called for hearing on the merits at a time and place to be designated in a
subsequent notice. Prior to setting the case for hearing, the parties are directed to confer for the
purpose of discussing settlement. If a settlement is reached, a motion for its approval shall be
filed by the Secretary of Labor no later than May 24, 2002.
If settlement is not agreed upon, counsel for the Secretary shall initiate a telephone
conference call with the Respondent's representative and the judge for the purpose of setting a
hearing date. The conference call may be made at any time convenient to the parties, but not
later than May 31, 2002.
Procedural motions filed in this case shall comply with Commission Rule 10(c), 29
C.F.R. § 2700.10(c), which requires that “the moving party shall confer or make reasonable
efforts to confer with the other parties and shall state in the motion if any other party opposes or
does not oppose the motion.”
Discovery requests made pursuant to Commission Rules 56, 57 and 58, 29 C.F.R. §§
2700.56, 2700.57 and 2700.58, responses to discovery requests and depositions should not be
filed with the judge.1 However, copies of such requests or responses shall accompany any
motion to compel or for other relief regarding discovery matters.
T. Todd Hodgdon
Administrative Law Judge
(703) 756-6213
1
Cover letters for discovery requests or responses may be filed with the judge if the party
desires to have a record of the request or response in the official file.
789
Page 4
Distribution: (Certified Mail)
Robert S. Wilson, Esq., Office of the Solicitor, U.S. Department of Labor, 1100 Wilson Blvd.,
22nd Floor West, Arlington, VA 22209
Mark E. Heath, Esq., Heenan, Althen & Roles, LLP, BB & T Square, P.O. Box 2549, Charleson,
WV 25329
yi
790
Get today's answer for your situation
You just read what one judge decided for one employer in 2002, and it binds only those parties. Ezel checks the current MSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.