Port Costa Materials, Inc. (Commission decision, September 1, 1994)
Port Costa Materials, Inc. (FMSHRC WEST 93-353-M): Citation discrepancy remanded for correction
Apply this precedent to your situation
This is citable Commission precedent from 1994, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Port Costa Materials faced 73 citations in a civil penalty proceeding under the Mine Act. The ALJ's decision discussed Citation No. 3636555 as affirmed in one part but listed it as vacated in the final disposition. The Commission treated the Secretary's letter requesting correction as a timely petition for discretionary review, granted review, and remanded the proceeding to the judge for further appropriate proceedings.
Decision snapshot
- Governing authority: 30 U.S.C. § 823(d)(2); 29 C.F.R. §§ 2700.69(b) and 2700.70(a)
- Outcome: The Commission granted review and remanded the proceeding to the ALJ to address the inconsistent disposition of Citation No. 3636555.
- Key point: An inconsistency in an ALJ decision's treatment of a citation can be addressed through a timely petition for discretionary review.
Full text (FMSHRC public release)
CCASE:
SOL (MSHA) V. PORT COSTA
DDATE:
19940901
TTEXT:
Page 2
~1929
SECRETARY OF LABOR,
:
MINE SAFETY AND HEALTH :
ADMINISTRATION (MSHA) :
:
v. : Docket No. WEST 93-353-M
:
PORT COSTA MATERIALS, INC. :
:
:
ORDER
BY THE COMMISSION:
This civil penalty proceeding arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. 801 et seq. (1988). On July 28, 1994, Administrative Law Judge John J. Morris issued a decision, in which he disposed of 73 citations issued against Port Costa Materials, Inc.
The Solicitor's Office of the Secretary of Labor, in a letter to the judge dated August 12, 1994, pointed out a discrepancy in the decision with regard to Citation No. 3636555. The letter stated that, on pages 45 and 46 of the judge's decision the citation was discussed and "affirmed," but that on page 66 of the decision, where the judge summarized the disposition of the citations in the proceeding, the citation was listed as "vacated." The letter requested that the "discrepancy ... be addressed/corrected." By letter dated August 15, 1994, the judge responded to the request by stating that he was limited by the Commission's Rules to correction of clerical errors and did not view the correction required as a "clerical error" within the meaning of the rules.
The judge's jurisdiction in this matter terminated when his Decision was issued on July 28, 1994. Commission Procedural Rule 69(b), 29 C.F.R. 2700.69(b) (1993). Under the Mine Act and the Commission's Procedural Rules, relief from a judge's decision may be sought by filing a petition for discretionary review within 30 days of its issuance. 30 U.S.C. 823(d)(2); 29 C.F.R. 2700.70 (a). We deem the Solicitor's August 12 letter to be a timely filed Petition for Discretionary Review, which we grant.
Page 3
~1930
See, e.g., Middle States Resources, Inc., 10 FMSHRC 1130 (September 1988).
In light of the apparent error in the judge's decision and the requested relief, we remand this proceeding to the judge for further appropriate proceedings.
Mary Lu Jordan, Chairman
Joyce A. Doyle, Commissioner
Arlene Holen, Commissioner
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Try Ezel Pro free for 7 days. Cancel anytime before the trial ends and you pay nothing.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace