Thomas Hale, employed by Damon Corp. (Commission decision, November 27, 1995)

Thomas Hale, employed by Damon Corp. (FMSHRC WEST 90-283-M): Relief from final order denied

Decision type
Commission decision
Docket
WEST 90-283-M
Decided
November 27, 1995
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-13

Apply this precedent to your situation

This is citable Commission precedent from 1995, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1995
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
The Commission denied relief from a final order because the request was filed more than four years after the ALJ's default order and beyond the one-year limit in Federal Rule of Civil Procedure 60(b). This is a final Commission decision. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Thomas Hale, a general manager at Damon's Valley Sand and Gravel Mine, asked the Commission to reopen a default order imposing $1,500 in penalties for five alleged violations of 30 C.F.R. § 56.14107(a). The Commission noted that a federal district court had already entered judgment for the United States to recover the penalty. It held that Hale's request, filed more than four years after the ALJ order became final, was outside the one-year limit for relief under Rule 60(b). The Commission denied the request.

Decision snapshot

  • Cited standard: 30 C.F.R. § 56.14107(a)
  • Outcome: Relief from the final order was denied.
  • Key point: A request to reopen a final Commission order under Rule 60(b) must be made within the rule's time limit.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR
WASHINGTON, D.C. 20006

November 27, 1995

SECRETARY OF LABOR,
:
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA)
:
:
v. : Docket No. WEST 90-283-M
:
THOMAS HALE,
:
employed by DAMON CORP.
:

BEFORE: Jordan, Chairman; Doyle, Holen and Marks, Commissioners

ORDER

BY THE COMMISSION:

This civil penalty proceeding arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. ' 801 et seq. (1988). On August 13, 1990, the Secretary of Labor filed a petition for assessment of civil penalty, pursuant to section 110(c) of the Mine Act, 30 U.S.C. ' 820(c), against Thomas Hale, general manager of the Valley Sand and Gravel Mine owned by Damon Corporation, alleging that he knowingly authorized, ordered, or carried out five violations of 30 C.F.R. ' 56.14107(a). On March 12, 1991, Chief Administrative Law Judge Paul Merlin issued an Order of Default to Hale for his failure to answer the Secretary=s penalty proposal or the judge=s Order to Show Cause dated October 30, 1990. The judge assessed civil penalties of $1,500.

On October 11, 1995, the Commission received a letter from Hale requesting that the case be reopened for hearing. In his letter, Hale acknowledges that the citations had been properly issued but asserts that he is not responsible for payment of the penalties because he had been told by the company=s controller that they would be paid. Letter at 1-2. Hale states that he was unaware that the penalties had not been paid until he was contacted in 1991 by a collection office. Id. at 3. Subsequently, he was contacted by the Department of Justice regarding the matter. Id. Hale asserts that he Abegan to know how to handle@ the situation only after contacting the local director of the Mine Safety and Health Administration in Vacaville, California, who suggested that he contact the Commission. Id. at 3-4.

On October 31, 1995, the Commission received the Secretary=s opposition to Hale=s


Page 2

request for relief. The Secretary informs the Commission that the United States filed an action pursuant to section 110(j) of the Mine Act, 30 U.S.C. ' 820(j), in the United States District Court for the Eastern District of California for recovery of the penalty owed by Hale, and that the District Court granted summary judgment in favor of the United States on April 12, 1994. Opp=n at 2-3. Hale filed a motion to set aside the summary judgment, which was denied, and final judgment was entered on May 9, 1995. Id. at 3. The Secretary asserts that the time limitations set forth in Fed. R. Civ. P. 60(b) preclude the Commission from considering the case. Id. at 9-12.

The judge=s jurisdiction over this case terminated when his default order was issued on March 12, 1991. 29 C.F.R. ' 2700.69(b). Relief from a judge=s decision may be sought by filing a petition for discretionary review within 30 days of its issuance. 30 U.S.C. ' 823(d)(2); 29 C.F.R. ' 2700.70(a). If the Commission does not direct review within 40 days of a decision=s issuance, it becomes a final decision of the Commission. 30 U.S.C. ' 823(d)(1). Hale=s letter was received by the Commission on October 11, 1995, more than four years after the judge=s default order had become a final decision of the Commission.

Relief from a final Commission judgment or order is available to a party under Fed. R.
Civ. P. 60(b)(1) in circumstances such as mistake, inadvertence, or excusable neglect. 29 C.F.R. ' 2700.1(b) (Federal Rules of Civil Procedure apply Aso far as practicable@ in the absence of applicable Commission rules); e.g., Lloyd Logging, Inc., 13 FMSHRC 781, 782 (May 1991). A motion requesting relief based on such reasons must be made Awithin a reasonable time, and . . . not more than one year after the judgment, order, or proceeding was entered or taken.@ Fed. R. Civ. P. 60(b).

2


Page 3

Hale=s request for relief was filed more than four years after the judge=s default order became a final decision of the Commission, well beyond the one-year time limit set forth in Rule 60(b) for filing such requests. See Ravenna Gravel, 14 FMSHRC 738, 739 (May 1992). Accordingly, the request for relief is denied.

Mary Lu Jordan, Chairman

Joyce A. Doyle, Commissioner

Arlene Holen, Commissioner

Marc Lincoln Marks, Commissioner

3


Page 4

TALLY SHEET

Hale, employed by Damon Corp., Docket No. WEST 90-283-M

Commissioner
Date

Deny the request for relief from final order (order to that effect attached).

Other:

Comments:

Please return to Lynne Bowman

4

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace