Secretary of Labor (MSHA) v. The Anaconda Company (ALJ decision, August 13, 1981)

The Anaconda Company (FMSHRC WEST 81-94-M): Penalty case dismissed after lengthy delay

Decision type
ALJ decision
Docket
WEST 81-94-M
Decided
August 13, 1981
Presiding judge
Outcome
Procedural
Precedential status
Final order, not precedent
Checked against source
2026-10-22

Apply this to your situation

This order from 1981 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1981
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision under the Mine Act's 40-day rule
This administrative law judge decision became a final decision of the Commission because no Commissioner directed review within 40 days, under 30 U.S.C. § 823(d)(1). It binds the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Transcribed from a scanned original: FMSHRC released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (fmshrc.gov)

Plain-English summary

The Anaconda Company sought dismissal of a mine safety penalty case because the Secretary of Labor waited nearly two years after issuing a citation to propose a penalty. The Secretary argued that the company still had enough evidence to obtain a reduced proposed penalty at a conference. The judge found that the delay was inherently prejudicial to the company's defense and that the Secretary gave no reason for it. He granted the motion and dismissed the case with prejudice. The order did not decide whether the cited mine condition violated a safety standard.

Decision snapshot

  • Cited standards: No mine safety standard is identified in the order; the judge discussed the penalty notice requirement in 30 U.S.C. § 815(a).
  • Outcome: Case dismissed with prejudice; no penalty assessed.
  • Key point: An unexplained delay of nearly two years in proposing a penalty justified dismissal where the judge found it prejudiced the operator's defense.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 333 W. COLFAX AVENUE, SUITE 400 DENVER, COLORADO 80204

AUG 13 1981

SECRETARY OF LABOR, MINE SAFETY AND ) CIVIL PENALTY PROCEEDING HEALTH ADMINISTRATION (MSHA), ) ) DOCKET NO. WEST 81-94-M
Petitioner, )
) MSHA CASE NO. 24-00689-05018
v. )
) MINE: Weed Concentrator
THE ANACONDA COMPANY,
)
)
Respondent. )
)

ORDER

Respondent has filed a motion to dismiss this case. As reason therefor, respondent states that it has been prejudiced by the delay of nearly two years between the time the citation in question was issued and the assessment of a penalty. The Secretary in opposition to the motion argues that the respondent was not prejudiced by the delay as shown by the fact that it had retained sufficient evidence to persuade the MSHA assessment officer to reduce the penalty at a conference held on November 3, 1980.

The Federal Mine Safety and Health Act requires the Secretary to notify the mine operator of a proposed penalty within a reasonable time after the issuance of a citation. The remarks of the Senate Committee clarify the purpose for this requirement.

To promote fairness to operators and miners
and encourage improved mine safety and health
generally, such penalty proposals must be for-
warded to the mine operator and mine representative promptly. The Committee notes, however, that there may be circumstances, although rare, when prompt proposal of a penalty may not be possible, and the Committee does not expect that the failure to propose a penalty with promptness shall vitiate any proposed penalty. S. Rep. No. 95-181, 95th Cong., 1st Sess. 34 (1977).

The Commission reasoned in a recent decision that the above expressed intent of Congress demonstrates their overriding concern with effective enforcement, and, thus a citation should be vacated only when to do so imple- ments the remedial purpose of the Act. The Commission also recognized the secondary purpose of protecting mine operators from stale claims. Sec. of Labor v. Salt Lake County Road Dept., Docket No. WEST 79-365-M (July 28, 1981).

1926

The Commission established a two prong test to determine if the late filing of the proposal for penalty addressed to the Commission is in substantial compliance with the Act and, therefore, should not result in the dismissal of the case. The Secretary must show that there was adequate cause for the delay. The mine operator must show that it has been prejudiced by the delay. These two requirements are to be balanced against each other with the scales weighing heavily on the side of enforcement. However, the objective of effective enforcement can be thwarted by the Secretary's inexcusable delay over a substantial period of time. The Commission warned the Secretary against any unwarranted dilatory action.

The above test is directly applicable here. Congress perceived that the prompt assessment of a penalty was necessary for effective enforcement. In the present case, the delay of nearly two years is on its face a blatant disregard of this objective. Contrary to the Secretary's statement in its response to the motion, Section 815(a) of the Act provides the statutory authority for the vacation of a citation where the Secretary has been so dilatory in assessing a penalty that effective enforcement of the Act is impossible.

In the present case the citation was issued on December 5, 1978. Due to the delay in the assessment of a penalty, this case was not ripe for the adjudication of the penalty until the filing of the proposal for penalty on February 5, 1981. The Secretary offers no reason for the delay. Such a lengthy delay is inherently prejudicial to the operators' preparation of a proper defense.

For the above stated reasons, the motion to dismiss is granted. This case is dismissed with prejudice.

John J. Morris
Administrative Law Judge

Distribution:

James H. Barkley, Esq., Office of the Solicitor United States Department of Labor 1585 Federal Building, 1961 Stout Street Denver, CO 80294

Karla M. Gray, Esq., The Anaconda Company
Post Office Box 689
Butte, Montana 59703

1927

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace