William A. Haro v. Magma Copper Company (Commission decision, September 1, 1982)

William A. Haro v. Magma Copper Company (FMSHRC WEST 80-482-DM): Late review petition dismissed

Decision type
Commission decision
Docket
WEST 80-482-DM
Decided
September 1, 1982
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-10-21

Apply this precedent to your situation

This is citable Commission precedent from 1982, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1982
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This order dismisses a petition for discretionary review as untimely and leaves the judge's decision in place. It is a final Commission order on the petition and may have been appealed to a U.S. Court of Appeals under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

William Haro sought Commission review of an administrative law judge's July 23, 1982 decision in his case against Magma Copper Company. The Mine Act allowed 30 days to file a petition, and Commission rules made filing effective when the petition was received. Haro's counsel mailed the petition on August 27; the Commission received it on August 30, 38 days after the judge's decision. The Commission dismissed the petition as untimely without reaching the merits of the judge's decision. No civil penalty was assessed in this order.

Decision snapshot

  • Governing provision: 30 U.S.C. § 823(d)(2)(A)(i), the 30-day period for a petition for discretionary review.
  • Outcome: Petition for discretionary review dismissed as untimely; no penalty assessed in this order.
  • Key point: A petition was filed when the Commission received it, not when counsel mailed it.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY & HEALTH REVIEW COMMISSION WASHINGTON, D.C. September 1, 1982 WILLIAM A. HARO

v. Docket No. WEST 80-482-DM

MAGMA COPPER COMPANY

ORDER
William A. Haro has petitioned for discretionary review of a decision of an administrative law judge issued on July 23, 1982. Magma Copper has filed a motion requesting that the petition be dismissed as untimely. For the reasons that follow, the petition is dismissed as untimely. The Federal Mine Safety and Health Act of 1977, 30 U.S.C.
$ 801 et seq., provides that "any person adversely affected or aggrieved by a decision of an administrative law judge, may file and serve a petition for discretionary review by the Commission of such decision within 30 days after the issuance of such decision." 30 U.S.C. $ 823 (d) (2)(A)(i) (emphasis added). Further, Rules 5(d) and 70(a) of the Commission's rules of procedure expressly provide that "filing of a petition for discretionary review is effective only upon receipt." 29 C.F.R. $$ 2700.5(d), 70(a). The administrative law judge's decision in this case was issued on July 23, 1982. The thirtieth day following the issuance of the judge's decision was August 22, 1982. Counsel did not mail the petition for discretionary review until August 27, 1982. It was not received, and therefore filed, at the Commission until August 30, 1982, the thirty-eighth
~1620
day after the issuance of the judge's decision. Accordingly, under the statute and the Commission's rules the petition was untimely filed. Valley Rock and Sand Corp., 2 BNA MSHC 1673 (Docket No. WEST 80-3-M, March 29, 1982) (Order denying motion for reconsideration); Sunbeam Coal Corp., 2 FMSHRC 775 (1980).
~1621
Distribution
Thomas G. Martin, Esq.
1601 North Stone Avenue
Tucson, Arizona 85705
for William Haro
N. Douglas Grimwood, Esq.
Twitty, Sievwright & Mills
1700 TowneHouse Tower
100 West Clarendon
Phoenix, Arizona 85013
for Magma Copper Co.
Administrative Law Judge Jon D. Boltz
FMSHRC
333 West Colfax Ave.
Denver, Colorado 80204

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace