Secretary of Labor v. John Richards Construction (ALJ decision, July 23, 2014)
Secretary of Labor v. John Richards Construction (FMSHRC WEST 2011-129-M, WEST 2014-31-M): three citations settled for $150
Apply this to your situation
This order from 2014 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.
Plain-English summary
John Richards Construction contested three $100 citations involving a removed equipment guard, an equipment travel area that the company disputed was a mine roadway, and a temporary electrical splice. The operator asserted that the guard was removed for repairs, a spotter guided the equipment through the disputed area, and the pump with the temporary splice was unplugged while a permanent repair was on order. The Secretary retained each citation but agreed to cut each penalty to $50 because of conflicting evidence and litigation risk. Judge William B. Moran approved the $150 settlement after finding the supplied explanations adequate under the Mine Act's penalty criteria. He also rejected the Secretary's position that settlement motions need not provide a factual basis for compromised penalties.
Decision snapshot
- Cited standard(s): Not identified by number in the decision
- Outcome: Three unchanged citations were settled for $50 each, reducing total penalties from $300 to $150.
- Key point: A Mine Act settlement must provide enough factual explanation for the judge to evaluate the proposed penalty reductions under sections 110(i) and 110(k).
Full text (FMSHRC public release)
UNITED STATES OF AMERICA
UNITED STATES OF AMERICA
FEDERAL
MINE SAFETY AND HEALTH REVIEW COMMISSION
OFFICE OF ADMINISTRATIVE LAW JUDGES
1331 Pennsylvania Avenue NW, Suite 520N
Washington, DC 20004
Telephone: 202-434-9900 / Fax: 202-434-9949
July 23, 2014
SECRETARY OF LABOR, MINE SAFETY
AND HEALTH ADMINISTRATION
(MSHA)
Petitioner,
v.
JOHN RICHARDS CONSTRUCTION
Respondent.
)
)
)
)
)
)
)
)
)
)
CIVIL PENALTY PROCEEDINGS
DOCKET NO. WEST
2011-129-M
A.C. NO. 24-02070-2232297
DOCKET NO. WEST
2014-31-M
A.C. No.
24-02070-332585
Mine: Richards
Pit
DECISION APPROVING SETTLEMENT
Before: Judge Moran
This
case is before the Court upon a petition for assessment of a civil penalty under section 105(d) of the Federal Mine Safety and Health Act of 1977. The Secretary has filed a Motion to Approve Settlement. The original assessed amount was $300.00 and the proposed modified penalty amount is $150.00. This case had been set for a hearing which was to commence on July 10, 2014. Shortly before that date, the parties notified the Court that they had reached a settlement and the hearing was cancelled. The proposed settlement is set forth in the table below:
Citation Number
Proposed Penalty
Amended Penalty
WEST 2011-129
6458464
$100.00
$50.00
No modifications to the
citation; Reduce the proposed penalty
The
Secretary represents that the Respondent takes the position and would have alleged at hearing that the citation should be vacated because at the time of the inspection, the plant had not been in production for a year and that the guard had been removed to make repairs and that adjustments had to be made. In addition, Respondent would have argued that the guards were only removed to facilitate the repairs and Respondent would have replaced the guards once the adjustments were made. Respondent contends this was not a violation of the Mine Act.
The Secretary
reviewed the Citation, the surrounding evidence, and each party’s arguments. Without conceding Respondent’s arguments, but given the conflicting evidence and the associated litigation risk, the Secretary has agreed to a reduction of the proposed civil money penalty. Neither party admits that the arguments of the other party are correct.
WEST 2014-31M
8762608
$100.00
$50.00
No
modifications to the citation; Reduce the proposed penalty
The Secretary represents that the Respondent takes the position and would have alleged at hearing that the cited area was not a roadway. In addition, the Respondent contended that the citation should be vacated because the CAT 930G only traveled the cited area once and a spotter was used to help guide the equipment through the cited area. Respondent has also contended that this area was not part of the mine and was on a separate commercial area not subject to MSHA jurisdiction.
The Secretary reviewed the Citation, the surrounding evidence, and each party’s arguments. Without conceding Respondent’s arguments, but given the conflicting evidence and the associated litigation risk, the Secretary has agreed to a reduction of the proposed civil money penalty. Neither party admits that the arguments of the other party are correct.
8762609
$100.00
$50.00
No
modifications to the citation; Reduce the proposed penalty
The Secretary represents that the Respondent takes the position and would have alleged at hearing that the gravity was less than contended because the 120v well pump was not plugged in and the copper conductors were not exposed. Respondent would have argued the cited splice did not create an electrocution hazard. In addition, Respondent maintains that the splice was temporary, and it was performed to prevent miners from contacting the wires. Finally, Respondent would have argued that a permanent splice had been ordered to comply with MSHA requirements prior to the inspection. Once Respondent received the permanent splice, and prior to resuming production, it was installed.
The Secretary reviewed the Citation, the surrounding evidence, and each party’s arguments. Without conceding Respondent’s arguments, but given the conflicting evidence and the associated litigation risk, the Secretary has agreed to a reduction of the proposed civil money penalty. Neither party admits that the arguments of the other party are correct.
Total Amended Penalties:
$150.00
The Court accepts the representations and
modifications of the Secretary as set forth in the motion to approve settlement. However, the Court unequivocally rejects the Secretary’s claim in its motion that it need not supply a factual basis to the Court for any compromised, mitigated or settled proposed penalty as that stance is contrary to Congress’ express command at section 110(k) of the Mine Act. The Motion takes what has become the Secretary’s now routine approach of insisting that it need do no more than rely upon its pleadings together with a statement reflecting its changes but without any explanation to justify those changes. Then, within the same motion, the Secretary proceeds to provide the required information and thereby relents from its claim that the information need not be supplied. Viewing the reluctantly supplied justification, the Court then considered the representations supplied and finds that the modifications are reasonable and therefore concludes that the proposed settlement is appropriate under the criteria set forth in section 110(i) of the Act.
Accordingly, the motion to approve this settlement is GRANTED and the settlement amount of $150.00 is accepted as appropriate. The Court further notes that the parties agree that the Respondent has already recently paid the settlement amount of $150.00 associated with these two dockets.[1]
William B. Moran
William B. Moran
Administrative
Law Judge
Distribution:
Lauren A. Polk, Office of the Solicitor, 1999
Broadway, Suite 800, Denver, CO 80202
John Richards Construction, Attn:
John Richards, Owner2824 Hwy 83Seeley Lake, MT 59868
[1] On July 1, 2014,
Respondent mailed the agreed upon settlement amount of $150.00 to the MSHA U.S. Department of Labor Payment Office. Payment was received at the assessments office on July 3, 2014.
What applies to your situation today?
This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace