Parker-Northwest Paving Company (Commission decision, November 16, 2010)

Parker-Northwest Paving Company (FMSHRC WEST 2010-1074-M, WEST 2011-72-M): One reopening time-barred, one inadequately explained

Decision type
Commission decision
Dockets
WEST 2010-1074-M, WEST 2011-72-M
Decided
November 16, 2010
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2010, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2010
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Parker-Northwest asked to reopen two final penalty assessments and generally admitted negligent handling without giving specific facts. The Commission denied reopening of Assessment No. 000177107 with prejudice because the company waited more than one year after it became final, exceeding Rule 60(b)'s limit for mistake or excusable neglect. It denied reopening of Assessment No. 000191325 without prejudice because Parker did not explain the missed contest or its six-month delay after a delinquency notice. Parker was allowed 30 days to file a detailed renewed request for the second assessment.

Decision snapshot

  • Governing provisions: 30 U.S.C. § 815(a) and 29 C.F.R. § 2700.1(b)
  • Outcome: One reopening request was denied with prejudice as untimely, and the other was denied without prejudice for lack of detail.
  • Key point: Rule 60(b) bars excusable-neglect relief after one year, while a timely request still must explain both the original default and any delay after notice.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

November 16, 2010

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

PARKER-NORTHWEST PAVING COMPANY

:

:

:

:

:

:

:

Docket No. WEST 2010-1074-M

A.C. No. 35-00497-191325

Docket No. WEST 2011-72-M

A.C. No. 35-00497-177107

BEFORE: Jordan, Chairman; Duffy, Young, Cohen, and Nakamura, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On April 20, 2010, the Commission received a request to reopen two penalty assessments issued to Parker-Northwest Paving Company (“Parker”) that became final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

On February 18, and July 15, 2009, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment Nos. 000177107 and 000191325, respectively, to Parker, proposing civil penalties for numerous citations. In its letter seeking reopening, Parker apologizes for “being negligent in the handling of the citations that we wished to contest and not following the correct MSHA procedures.”

The Secretary opposes Parker’s request to reopen both assessments. As to Assessment No. 000177107, she maintains that Parker did not seek reopening until April 20, 2010, over one year after the proposed assessment became a final order of the Commission on March 27, 2009. The Secretary argues that because the reopening request was filed more than one year after the penalty assessment became a final order, it should be denied. As to Assessment No. 000191325, she asserts that Parker’s explanation lacks sufficient detail as to why it failed to timely contest the assessments and therefore does not provide adequate grounds for reopening. The Secretary also notes that a delinquency notice was sent to the operator on October 8, 2009, but the operator waited more than six months to seek reopening.

Having reviewed Parker’s request to reopen and the Secretary’s responses thereto, we agree that Parker has failed to provide a sufficient basis for the Commission to reopen the penalty assessments. With respect to Assessment No. 000177107, which, according to MSHA’s records, was delivered on February 25, 2009, and became a final order on March 27, 2009, more than a year passed before the operator sought reopening with the Commission. Under Rule 60(b), any motion for relief must be made within a reasonable time, and in the case of mistake, inadvertence, or excusable neglect not more than one year after the order was entered. Fed. R. Civ. P. 60(b). The Commission denies requests for reopening that are brought more than a year after the order has become final. J S Sand & Gravel, Inc., 26 FMSHRC 795, 796 (Oct. 2004). Accordingly, we deny with prejudice the request to reopen Assessment No. 000177107.

As to Assessment No.000191325, Parker has failed to adequately explain its failure to timely contest the proposed assessments. Furthermore, Parker has failed to explain the circumstances surrounding its receipt of the October delinquency notice.

Accordingly, we
hereby deny without prejudice Parker’s request to reopen Assessment No. 000191325. FKZ Coal Inc., 29 FMSHRC 177, 178 (Apr. 2007); Petra Materials, 31 FMSHRC 47, 49 (Jan. 2009). The words “without prejudice” mean that Parker may submit another request to reopen Assessment No. 000191325.

Any amended or renewed request by Parker to reopen this
assessment must be filed within 30 days of this order. Any such request filed after that time will be denied with prejudice.


Mary Lu Jordan, Chairman


Michael F. Duffy, Commissioner


Michael G. Young, Commissioner


Robert F. Cohen, Jr., Commissioner


Patrick K. Nakamura, Commissioner

Distribution:

Duane Johnson

Parker-Northwest Paving Co.

24370 S. Hwy., 99E

Canby, OR 97013

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Melanie Garris, Acting Chief

Office of Civil Penalty Compliance, MSHA

U.S. Dept. of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace