Secretary of Labor v. Newmont USA Limited (Commission decision, July 31, 2009)

Secretary of Labor v. Newmont USA Limited (FMSHRC WEST 2009-395-M): Reopening denied after one-year limit expired

Decision type
Commission decision
Docket
WEST 2009-395-M
Decided
July 31, 2009
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2009
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Newmont mistakenly mailed a penalty contest with payment for a different citation instead of sending it to the proper MSHA address. After Treasury began collection, Newmont and collection counsel suspended the collection dispute but did not recognize that only the Commission could reopen the final order. The company filed its Commission request more than one year after the assessment became final. Because mistake-based relief under Rule 60(b)(1) must be sought within one year, the Commission denied reopening as untimely.

Decision snapshot

  • Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
  • Outcome: Reopening was denied because the motion was filed more than one year after finality.
  • Key point: Communications with collection counsel do not substitute for a timely Commission motion, and mistake-based relief has an absolute one-year limit.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

July 31, 2009

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

NEWMONT USA LIMITED

Docket No. WEST 2009-395-M

A.C. No. 26-02512-130423

BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On January 13, 2009, the Commission received a letter from Newmont USA Limited (“Newmont”) seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

On October 31, 2007, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000130423 to Newmont, proposing civil penalties for Citations Nos. 6394861 and 6342286. Newmont states that it paid the penalty for Citation No. 6342286 on November 26, 2007, but that it mistakenly mailed its contest of Citation No. 6394861 along with that payment, rather than sending the contest to a separate MSHA address. The operator states that on May 29, 2008, it received a Notice of Debt from the U.S. Department of Treasury. Newmont explains that on June 2, 2008, it faxed documents demonstrating that it had contested the citation to the counsel listed in the notice as handling the collection effort. On June 4, 2008, Newmont received a letter from that counsel stating that the collection matter was suspended until the dispute was reviewed. On November 10, 2008, Newmont contacted MSHA and was informed that the contest of the citation had not been received in a timely manner, and that the penalty had been referred to Treasury for collection.

The Secretary opposes Newmont’s request to reopen Proposed Assessment No. 000130423. She asserts that the penalty assessment became a final Commission order on December 7, 2007, and that the request to reopen was not received by the Commission until January 13, 2009. The Secretary maintains that because the operator filed its request more than one year after the assessment became a final order, the request should be denied. The Secretary further notes that on January 23, 2008, MSHA sent a delinquency notice to Newmont informing the operator that it had failed to timely contest the proposed penalty. The Secretary contends that Newmont failed to explain why, after it was informed that it had not contested the proposed penalty, it took so long to request reopening.

We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect.

See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also held that a Rule 60(b) motion shall be made within a reasonable time, and for reasons (1), (2), and (3) not more than one year after the judgment, order, or proceeding was entered or taken.

Celite Corp., 18 FMSHRC 105, 106 (Apr. 2006) (citations and quotations omitted).

Here, we have been presented with Newmont’s failure to timely contest Proposed Assessment No. 000130423 due to its mistake in sending its contest to an incorrect address, followed by a communication between Newmont and counsel in charge of the collection action where both apparently failed to realize that the only remedy available to Newmont was for the Commission to reopen the order that had gone final, and then only for good cause and subject to the time limits set forth in Rule 60(c). This misunderstanding falls squarely within the ambit of Rule 60(b)(1). See Celite, 18 FMSHRC at 107.

Because Newmont waited over a year to request relief with regard to Proposed Assessment No. 000130423, its motion is untimely. J S Sand & Gravel, Inc., 26 FMSHRC 795, 796 (Oct. 2004). Accordingly, we deny Newmont’s request to reopen.

______

Michael F. Duffy, Chairman

______

Mary Lu Jordan, Commissioner

______

Michael G. Young, Commissioner

______

Robert F. Cohen, Jr., Commissioner 

Distribution:

Richard Tucker

Compliance & Safety

Newmont Mining Corporation

P.O. Box 669

Carlin, NV 89822-0669

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Myra James, Chief

Office of Civil Penalty Compliance, MSHA

U.S. Dept. of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace