Alaska Mechanical, Inc. (Commission decision, January 22, 2009)
Alaska Mechanical, Inc. (FMSHRC WEST 2008-1582-M): Disputed contest deadline remanded for fact-finding
Apply this precedent to your situation
This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Alaska Mechanical asked to reopen a proposed penalty assessment covering two citations. The company said it received the assessment on August 11 and that Federal Express delivered its contest on the September 10 deadline. MSHA's records instead showed receipt on August 8, which would make the September 9 filing one day late. Because the record did not establish the assessment's actual delivery date, the Commission could not determine whether a final order existed. It remanded for the Chief ALJ to decide timeliness and, if the contest was late, whether good cause justified reopening.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The matter was remanded to determine whether the penalty contest was timely and, if not, whether reopening was warranted.
- Key point: A factual dispute about when an operator received an assessment must be resolved before the Commission can determine whether the contest deadline was missed.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
January 22, 2009
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
ALASKA MECHANICAL, INC.
:
:
:
:
:
:
:
Docket No. WEST 2008-1582-M
A.C. No. 50-01850-159018 LWI
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On September 25, 2008, the Commission received from Alaska Mechanical, Inc. (“Alaska Mechanical”) a motion by counsel seeking to reopen a penalty assessment that may have become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On October 4, 2007, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Citation Nos. 6398234 and 6398235 to Alaska Mechanical. Alaska Mechanical contested the citations, which are the subject of Docket Nos. WEST 2008-152-RM and WEST 2008-153-RM and are currently stayed. The operator states that it received Proposed Assessment No. 000159018, which proposed civil penalties for the citations, on August 11, 2008, and thus its deadline for contesting the penalties was September 10, 2008. Alaska Mechanical further states that it sent its contest by Federal Express priority delivery on September 9, and that, contrary to the assertion in MSHA’s delinquency notice that MSHA received the contest on September 12, a tracking slip indicates that MSHA received the contest on September 10. Alaska asserts that it timely submitted its contest and that MSHA miscalculated applicable deadlines.
The Secretary states that she does not oppose Alaska Mechanical’s request to reopen. She notes, however, that MSHA records show that the operator received the proposed penalty assessment on August 8, 2008. She asserts that the operator’s contest filed on September 9 was filed one day late.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
On the record presently before us, we are unable to determine whether Alaska Mechanical timely contested the proposed penalty assessment. Specifically, it is unclear on what date (August 8 or August 11, 2008) Alaska Mechanical received the proposed penalty assessment.
If the company timely contested the proposed assessment, the proposed assessment has not become a final order of the Commission and the company’s request for relief would be moot. DS Mine & Dev. LLC, 28 FMSHRC 462, 463 (July 2006).
Accordingly, we remand this matter to the Chief Administrative Law Judge for a determination of whether Alaska Mechanical timely contested the proposed penalty assessment at issue. If it is determined that the company did file a timely contest, the Chief Judge shall order further proceedings as appropriate pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. If it is determined that Palmer failed to timely contest the proposed assessment, the Chief Judge shall determine whether good cause exists for granting relief from the final order. See Palmer Coking Coal Co., 30 FMSHRC ___, No. WEST 2008-934-M (Dec. 22, 2008).
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
______
Robert F. Cohen, Jr., Commissioner
Distribution:
Cole A. Wist
Baker & Hostetler, LLP
303 E. 17th Ave., Suite 1100
Denver, CO 80203
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor, Room 2220
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace