Cam Mining, LLC. (Commission decision, November 13, 2006)
Cam Mining, LLC. (FMSHRC WEST 2007-37): Missed contest after internal miscommunication remanded
Apply this precedent to your situation
This is citable Commission precedent from 2006, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Cam Mining received a proposed assessment covering eight citations and orders. A miscommunication between company personnel and counsel delayed delivery of the assessment to counsel until after the contest deadline. Cam asked to reopen the final assessment based on inadvertence or mistake, and the Secretary did not oppose the request. The Commission remanded for the chief judge to determine whether Cam had good cause for missing the deadline and whether relief from the final order should be granted.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The reopening request was remanded for findings on good cause and possible relief from the final penalty order.
- Key point: An internal failure to route an assessment to counsel may support reopening if the operator proves good cause.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
November 13, 2006
SECRETARY OF LABOR
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
CAM MINING, LLC.
:
:
:
:
:
:
:
:
Docket No. WEST 2007-37
A.C. No. 05-03013-95774
BEFORE: Duffy, Chairman; Jordan and Young, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On October 19, 2006, the Commission received from Cam Mining, LLC. (“Cam”) a motion by counsel seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On August 15, 2006, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued a proposed penalty assessment to Cam resulting from eight citations and orders. Cam states that, due to a miscommunication between company personnel and counsel, the proposed assessment was not sent to counsel until after the deadline for filing a penalty contest had passed. Cam further states that, because of this inadvertence or mistake, it was unable to file the assessment form in a timely manner. The Secretary states that she does not oppose Cam’s motion to reopen the penalty assessment.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Cam’s request, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Cam’s failure to timely contest the penalty proposal and whether relief from the final order should be granted. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
Distribution
Karen L. Johnston, Esq.
Jackson Kelly PLLC
1099 18th Street, Suite 2150
Denver, CO 80202
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace