Fann Contracting, Inc. (Commission decision, April 5, 2007)
Fann Contracting, Inc. (FMSHRC WEST 2007-283-M): Claimed timely penalty contest remanded for review
Apply this precedent to your situation
This is citable Commission precedent from 2007, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Fann Contracting asked the Commission to reopen a penalty assessment that had become final. The company said it received the assessment on June 26, 2006, mailed its contest on July 24, and MSHA received it on July 26, but no hearing followed. The Secretary did not oppose reopening. The Commission remanded for the chief administrative law judge to determine whether the contest was timely and, if not, whether good cause supported relief from the final order.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The reopening request was remanded for findings on timeliness and, if necessary, good cause.
- Key point: When an operator claims MSHA received a timely penalty contest, the filing history must be resolved before the final assessment remains in force.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
April 5, 2007
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
FANN CONTRACTING, INC.
:
:
:
:
:
:
:
:
Docket No. WEST 2007-283-M
A.C. No. 02-03016-91269
BEFORE: Duffy, Chairman; Jordan and Young, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On March 14, 2007, the Commission received from Fann Contracting, Inc. (“Fann”) a letter by counsel seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
Fann states that it received a proposed penalty assessment on June 26, 2006. It asserts that on July 24, 2006, it timely sent its contest of the proposed penalty assessment to the Department of Labor’s Mine Safety and Health Administration (“MSHA”). Fann contends that, although MSHA received its contest on July 26, the operator was not granted a hearing on the contested proposed penalties. The Secretary of Labor states that she does not oppose Fann’s request to reopen the penalty assessment.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Fann’s request, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether Fann timely contested the penalty proposal and, if not, whether good cause exists for granting relief from the final order. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
Distribution
Tophas Anderson, IV, Esq.
Jennings, Haug & Cunningham, LLP
2800 North Avenue, Suite 1800
Phoenix, AZ 85004-1049
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor
Arlington, VA 22209
Myra James, Chief
Office of Civil Penalty, MSHA
U.S. Department of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety and Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace