Grangeville Transit Mix, Inc. (Commission decision, February 1, 2007)

Grangeville Transit Mix, Inc. (FMSHRC WEST 2007-134-M through WEST 2007-137-M): Four assessments sent for good-cause review

Decision type
Commission decision
Dockets
WEST 2007-134-M, WEST 2007-135-M, WEST 2007-136-M, WEST 2007-137-M
Decided
February 1, 2007
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-08-09

Apply this precedent to your situation

This is citable Commission precedent from 2007, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2007
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Grangeville Transit Mix failed to timely contest four separate MSHA penalty assessments issued during 2006. It first explained that one contest form had been mailed to the wrong address, then said its foreman had not received some citations and proposed penalties and that the company misunderstood MSHA's procedures. The Secretary ultimately did not oppose reopening any of the four assessments. The Commission remanded the matters for a judge to determine whether Grangeville had good cause for each missed deadline and whether relief from the final orders should be granted.

Decision snapshot

  • Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
  • Outcome: Four reopening requests were remanded for good-cause determinations.
  • Key point: A judge must evaluate whether mailing errors, missing notices, and procedural misunderstandings establish good cause for reopening final assessments.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

February 1, 2007

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

GRANGEVILLE TRANSIT MIX, INC.

:

:

:

:

:

:

:

:

:

:

:

Docket No. WEST 2007-134-M
A.C. No. 10-02063-77188

Docket No. WEST 2007-135-M
A.C. No. 10-02063-87813

Docket No. WEST 2007-136-M
A.C. No. 10-02063-93037

Docket No. WEST 2007-137-M
A.C. No. 10-02063-95511

BEFORE: Duffy, Chairman; Jordan and Young, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”).

On December 14, 2006, the Commission received a letter
from Grangeville Transit Mix, Inc. (“Grangeville”) requesting that the Commission reopen four penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

Between January 2006 and August 2006, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) sent four separate proposed penalty assessments to the operator. None of the proposed assessments was timely contested. Each of the assessments therefore became a final Commission order.

Grangeville’s original letter of December 14, 2006, attached only one of the four assessments that had become final Commission orders, and with respect to that assessment (A.C. No. 10-02063-95511), Grangeville stated it had tried to timely contest the assessment, but had sent the contest form to the wrong address. The Secretary responded to the letter by stating that, while she did not oppose reopening of that assessment, she could not take a position on the reopening of the other three assessments until Grangeville explained why it believes reopening of those three assessments is also warranted.

Grangeville subsequently submitted a second letter, dated January 14, 2007, stating that its foreman did not receive some of the citations and proposed penalties at issue in the four assessments, and that it misunderstood the MSHA enforcement procedures in this instance. In response, the Secretary now states that she does not oppose Grangeville’s request to reopen all four penalty assessments.

We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Having reviewed Grangeville’s request, in the interests of justice, we remand these matters to the Chief Administrative Law Judge for a determination of whether good cause exists for Grangeville’s failure to timely contest the penalty proposals and whether relief from the final orders should be granted. If it is determined that such relief is appropriate, these cases shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.

______

Michael F. Duffy, Chairman

______

Mary Lu Jordan, Commissioner

______

Michael G. Young, Commissioner

Distribution

Mr. Max Nuxoll

Grangeville Transit Mix

P.O. Box 175

Grangeville, ID 83530

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., 22nd Floor

Arlington, VA 22209-2296

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace