Westmoreland Coal Company (Commission decision, March 1, 1989)

Westmoreland Coal Company (FMSHRC VA 89-17): Penalty-payment dispute remanded

Decision type
Commission decision
Docket
VA 89-17
Decided
March 1, 1989
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-08-17

Apply this precedent to your situation

This is citable Commission precedent from 1989, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1989
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
The Commission vacated the dismissal of Westmoreland's case and sent it back to determine whether its penalty payment was mistaken and what relief was appropriate. This order did not decide the citation. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Transcribed from a scanned original: FMSHRC released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (fmshrc.gov)

Plain-English summary

Westmoreland Coal paid an $85 civil penalty. An ALJ then approved a settlement and dismissed the case based on that payment. The company later said the payment was a mistake and asked that the dismissal be reopened so it could contest the violation. The Commission treated the company's letters as a petition for discretionary review, vacated the ALJ's dismissal, and remanded for further proceedings. The Commission stated that more information was needed to determine whether the payment was a genuine mistake.

Decision snapshot

  • Cited standard(s): 30 C.F.R. § 75.203; 29 C.F.R. §§ 2700.65(c) and 2700.70(a); 30 U.S.C. §§ 814(a), 816, and 823(d)(2)(A)(i).
  • Outcome: The ALJ's dismissal was vacated and the matter was remanded for proceedings consistent with the Commission's order.
  • Key point: Payment of a civil penalty generally ends an operator's right to contest the violation, but a genuine mistake may preserve that right if proven.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY & HEALTH REVIEW COMMISSION WASHINGTON, D.C.
March 1, 1989

SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)

v. Docket No. VA 89-17

WESTMORELAND COAL COMPANY

BEFORE: Ford, Chairman; Backley, Doyle, Lastowka and Nelson, Commissioners

ORDER

BY THE COMMISSION:

In this civil penalty proceeding arising under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (1982), Commission Administrative Law Judge William Fauver issued a Decision Approving Settlement on February 3, 1989. After noting that Westmoreland Coal Company ("Westmoreland") had paid the civil penalty proposed for the violation in issue, the judge granted a dismissal request from the Secretary of Labor and dismissed the proceeding. Subsequently, the judge received from counsel for Westmoreland letters stating that Westmoreland had mistakenly paid the civil penalty and requesting, in effect, that the judge's decision be vacated and the matter be reopened for further proceedings. We deem these letters to constitute a petition for discretionary review and, for the following reasons, we vacate the judge's decision and remand for further proceedings.

On November 9, 1988, an inspector of the Department of Labor's Mine Safety and Health Administration ("MSHA") issued to Westmoreland, at its Prescott No. 2 underground coal mine, a citation pursuant to section 104(a) of the Act, 30 U.S.C. § 814(a), alleging a violation of


Page 2

mandatory safety standard 30 C.F.R. § 75.203. 1/ On December 16, 1988,
_____
1/ Section 75.203(a), a mandatory safety standard for underground coal mines, provides:

The method of mining shall not expose any person to hazards caused by excessive widths of rooms,


Page 3

~276
the Secretary filed with the Commission a Petition for Assessment of Civil Penalty proposing an §85 penalty for the alleged violation. Westmoreland subsequently filed an Answer contesting the penalty and underlying violation. The matter was assigned to Judge Fauver, who issued a Prehearing Order on January 26, 1989, directing the parties to confer by February 21, 1989, for the purposes of discussing any possible settlement or stipulations.

By letter to Chief Administrative Law Judge Paul Merlin, dated January 26, 1989, and received by the Commission on January 30, 1989, counsel for the Secretary stated:

The operator in this case has paid the full amount of the penalty that was assessed, §85. As far as we are concerned, the case may now be dismissed.

On February 3, 1989 Judge Fauver issued his decision dismissing the case. He stated: Petitioner has moved to dismiss the case based upon full payment of the proposed civil penalty. I have considered the representations and documentation submitted and I conclude that the proffered settlement is consistent with the criteria in § 110(i) of the Act."

By letters to Judge Fauver dated February 1 and February 7, 1989, and received by the Commission on February 3 and February 9, respectively, counsel for Westmoreland stated that the civil penalty in question had been paid in error and requested that the matter not be dismissed and remain on the Commission's docket.

The judge's jurisdiction in this matter terminated when his decision issued on February 3, 1989. 29 C.F.R. § 2700.65(c). Under the Mine Act and the Commission's procedural rules, once a judge's decision has issued, relief from the decision may be sought by filing with the Commission a petition for discretionary review within 30 days of the decision. 30 U.S.C. § 823(d)(2)(A)(i), 29 C.F.R. 2700.70(a). Here, Westmoreland's letters are a request for relief from the judge's decision, and we will treat them as a petition for discretionary review.

A civil penalty under the Mine Act is predicated upon the existence of a violation. An operator cannot deny the existence of a violation for purposes connected with the Mine Act and at the same time pay a civil penalty. Therefore, the Commission has held that an operator's payment of a civil penalty proposed for a violation extinguishes the operator's right to contest the fact of violation.


Page 4

Old Ben Coal Co., 7 FMSHRC 205, 209 (February 1985). The Commission has also expressly noted, however, that where a civil penalty has been paid by genuine mistake, the operator's right to contest the violation may not be lost. Old Ben Coal Co., 7 FMSHRC at 210 n.6.
_______________
crosscuts and entries, or faulty pillar recovery methods. Pillar dimensions shall be compatible with effective control of the roof, face and ribs and coal or rock bursts.


Page 5

~277
The record does not contain sufficient information to permit us to determine whether Westmoreland's penalty payment was a "genuine mistake." Further proceedings may be necessary to address Westmoreland's assertions and for the judge to determine what relief, if any, is appropriate.

Accordingly, the judge's decision is vacated, and the matter is remanded for proceedings consistent with this order.

Ford B. Ford, Chairman

Richard V. Backley, Commissioner

Joyce A. Doyle, Commissioner

James A Lastowka, Commissioner

Clair Nelson, Commissioner

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace