Secretary of Labor v. Red River Coal Company (Commission decision, June 18, 2008)
Secretary of Labor v. Red River Coal Company (FMSHRC VA 2008-258): Disputed mailed contest remanded for factfinding
Apply this precedent to your situation
This is citable Commission precedent from 2008, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Red River Coal said it mailed its penalty contest within 30 days, but MSHA had no record of receiving it and later notified the company that the assessment had not been timely contested. The Secretary did not oppose reopening. The Commission remanded for findings on whether Red River timely contested and, if it did not, whether good cause warranted relief from the final order.
Decision snapshot
- Cited authority: 30 U.S.C. § 815(a); 29 C.F.R. § 2700.1(b)
- Outcome: The matter was remanded to determine timeliness and, if necessary, good cause for reopening.
- Key point: A factual dispute between an operator's claimed mailing and MSHA's nonreceipt requires factfinding before the Commission can determine finality or grant relief.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
June 18, 2008
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
RED RIVER COAL COMPANY
:
:
:
:
:
:
:
Docket No. VA 2008-258
A.C. No. 44-06199-135474
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On May 1, 2008, the Commission received from Red River Coal Company, Inc. (“Red River”) a letter seeking to reopen a penalty assessment that may have become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On January 8, 2008, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000135474 to Red River, which proposed civil penalties for several citations. Red River states that it mailed its contest of the proposed assessment on February 5, 2008, but that it did not receive a response from MSHA until it received a letter from MSHA dated April 9, 2008, stating that Red River had failed to timely contest the proposed assessment. While the Secretary states that she does not oppose Red River’s request to reopen, she notes that she has no record of receiving Red River’s contest of the penalty assessment.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Red River’s request and the Secretary’s response, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether Red River timely contested the penalty proposal and, if not, whether good cause exists for granting relief from the final order. If it is determined that relief from the final order is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
______
Robert F. Cohen, Jr., Commissioner
Distribution:
Karen L. Johnston, Esq.
Jackson Kelly PLLC
1099 18th Street
Suite 2150
Denver, CO 80202
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance, MSHA
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace